9042 N LEDGE AVE 91352
Certificate Information: 9042 N LEDGE AVE 91352
- Application / Permit
- 19010-20000-00631
- Plan Check / Job No.
- B19VN02309
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-4" X 40'-9" DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 11/22/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2019 | JENNIFER LEE |
| Corrections Issued | 2/25/2019 | JENNIFER LEE |
| Quality Review Completed | 2/26/2019 | STEVEN KIM |
| Building Plans Picked Up | 2/26/2019 | APPLICANT |
| Green Plans Picked Up | 3/4/2019 | APPLICANT |
| Applicant returned to address corrections | 10/22/2019 | JENNIFER LEE |
| Plan Check Approved | 11/21/2019 | JENNIFER LEE |
| Issued | 11/22/2019 | LADBS |
| CofO in Progress | 5/28/2025 | DAVID ANDERSON |
| CofO Issued | 6/9/2025 | RUBEN SALAS |
| Permit Finaled | 6/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2019 | JOHN LIN |
| Sewer availability | Cleared | 7/12/2019 | JOHN LIN |
| Green Code | Cleared | 8/12/2019 | MICHAEL AYERS |
| Specific Plan | Cleared | 9/4/2019 | PEGGY MALONE-BROWN |
| Low Impact Development | Cleared | 10/1/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/1/2019 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 10/22/2019 | JENNIFER LEE |
| ZA Case | Cleared | 10/23/2019 | HERMINIGILDO AGUSTIN |
| GPI Written Notices | Cleared | 11/21/2019 | JENNIFER LEE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/27/2019 | Approved | BEAU COLLINS |
| Sewer | 2/11/2020 | Partial Inspection | BEAU COLLINS |
| Interior/Exterior Lathing | 6/5/2020 | Approved | BEAU COLLINS |
| Sewer | 6/30/2020 | Partial Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 8/18/2020 | Conditional Approval | BEAU COLLINS |
| ELECTRICAL-Rough | 8/18/2020 | Conditional Approval | BEAU COLLINS |
| Green Building Rough | 8/18/2020 | Not Ready for Inspection | BEAU COLLINS |
| PLUMBING-Rough | 8/18/2020 | Partial Approval | BEAU COLLINS |
| Verify Sprinkler Sign Off | 8/18/2020 | Approved | BEAU COLLINS |
| Insulation | 8/24/2020 | Approved | BEAU COLLINS |
| Drywall Nailing | 9/8/2020 | Partial Approval | PIERRE VEGA |
| Gas Test | 9/8/2020 | Not Ready for Inspection | PIERRE VEGA |
| Green Building Rough | 9/8/2020 | Not Ready for Inspection | PIERRE VEGA |
| Gas Test | 9/10/2020 | Partial Approval | BEAU COLLINS |
| Interior/Exterior Lathing | 9/29/2020 | Approved | JOHN HAYES |
| Shower Pan | 9/29/2020 | Approved | JOHN HAYES |
| Underground Mechanical | 11/25/2020 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/23/2020 | Approved | BEAU COLLINS |
| Drywall Nailing | 12/23/2020 | Approved | BEAU COLLINS |
| Final | 12/23/2020 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 12/23/2020 | Approved | BEAU COLLINS |
| Green Building Rough | 12/23/2020 | Approved | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Not Ready | BEAU COLLINS |
| Final | 2/25/2021 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 2/25/2021 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 2/25/2021 | SGSOV Not Ready | BEAU COLLINS |
| Service/Power Release | 2/25/2021 | Corrections Issued | BEAU COLLINS |
| Smoke Detectors | 2/25/2021 | Approved | BEAU COLLINS |
| Special/Order Compliance | 3/2/2021 | Corrections Issued | BEAU COLLINS |
| Final | 7/27/2021 | Corrections Issued | WILLIAM KUEHN |
| Green Building Final | 7/27/2021 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Approved | WILLIAM KUEHN |
| Service/Power Release | 7/27/2021 | Not Required | WILLIAM KUEHN |
| Pre-Inspection | 4/29/2025 | Corrections Issued | JOSE AVILA |
| Final | 5/20/2025 | Corrections Issued | DAVID ANDERSON |
| Final | 5/27/2025 | OK to Issue CofO | DAVID ANDERSON |