12758 W MUSCATINE ST 91331
Certificate Information: 12758 W MUSCATINE ST 91331
- Application / Permit
- 19010-20000-00562
- Plan Check / Job No.
- B19VN02008
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21'-6" x 28'-0" DETACHED TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Current Status
- CofO Issued on 9/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2019 | SARKIS HARABEDIAN |
| Corrections Issued | 3/4/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 3/11/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 3/12/2019 | APPLICANT |
| Green Plans Picked Up | 3/19/2019 | APPLICANT |
| Applicant returned to address corrections | 9/6/2023 | SARKIS HARABEDIAN |
| Plan Check Approved | 9/15/2023 | SARKIS HARABEDIAN |
| Issued | 9/15/2023 | APPLICANT |
| CofO in Progress | 9/13/2024 | MATTHEW NELSON |
| Permit Finaled | 9/21/2024 | DANIEL ORRANTE |
| CofO Issued | 9/21/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/21/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/14/2019 | RIDWAN HARDY |
| Address approval | Cleared | 2/24/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/25/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 7/15/2023 | KURT CORRAL |
| Low Impact Development | Cleared | 8/18/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 8/22/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2023 | Corrections Issued | DAVID ANDERSON |
| Underground Mechanical | 9/19/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/26/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 9/26/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 9/26/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/6/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/6/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 11/6/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/6/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/6/2023 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/6/2023 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 11/6/2023 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/8/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/8/2023 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/8/2023 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/8/2023 | Approved | CHRISTOPHER ROJAS |
| Insulation | 11/14/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 11/14/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/17/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Insulation | 12/19/2023 | Approved | RYAN SALAZAR |
| Insulation | 12/20/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 12/27/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/27/2023 | Approved | MATTHEW NELSON |
| Gas Test | 3/1/2024 | Approved | MATTHEW NELSON |
| Sewer | 3/1/2024 | Approved | MATTHEW NELSON |
| Final | 9/6/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/6/2024 | Approved | MATTHEW NELSON |
| Green Building Final | 9/6/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 9/6/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 9/6/2024 | Approved | MATTHEW NELSON |
| Final | 9/12/2024 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 9/12/2024 | Approved | MATTHEW NELSON |