11410 W CALVERT ST LOT 1 91606

Certificate Information: 11410 W CALVERT ST LOT 1 91606

Application / Permit
19010-20000-00256
Plan Check / Job No.
B19VN01015
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 4 STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE AND ROOF DECK. FIRE SPRINKLERS THROUGHOUT NFPA 13R. "Small lot subdivision pursuant to Tenative Tract Map No./Preliminary Parcel Map No. 74289. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded."
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
CofO Issued on 2/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2019 APPLICANT
Assigned to Plan Check Engineer 2/14/2019 JOSE MENDOZA
Corrections Issued 2/25/2019 JOSE MENDOZA
Quality Review Completed 2/26/2019 STEVEN KIM
Building Plans Picked Up 2/26/2019 APPLICANT
Green Plans Picked Up 2/26/2019 APPLICANT
Applicant returned to address corrections 10/1/2021 SELLA BENYAMIN
Plan Check Approved 12/22/2021 SELLA BENYAMIN
Issued 4/25/2022 APPLICANT
CofO in Progress 2/2/2026 JEFFREY PARD
CofO in Progress 2/2/2026 JOHN JANSON
CofO in Progress 2/17/2026 JEFFREY PARD
CofO in Progress 2/24/2026 JEFFREY PARD
Permit Finaled 2/24/2026 JOHN JANSON
CofO Issued 2/24/2026 JOHN JANSON
Permit Finaled 2/24/2026 JOHN JANSON

Permit Application Clearance Information

"Q" conditions Cleared 6/18/2019 STEVEN WECHSLER
Tract Map conditions Cleared 6/18/2019 STEVEN WECHSLER
Tract Map conditions Cleared 6/18/2019 STEVEN WECHSLER
Address approval Cleared 6/26/2019 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 6/26/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 6/26/2019 GEORGE SUCHAND
Sewer availability Cleared 6/26/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 7/16/2019 MICHAEL AYERS
Trees in Parkway Cleared 7/29/2019 JOHN KIM
Building over 3-story or 36-ft Cleared 10/3/2019 CALOSHA APPROVED
Low Impact Development Cleared 1/29/2020 JORGE MEJIA LEMUS
Highway dedication Cleared 10/7/2021 LEE GUILBEAUX
Miscellaneous Cleared 10/7/2021 LEE GUILBEAUX
Permit Cleared 10/7/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/13/2021 LEE GUILBEAUX
Tract Map conditions Cleared 12/10/2021 NOAH MCCOY

Contact Information

Contractor Crescenta Valley Engineering Inc; Lic. No.: 523164-B 2801 E FOOTHILL BLVD      PASADENA, CA 91107
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/31/2022 Partial Approval HENRY KIM
Footing/Foundation/Slab 6/3/2022 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Corrections Issued HENRY KIM
Interior/Exterior Lathing 7/27/2022 Not Ready for Inspection HENRY KIM
Deputy Wood Construction 7/28/2022 Approved HENRY KIM
Interior/Exterior Lathing 8/2/2022 Partial Approval HENRY KIM
Interior/Exterior Lathing 8/4/2022 Partial Approval HENRY KIM
Deputy Wood Construction 8/18/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Partial Approval JEFFREY PARD
Interior/Exterior Lathing 8/25/2022 Partial Approval JEFFREY PARD
Interior/Exterior Lathing 8/29/2022 Partial Approval JEFFREY PARD
Deputy Wood Construction 9/8/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval JEFFREY PARD
Interior/Exterior Lathing 9/15/2022 Partial Approval JEFFREY PARD
Interior/Exterior Lathing 9/19/2022 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Partial Approval JEFFREY PARD
Interior/Exterior Lathing 9/29/2022 Partial Approval JEFFREY PARD
Interior/Exterior Lathing 9/30/2022 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Partial Approval JEFFREY PARD
PLUMBING-Rough 10/19/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 11/4/2022 Corrections Issued JEFFREY PARD
PLUMBING-Rough 11/17/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 1/6/2023 No Access for Inspection JEFFREY PARD
ELECTRICAL-Rough 1/10/2023 Approved JEFFREY PARD
PLUMBING-Rough 1/19/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 1/20/2023 Corrections Issued JEFFREY PARD
HVAC-Rough 2/16/2023 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 2/21/2023 Corrections Issued JEFFREY PARD
HVAC-Rough 3/3/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 3/16/2023 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 3/20/2023 Corrections Issued JEFFREY PARD
Green Building Rough 3/20/2023 Not Ready for Inspection JEFFREY PARD
Verify Sprinkler Sign Off 3/20/2023 Approved JEFFREY PARD
BUILDING-Rough-Frame 5/8/2023 Approved JEFFREY PARD
Green Building Rough 5/8/2023 Approved JEFFREY PARD
Pre-Inspection 5/9/2023 Approved JEFFREY PARD
Wood Frame 5/9/2023 Approved JEFFREY PARD
Insulation 5/12/2023 Not Ready for Inspection HENRY KIM
Insulation 5/15/2023 Approved JEFFREY PARD
Drywall Nailing 6/21/2023 Approved JEFFREY PARD
Interior/Exterior Lathing 6/21/2023 Approved JEFFREY PARD
Shower Pan 6/21/2023 Approved JEFFREY PARD
ELECTRICAL-Rough 4/17/2024 Approved JEFFREY PARD
Underground Mechanical 5/1/2024 Approved JEFFREY PARD
HVAC-Final 11/18/2025 Approved JEFFREY PARD
PLUMBING-Final 11/18/2025 Corrections Issued JEFFREY PARD
ELECTRICAL-Final 12/9/2025 Approved JEFFREY PARD
Final 12/9/2025 OK to Issue CofO JEFFREY PARD
Gas Test 12/9/2025 Approved JEFFREY PARD
Green Building Final 12/9/2025 Approved JEFFREY PARD
PLUMBING-Final 12/9/2025 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved JEFFREY PARD
Service/Power Release 12/9/2025 Approved JEFFREY PARD
Smoke Detectors 12/9/2025 Approved JEFFREY PARD
Special/Order Compliance 2/18/2026 Corrections Issued JEFFREY PARD