13263 N WHEELER AVE UNIT 6 91342

Certificate Information: 13263 N WHEELER AVE UNIT 6 91342

Application / Permit
19010-20000-00375
Plan Check / Job No.
B19VN01394
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(35) Condo-Single Family
Work Description
NEW 2-STORY, SINGLE FAMILY CONDO UNIT W/ ATTACHED 2-CAR GARAGE & PORCH PER PLAN 1A, FIRE SPRINKLERS REQ'D THROUGH-OUT (PER TT-63084-CN).
Permit Issued
Issued on 9/12/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2019 APPLICANT
Green Plans Picked Up 2/6/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2019 ALEXANDER SBARDELLATI
Corrections Issued 2/20/2019 ALEXANDER SBARDELLATI
Quality Review Completed 2/21/2019 CHON CHIO KUO
Building Plans Picked Up 2/22/2019 APPLICANT
Applicant returned to address corrections 5/14/2019 ALEXANDER SBARDELLATI
Applicant returned to address corrections 7/8/2019 RODNEY SAMIIAN
Applicant returned to address corrections 8/1/2019 RODNEY SAMIIAN
Applicant returned to address corrections 8/5/2019 RODNEY SAMIIAN
Plan Check Approved 9/12/2019 RODNEY SAMIIAN
Issued 9/12/2019 LADBS
TCO Issued (Expire Date: 08-31-2020) 3/4/2020 MICHAEL SMITH
CofO in Progress 10/6/2020 JOSEPH SAGEN
No Progress 10/7/2020 JOSEPH SAGEN
CofO in Progress 10/7/2020 DONALD SUNSERI
CofO in Progress 10/13/2020 JOSEPH SAGEN
Permit Finaled 10/15/2020 DONALD SUNSERI
CofO Issued 10/15/2020 DONALD SUNSERI
Permit Finaled 10/15/2020 DONALD SUNSERI

Permit Application Clearance Information

APC Cleared 6/25/2019 SOPHIE GABEL-SCHEINBAU
Address approval Cleared 6/25/2019 HOWARD COOPER
Frnt yard landscape/Water mgmt Cleared 6/25/2019 SOPHIE GABEL-SCHEINBAU
Hydrant and Access approval Cleared 6/25/2019 GILBERT URREA
Miscellaneous Cleared 6/25/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 6/25/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 6/25/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 6/25/2019 SOPHIE GABEL-SCHEINBAU
Eng Process Fee Ord 176,300 Cleared 6/27/2019 LEE GUILBEAUX
Highway dedication Cleared 6/27/2019 LEE GUILBEAUX
Permit Cleared 6/27/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/27/2019 LEE GUILBEAUX
Sewer availability Cleared 6/27/2019 LEE GUILBEAUX
Low Impact Development Cleared 7/2/2019 MARTIN FRAGOSO
Miscellaneous Cleared 7/17/2019 BRANDON WILSON
Green Code Cleared 7/18/2019 DAVID MATSON
"Q" conditions Cleared 8/23/2019 STEVEN WECHSLER
Trees in Parkway Cleared 8/30/2019 ADRIAN SANCHEZ
"T" removal Cleared 9/10/2019 STEVEN WECHSLER
CPC Cleared 9/10/2019 STEVEN WECHSLER
Miscellaneous Cleared 9/10/2019 STEVEN WECHSLER
Tract Map conditions Cleared 9/10/2019 STEVEN WECHSLER

Contact Information

No Data Available.

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/18/2019 Not Ready for Inspection JOSEPH SAGEN
Underground Mechanical 9/18/2019 Approved JOSEPH SAGEN
Sewer 9/19/2019 Not Ready for Inspection JOSEPH SAGEN
Footing/Foundation/Slab 9/30/2019 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 10/7/2019 Not Ready for Inspection JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 10/17/2019 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 10/23/2019 Partial Approval JOSEPH SAGEN
BUILDING-Rough-Frame 10/31/2019 Approved BRUCE ROZAK
ELECTRICAL-Rough 10/31/2019 Approved BRUCE ROZAK
Green Building Rough 10/31/2019 Approved BRUCE ROZAK
HVAC-Rough 10/31/2019 Approved BRUCE ROZAK
PLUMBING-Rough 10/31/2019 Corrections Issued BRUCE ROZAK
Verify Sprinkler Sign Off 10/31/2019 Approved BRUCE ROZAK
Insulation 11/1/2019 Approved JOSEPH SAGEN
PLUMBING-Rough 11/1/2019 Approved JOSEPH SAGEN
Drywall Nailing 11/5/2019 Approved JOSEPH SAGEN
Interior/Exterior Lathing 11/7/2019 Partial Approval JOSEPH SAGEN
Service/Power Release 12/13/2019 Approved SEAN WIRCH
Gas Test 12/19/2019 Approved JOSEPH SAGEN
ELECTRICAL-Final 2/4/2020 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 2/26/2020 SGSOV Approved JOSEPH SAGEN
HVAC-Final 2/28/2020 Approved JOSEPH SAGEN
PLUMBING-Final 2/28/2020 Approved JOSEPH SAGEN
Service/Power Release 6/26/2020 Approved JOSEPH SAGEN
Special/Order Compliance 8/4/2020 Approved JOSEPH SAGEN
ELECTRICAL-Final 9/24/2020 Approved JOSEPH SAGEN
Final 9/24/2020 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 9/24/2020 Approved JOSEPH SAGEN
HVAC-Final 9/24/2020 Approved JOSEPH SAGEN
PLUMBING-Final 9/24/2020 Approved JOSEPH SAGEN
Smoke Detectors 9/24/2020 Approved JOSEPH SAGEN
Final 10/5/2020 Partial Approval JOSEPH SAGEN
Final 10/13/2020 OK to Issue CofO JOSEPH SAGEN