3020 N LAKERIDGE DR 90068
Certificate Information: 3020 N LAKERIDGE DR 90068
- Application / Permit
- 19010-20000-00359
- Plan Check / Job No.
- B19VN01334
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 2-STORY DET. GARAGE & ALQ. <SPRINKLERS REQ'D THROUGHOUT>
- Permit Issued
- Issued on 3/19/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2019 | ABDUL CHEGENI |
| Green Plans Picked Up | 2/27/2019 | APPLICANT |
| Corrections Issued | 3/14/2019 | ABDUL CHEGENI |
| Quality Review Completed | 3/22/2019 | STEVEN KIM |
| Building Plans Picked Up | 3/26/2019 | APPLICANT |
| Applicant returned to address corrections | 7/15/2019 | ABDUL CHEGENI |
| Applicant returned to address corrections | 7/30/2019 | ABDUL CHEGENI |
| Applicant returned to address corrections | 9/17/2019 | ABDUL CHEGENI |
| Applicant returned to address corrections | 1/30/2020 | ABDUL CHEGENI |
| Applicant returned to address corrections | 2/25/2020 | ABDUL CHEGENI |
| Plan Check Approved | 3/10/2020 | ABDUL CHEGENI |
| Issued | 3/19/2020 | LADBS |
| CofO in Progress | 5/12/2022 | BRIAN SULLIVAN |
| CofO Issued | 6/3/2022 | DEROLD HAUFF |
| Permit Finaled | 6/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/27/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 7/17/2019 | MARTIN FRAGOSO |
| Address approval | Cleared | 7/23/2019 | ERIK BEASLEY |
| Miscellaneous | Cleared | 7/23/2019 | SOPHIE GABEL-SCHEINBAU |
| Miscellaneous | Cleared | 7/23/2019 | SOPHIE GABEL-SCHEINBAU |
| Permit | Cleared | 7/23/2019 | ERIK BEASLEY |
| ZA Case | Cleared | 7/23/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 7/23/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 7/23/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 7/23/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 7/23/2019 | SOPHIE GABEL-SCHEINBAU |
| Specific Plan | Cleared | 11/4/2019 | SARAH GOLDMAN |
| BHO/Hillside ordinance | Cleared | 11/20/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2019 | EMIL KYUPELYAN |
| Highway dedication | Cleared | 11/20/2019 | EMIL KYUPELYAN |
| Private street | Cleared | 11/25/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 11/25/2019 | SARAH GOLDMAN |
| BHO/Hillside ordinance | Cleared | 12/9/2019 | ARMEN MEHRABIAN |
| BHO/Hillside ordinance | Cleared | 12/9/2019 | ARMEN MEHRABIAN |
| Green Code | Cleared | 12/12/2019 | PARISA ZAHABI |
| Disturb/Remove Protected Trees | Cleared | 1/6/2020 | STEPHEN DUPREY |
| Trees in Parkway | Cleared | 1/6/2020 | STEPHEN DUPREY |
| Hydrant and Access approval | Cleared | 1/9/2020 | ROBERT DUFF |
| Miscellaneous | Cleared | 1/9/2020 | NOAH MCCOY |
| Construction near power lines | Cleared | 1/10/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/10/2020 | WALTER RAMIREZ |
| Watercourse | Cleared | 1/14/2020 | ARMEN MEHRABIAN |
| Excavation more than 5-ft deep | Cleared | 1/30/2020 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 2/25/2020 | ABDUL CHEGENI |
| GPI Written Notices | Cleared | 3/5/2020 | ABDUL CHEGENI |
| Grading Pre-Inspection | Cleared | 3/5/2020 | ABDUL CHEGENI |
Contact Information
| Architect | Hefner,, William Robert; Lic. No.: C17013 | 5820 WILSHIRE BLVD SUITE 500 LOS ANGELES, CA 90036 |
| Contractor | Mathew Lloyd Homes Llc; Lic. No.: 936706-B | 1126 EL MONTE DR THOUSAND OAKS, CA 91362 |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 1386 EAST WALNUT STREET SUITE 202 PASADENA, CA 91106 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
| Geologist | Minas,, Shant; Lic. No.: GEO8859 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/7/2020 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Barrier | 8/28/2020 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 8/28/2020 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 9/1/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/7/2020 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 10/20/2020 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/29/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Masonry Wall/Backfill | 10/29/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 11/17/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Rough | 11/17/2020 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 12/2/2020 | Conditional Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 12/23/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Underground Mechanical | 12/23/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 12/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Rough | 12/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 12/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 12/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 12/29/2020 | Partial Approval | BRIAN SULLIVAN |
| Underground Mechanical | 12/29/2020 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/19/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 1/19/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Final | 1/19/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Rough | 1/19/2021 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 1/19/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 1/20/2021 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Wood Construction | 3/2/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Partial Approval | BRIAN SULLIVAN |
| HVAC-Rough | 4/20/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 4/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/21/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/22/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/27/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 4/27/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 4/27/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/29/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/6/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 5/6/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 5/12/2021 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 5/12/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/12/2021 | Partial Approval | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 5/12/2021 | Approved | BRIAN SULLIVAN |
| Shower Pan | 5/19/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/20/2021 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/4/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 6/4/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 6/14/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 6/15/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 8/6/2021 | Approved | BRIAN SULLIVAN |
| Sewer | 1/28/2022 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 1/28/2022 | Approved | BRIAN SULLIVAN |
| Gas Test | 2/1/2022 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 2/1/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 2/4/2022 | Approved | BRIAN SULLIVAN |
| Sewer | 2/4/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 3/17/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 3/21/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 3/21/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 3/22/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 3/22/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 3/23/2022 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Final | 3/30/2022 | Approved | BRIAN SULLIVAN |
| Grading Pre-Inspection | 4/1/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 4/1/2022 | Approved | BRIAN SULLIVAN |
| Service/Power Release | 4/1/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/7/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Service/Power Release | 4/7/2022 | Corrections Issued | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/8/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/20/2022 | Approved | BRIAN SULLIVAN |
| Final | 4/27/2022 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 4/27/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 4/27/2022 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 4/27/2022 | Approved | BRIAN SULLIVAN |
| Final | 5/11/2022 | OK to Issue CofO | BRIAN SULLIVAN |