15429 W SAN JOSE ST 91345

Certificate Information: 15429 W SAN JOSE ST 91345

Application / Permit
19010-20000-00564
Plan Check / Job No.
B19VN02034
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'-4" X 35'-4" 2-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 W/ 7'-8" X 9'-8" TRELLIS AND 4'-0" X 9'-8" REAR PORCH. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2019 APPLICANT
Assigned to Plan Check Engineer 2/14/2019 JENNIFER LEE
Corrections Issued 2/19/2019 JENNIFER LEE
Quality Review Completed 2/20/2019 STEVEN KIM
Building Plans Picked Up 2/25/2019 APPLICANT
Green Plans Picked Up 3/1/2019 APPLICANT
Applicant returned to address corrections 10/2/2019 JENNIFER LEE
Plan Check Approved 2/3/2020 JENNIFER LEE
Issued 9/15/2022 APPLICANT
CofO in Progress 9/19/2023 JENNIFER RABUCHIN
Permit Finaled 9/20/2023 RUBEN SALAS
CofO Issued 9/20/2023 RUBEN SALAS
Permit Finaled 9/20/2023 RUBEN SALAS

Permit Application Clearance Information

Green Code Cleared 4/3/2019 PARISA ZAHABI
Hydrant and Access approval Cleared 4/4/2019 ROBERT DUFF
Low Impact Development Cleared 9/11/2019 JORGE MEJIA LEMUS
Address approval Cleared 1/23/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/23/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/23/2020 ADRIAN CASTRO
Sewer availability Cleared 1/23/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/9/2023 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 2/21/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/3/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/3/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/10/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/14/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/14/2023 Approved JENNIFER RABUCHIN
Green Building Rough 4/14/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 4/14/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 4/14/2023 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 4/14/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/18/2023 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 4/21/2023 Approved JENNIFER RABUCHIN
Insulation 4/21/2023 Approved JENNIFER RABUCHIN
Shower Pan 4/21/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 4/27/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/27/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/23/2023 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 9/1/2023 Corrections Issued JENNIFER RABUCHIN
Final 9/1/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 9/1/2023 Approved JENNIFER RABUCHIN
Green Building Final 9/1/2023 Approved JENNIFER RABUCHIN
HVAC-Final 9/1/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 9/1/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 9/1/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 9/1/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/11/2023 Approved ROBERT GOLD
Final 9/11/2023 OK to Issue CofO ROBERT GOLD
Gas Test 9/11/2023 Approved ROBERT GOLD
HVAC-Final 9/11/2023 Approved ROBERT GOLD
PLUMBING-Final 9/11/2023 Approved ROBERT GOLD
Service/Power Release 9/11/2023 Not Required ROBERT GOLD