12758 W MUSCATINE ST 91331

Certificate Information: 12758 W MUSCATINE ST 91331

Application / Permit
19010-20000-00562
Plan Check / Job No.
B19VN02008
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'-6" x 28'-0" DETACHED TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 9/15/2023
Issuing Office
Current Status
CofO Issued on 9/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2019 APPLICANT
Assigned to Plan Check Engineer 2/28/2019 SARKIS HARABEDIAN
Corrections Issued 3/4/2019 SARKIS HARABEDIAN
Quality Review Completed 3/11/2019 OMID HEDAYAT
Building Plans Picked Up 3/12/2019 APPLICANT
Green Plans Picked Up 3/19/2019 APPLICANT
Applicant returned to address corrections 9/6/2023 SARKIS HARABEDIAN
Plan Check Approved 9/15/2023 SARKIS HARABEDIAN
Issued 9/15/2023 APPLICANT
CofO in Progress 9/13/2024 MATTHEW NELSON
Permit Finaled 9/21/2024 DANIEL ORRANTE
CofO Issued 9/21/2024 DANIEL ORRANTE
Permit Finaled 9/21/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 11/14/2019 RIDWAN HARDY
Address approval Cleared 2/24/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/25/2023 CARLOS AGUILERA
Sewer availability Cleared 4/25/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/15/2023 KURT CORRAL
Low Impact Development Cleared 8/18/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 8/22/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2023 Corrections Issued DAVID ANDERSON
Underground Mechanical 9/19/2023 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 9/26/2023 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 9/26/2023 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 9/26/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 11/6/2023 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/6/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 11/6/2023 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 11/6/2023 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/6/2023 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 11/6/2023 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 11/6/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/8/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/8/2023 Approved CHRISTOPHER ROJAS
Green Building Rough 11/8/2023 Approved CHRISTOPHER ROJAS
HVAC-Rough 11/8/2023 Approved CHRISTOPHER ROJAS
Insulation 11/14/2023 Corrections Issued JENNIFER RABUCHIN
Shower Pan 11/14/2023 Approved JENNIFER RABUCHIN
Insulation 11/17/2023 Corrections Issued CHRISTOPHER ROJAS
Insulation 12/19/2023 Approved RYAN SALAZAR
Insulation 12/20/2023 Not Ready for Inspection MATTHEW NELSON
Drywall Nailing 12/27/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/27/2023 Approved MATTHEW NELSON
Gas Test 3/1/2024 Approved MATTHEW NELSON
Sewer 3/1/2024 Approved MATTHEW NELSON
Final 9/6/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 9/6/2024 Approved MATTHEW NELSON
Green Building Final 9/6/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 9/6/2024 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 9/6/2024 Approved MATTHEW NELSON
Final 9/12/2024 OK to Issue CofO MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Approved MATTHEW NELSON
Service/Power Release 9/12/2024 Approved MATTHEW NELSON