2908-2910 N ALLESANDRO ST #1-#36 90039

Certificate Information: 2908-2910 N ALLESANDRO ST #1-#36 90039

Application / Permit
19010-20000-00422
Plan Check / Job No.
B19VN01487
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
100% PDPP plan check for zoning, building, fire life-safety, green & ADA & structural: 36 unit mixed use live/work & retail building with 30% density bonus increase from 28 to 36 units with 5-units very low income units 3-incentice to increase building height , lot coverage .per DIR2019-2630-DB
Permit Issued
Issued on 3/15/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2019 CHON CHIO KUO
Disabled Access Plans Picked Up 2/7/2019 APPLICANT
Green Plans Picked Up 2/7/2019 APPLICANT
Corrections Issued 3/7/2019 CHON CHIO KUO
Quality Review Completed 3/8/2019 STEVEN KIM
Building Plans Picked Up 3/11/2019 APPLICANT
Applicant returned to address corrections 5/2/2019 CHON CHIO KUO
Applicant returned to address corrections 3/6/2020 CHON CHIO KUO
Applicant returned to address corrections 3/11/2021 CHON CHIO KUO
Plan Check Approved 3/15/2021 CHON CHIO KUO
Issued 3/15/2021 APPLICANT
TCO Issued (Expire Date: 12-11-2023) 6/14/2023 ERNESTO CORRAL
CofO in Progress 11/16/2023 RAFAEL ESPINOZA
CofO Issued 11/17/2023 ERNESTO CORRAL
Permit Finaled 11/17/2023 ERNESTO CORRAL

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/2/2019 GEORGE SUCHAND
Fire Marshall Fire Life Safety Cleared 7/12/2019 VIDAL GARCIA
Low Impact Development Cleared 1/14/2020 AMMAR ELTAWIL
Green Code Cleared 1/28/2020 MICHAEL AYERS
Address approval Cleared 3/18/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 3/18/2020 CECILIO NAVARRO
Highway dedication Cleared 3/18/2020 CECILIO NAVARRO
Permit Cleared 10/2/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 10/2/2020 JEANIE LAM
Sewer availability Cleared 10/20/2020 PAMELA TENEZA
"Q" conditions Cleared 11/10/2020 RUBEN VASQUEZ
Miscellaneous Cleared 11/10/2020 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 11/10/2020 RUBEN VASQUEZ
ZI Cleared 11/10/2020 RUBEN VASQUEZ
ZI Cleared 11/10/2020 RUBEN VASQUEZ
Density Bonus 12.22.A.25 Cleared 12/24/2020 LOUIE MILLER
Work Adjacent to Public Way Cleared 1/26/2021 BOK GOH
DAS Clearance Cleared 2/25/2021 CHON CHIO KUO
Miscellaneous Cleared 3/11/2021 CHON CHIO KUO
Building over 3-story or 36-ft Cleared 3/15/2021 CALOSHA APPROVED

Contact Information

Architect Capilouto,, Maurice Steven; Lic. No.: C24484 910 E PALMYRA AVE      ORANGE, CA 92866
Contractor J B Contractors Inc; Lic. No.: 797840-B 133 E BONITA AVE #201      SAN DIMAS, CA 91773
Engineer Morton,, Jeffery Scott; Lic. No.: C70507 8023 S BIG SPRING DR      WEST JORDAN, UT 84081
Engineer Varela,, Gregorio; Lic. No.: C81201 1108 S ADAMS ST      GLENDALE, CA 91205

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/23/2021 Approved MARK FERRARI
Deputy Reinf. Concrete 7/9/2021 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 7/9/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 7/19/2021 Conditional Approval LANNY MERRICK
Masonry Wall/Backfill 7/20/2021 Partial Approval JONATHAN QUACH
Masonry Wall/Backfill 7/22/2021 Not Ready for Inspection JONATHAN QUACH
Masonry Wall/Backfill 7/23/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Masonry 7/27/2021 Conditional Approval JONATHAN QUACH
Masonry Wall/Backfill 8/3/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 9/8/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Other (see comments) 9/21/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/30/2021 Partial Approval RAFAEL ESPINOZA
Deputy Other (see comments) 10/7/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 11/4/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Partial Approval RAFAEL ESPINOZA
Green Building Rough 11/4/2021 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/4/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 11/4/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 11/16/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 11/22/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 12/8/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/12/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/12/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/19/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/19/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/21/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/15/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wall Anchors 2/15/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/15/2022 Partial Approval RAFAEL ESPINOZA
Insulation 2/17/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Drilled-In Anchors 2/23/2022 Conditional Approval RAFAEL ESPINOZA
Insulation 2/24/2022 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 2/25/2022 Partial Approval RAFAEL ESPINOZA
Insulation 2/25/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/15/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/15/2022 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Partial Approval RAFAEL ESPINOZA
Insulation 4/8/2022 Partial Approval RAFAEL ESPINOZA
Insulation 4/12/2022 Partial Approval RAFAEL ESPINOZA
Insulation 4/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 4/27/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/27/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Wood Construction 5/9/2022 Conditional Approval RAFAEL ESPINOZA
Insulation 5/10/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/16/2022 Partial Inspection ERNESTO CORRAL
Insulation 5/16/2022 Partial Inspection ERNESTO CORRAL
Insulation 5/24/2022 Approved RAFAEL ESPINOZA
Drywall Nailing 5/27/2022 Partial Approval RAFAEL ESPINOZA
Insulation 6/3/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/9/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/15/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/28/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/30/2022 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 7/26/2022 Approved RAFAEL ESPINOZA
Deputy Wood Construction 8/26/2022 Conditional Approval WINSTON DUNNING
Green Building Final 12/20/2022 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 12/20/2022 Approved RAFAEL ESPINOZA
Final 1/11/2023 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 1/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Final 1/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 1/11/2023 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 1/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 1/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
Final 2/9/2023 Corrections Issued RAFAEL ESPINOZA
Special/Order Compliance 2/21/2023 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 2/28/2023 Partial Inspection RAFAEL ESPINOZA
Final 4/24/2023 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 4/24/2023 Approved RAFAEL ESPINOZA
Green Building Final 4/24/2023 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 4/24/2023 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 4/24/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/24/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 4/24/2023 Partial Approval RAFAEL ESPINOZA
Final 5/16/2023 Partial Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 5/16/2023 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 5/16/2023 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 5/16/2023 Approved RAFAEL ESPINOZA
Verify Rec and Parks Fee Memo 5/16/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/16/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 5/16/2023 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 5/24/2023 Partial Inspection RAFAEL ESPINOZA
Final 6/1/2023 Partial Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 6/1/2023 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/1/2023 Approved RAFAEL ESPINOZA
Wood Frame 6/1/2023 Approved RAFAEL ESPINOZA
Deputy Wood Construction 6/7/2023 Conditional Approval RAFAEL ESPINOZA
Special/Order Compliance 11/15/2023 Approved RAFAEL ESPINOZA
Final 11/16/2023 OK to Issue CofO RAFAEL ESPINOZA