8620 W OLIN ST UNIT-C 90034

Certificate Information: 8620 W OLIN ST UNIT-C 90034

Application / Permit
19010-20000-00574
Plan Check / Job No.
B19VN02083
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
"Small lot subdivision pursuant to Tentative Tract No./Preliminary Parcel Map No. VTT-78244-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded." NEW 4-STORY 35'-6" X 25'-9 1/2" SFD WITH ATT. 2-CAR GARAGE, PLAN 'B'; FIRE SPRINKLERS REQ'D THROUGH-OUT (PER VTT-78244-SL). -struct inv.
Permit Issued
Issued on 8/28/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2019 APPLICANT
Assigned to Plan Check Engineer 3/7/2019 ALEXANDER SBARDELLATI
Corrections Issued 3/14/2019 ALEXANDER SBARDELLATI
Green Plans Picked Up 3/22/2019 APPLICANT
Quality Review Completed 3/28/2019 CHON CHIO KUO
Building Plans Picked Up 4/1/2019 APPLICANT
Applicant returned to address corrections 7/10/2019 RODNEY SAMIIAN
Applicant returned to address corrections 7/23/2019 RODNEY SAMIIAN
Applicant returned to address corrections 7/24/2019 RODNEY SAMIIAN
Plan Check Approved 8/28/2019 BINH PHAN
Issued 8/28/2019 LADBS
CofO in Progress 9/29/2022 EVAN COOPER
Permit Finaled 10/13/2022 DANIEL ORRANTE
CofO Issued 10/13/2022 DANIEL ORRANTE
Permit Finaled 10/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 6/13/2019 MARTIN FRAGOSO
Address approval Cleared 7/3/2019 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 7/3/2019 JAMES KHO
Miscellaneous Cleared 7/3/2019 JAMES KHO
Permit Cleared 7/3/2019 JAMES KHO
Roof/Waste drainage to street Cleared 7/3/2019 JAMES KHO
Sewer availability Cleared 7/3/2019 JAMES KHO
Green Code Cleared 7/19/2019 MICHAEL AYERS
Highway dedication Cleared 7/19/2019 ELAINE LEI
Hydrant and Access approval Cleared 7/19/2019 JEREMY CARTER
Miscellaneous Cleared 7/23/2019 DAISY BENICIA
Tract Map conditions Cleared 7/23/2019 DAISY BENICIA
Trees in Parkway Cleared 7/23/2019 JOHN KIM
ZI Cleared 7/23/2019 DAISY BENICIA
Frnt yard landscape/Water mgmt Cleared 7/29/2019 HERMINIGILDO AGUSTIN

Contact Information

Architect Brumer,, Aaron Jason; Lic. No.: C30005 10999 RIVERSIDE DRIVE SUITE 300      STUDIO CITY, CA 91602
Contractor Free Creation Inc; Lic. No.: 1003352-B 8019 SALE AVENUE      CANOGA PARK, CA 91304
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 15038 CLARK AVE      HACIENDA HEIGHTS, CA 91745

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/23/2019 Partial Approval EVAN COOPER
Deputy Steel/Welding 3/5/2020 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 3/9/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Corrections Issued CRAIG DAVIS
Wood Frame 8/11/2020 Partial Approval EVAN COOPER
Wood Frame 11/6/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 4/6/2021 Approved EVAN COOPER
HVAC-Rough 4/6/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 4/6/2021 Not Ready for Inspection EVAN COOPER
Shower Pan 4/6/2021 Approved EVAN COOPER
HVAC-Rough 4/16/2021 Approved EVAN COOPER
Interior/Exterior Lathing 4/16/2021 Approved EVAN COOPER
PLUMBING-Rough 4/16/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Approved EVAN COOPER
Insulation 5/3/2021 Approved EVAN COOPER
Drywall Nailing 5/19/2021 Approved EVAN COOPER
Green Building Rough 5/19/2021 Approved EVAN COOPER
Gas Test 11/9/2021 Approved EVAN COOPER
ELECTRICAL-Final 7/11/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Final 7/21/2022 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 7/25/2022 Approved EVAN COOPER
HVAC-Final 7/25/2022 Corrections Issued EVAN COOPER
PLUMBING-Final 7/25/2022 Corrections Issued EVAN COOPER
Service/Power Release 8/5/2022 Approved KENNETH NAGLE
BUILDING-Rough-Frame 8/9/2022 Approved EVAN COOPER
Final 8/9/2022 Corrections Issued EVAN COOPER
Green Building Final 8/9/2022 Approved EVAN COOPER
HVAC-Final 8/9/2022 Approved EVAN COOPER
MERV13>=Final 8/9/2022 Approved EVAN COOPER
MERV13>=Rough 8/9/2022 Approved EVAN COOPER
PLUMBING-Final 8/9/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Not Ready EVAN COOPER
Smoke Detectors 8/9/2022 Approved EVAN COOPER
Structural Steel Frame 8/9/2022 Approved EVAN COOPER
Verify Sprinkler Sign Off 8/9/2022 Approved EVAN COOPER
Service/Power Release 8/31/2022 Approved EVAN COOPER
Final 9/19/2022 Not Ready for Inspection ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Not Ready ANDREW NAVE
Final 9/22/2022 Conditional Approval EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Approved EVAN COOPER
Final 9/29/2022 OK to Issue CofO EVAN COOPER