8965-8967 N HERRICK AVE 91352

Certificate Information: 8965-8967 N HERRICK AVE 91352

Application / Permit
19010-20000-00511
Plan Check / Job No.
B19VN01832
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(8) Auto Repair Garage
Work Description
(N) AUTO BODY SHOP
Permit Issued
Issued on 1/3/2020
Issuing Office
Valley
Current Status
Issued on 1/3/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/5/2019 APPLICANT
Assigned to Plan Check Engineer 2/28/2019 CHON CHIO KUO
Disabled Access Plans Picked Up 3/4/2019 APPLICANT
Green Plans Picked Up 3/13/2019 APPLICANT
Corrections Issued 3/20/2019 CHON CHIO KUO
Quality Review Completed 3/22/2019 STEVEN KIM
Building Plans Picked Up 3/26/2019 APPLICANT
Applicant returned to address corrections 11/21/2019 CHON CHIO KUO
Plan Check Approved 12/20/2019 CHON CHIO KUO
Issued 1/3/2020 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/8/2019 LEE GUILBEAUX
Highway dedication Cleared 4/8/2019 LEE GUILBEAUX
Permit Cleared 4/8/2019 LEE GUILBEAUX
Sewer availability Cleared 4/8/2019 LEE GUILBEAUX
Automotive Use Cleared 9/9/2019 DAISY BENICIA
Hydrant and Access approval Cleared 9/9/2019 ROBERT DUFF
Prkng lot landscape/Water mgmt Cleared 9/9/2019 DAISY BENICIA
DAS Clearance Cleared 10/4/2019 CHON CHIO KUO
Automotive Use Cleared 11/5/2019 HERMINIGILDO AGUSTIN
Clean Up Green Up Cleared 11/5/2019 HERMINIGILDO AGUSTIN
Green Code Cleared 11/19/2019 DAVID MATSON
Low Impact Development Cleared 11/21/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/21/2019 ADRIAN CASTRO
Food Service Establishment Cleared 11/27/2019 KENNETH BROWNE

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2020 Corrections Issued ROBERT DAVIS
Footing/Foundation/Slab 1/31/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/5/2020 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 3/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 3/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 3/25/2020 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 4/3/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 4/6/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 4/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 4/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 4/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 4/14/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/27/2020 Not Ready for Inspection ROBERT COLE
Masonry Wall/Backfill 5/27/2020 Corrections Issued ROBERT COLE
Verify Sprinkler Sign Off 5/27/2020 Not Ready for Inspection ROBERT COLE
Masonry Wall/Backfill 5/28/2020 Corrections Issued ROBERT COLE
Green Building Rough 5/29/2020 Not Ready for Inspection ROBERT COLE
Masonry Wall/Backfill 5/29/2020 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 5/29/2020 Not Ready for Inspection ROBERT COLE
Green Building Rough 6/3/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 6/3/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/3/2020 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 6/4/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 6/4/2020 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 6/9/2020 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/9/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 6/12/2020 Not Ready for Inspection ANDREW DORSO
Masonry Wall/Backfill 6/12/2020 Not Ready for Inspection ANDREW DORSO
Verify Sprinkler Sign Off 6/12/2020 Not Ready for Inspection ANDREW DORSO
Wall Anchors 6/13/2020 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 7/6/2020 Approved ANDREW DORSO
Green Building Rough 7/6/2020 Not Ready for Inspection ANDREW DORSO
Reinforced Masonry Frame 7/6/2020 Partial Inspection ANDREW DORSO
Wood Frame 7/6/2020 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 No Access for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/22/2021 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 2/23/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/23/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 2/23/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 6/24/2021 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/6/2021 Partial Inspection DANNY RODRIGUEZ
Pre-Inspection 7/30/2021 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 9/9/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 11/9/2021 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 11/9/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 11/9/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 11/30/2021 Partial Approval RICKEY JACKSON
Drywall Nailing 1/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 1/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 1/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 1/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/12/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 1/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Structural Steel Frame 1/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/12/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 1/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 3/11/2025 Not Ready for Inspection DANNY RODRIGUEZ