- NEW 4 STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE AND ROOF DECK. FIRE SPRINKLERS THROUGHOUT NFPA 13R. "Small lot subdivision pursuant to Tenative Tract Map No./Preliminary Parcel Map No. 74289. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded."
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- CofO Issued on 2/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2019 | JOSE MENDOZA |
| Corrections Issued | 2/25/2019 | JOSE MENDOZA |
| Quality Review Completed | 2/26/2019 | STEVEN KIM |
| Building Plans Picked Up | 2/26/2019 | APPLICANT |
| Green Plans Picked Up | 2/26/2019 | APPLICANT |
| Applicant returned to address corrections | 10/1/2021 | SELLA BENYAMIN |
| Plan Check Approved | 12/22/2021 | SELLA BENYAMIN |
| Issued | 4/25/2022 | APPLICANT |
| CofO in Progress | 2/2/2026 | JEFFREY PARD |
| CofO in Progress | 2/2/2026 | JOHN JANSON |
| CofO in Progress | 2/17/2026 | JEFFREY PARD |
| CofO in Progress | 2/24/2026 | JEFFREY PARD |
| Permit Finaled | 2/24/2026 | JOHN JANSON |
| CofO Issued | 2/24/2026 | JOHN JANSON |
| Permit Finaled | 2/24/2026 | JOHN JANSON |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/18/2019 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 6/18/2019 | STEVEN WECHSLER |
| Tract Map conditions | Cleared | 6/18/2019 | STEVEN WECHSLER |
| Address approval | Cleared | 6/26/2019 | HOWARD COOPER |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 6/26/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 6/26/2019 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 7/16/2019 | MICHAEL AYERS |
| Trees in Parkway | Cleared | 7/29/2019 | JOHN KIM |
| Building over 3-story or 36-ft | Cleared | 10/3/2019 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 1/29/2020 | JORGE MEJIA LEMUS |
| Highway dedication | Cleared | 10/7/2021 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 10/7/2021 | LEE GUILBEAUX |
| Permit | Cleared | 10/7/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/13/2021 | LEE GUILBEAUX |
| Tract Map conditions | Cleared | 12/10/2021 | NOAH MCCOY |
Contact Information
| Contractor | Crescenta Valley Engineering Inc; Lic. No.: 523164-B | 2801 E FOOTHILL BLVD PASADENA, CA 91107 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSEPH SAGEN, (818) 774-4353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/31/2022 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 6/3/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 7/27/2022 | Not Ready for Inspection | HENRY KIM |
| Deputy Wood Construction | 7/28/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 8/2/2022 | Partial Approval | HENRY KIM |
| Interior/Exterior Lathing | 8/4/2022 | Partial Approval | HENRY KIM |
| Deputy Wood Construction | 8/18/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Partial Approval | JEFFREY PARD |
| Interior/Exterior Lathing | 8/25/2022 | Partial Approval | JEFFREY PARD |
| Interior/Exterior Lathing | 8/29/2022 | Partial Approval | JEFFREY PARD |
| Deputy Wood Construction | 9/8/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2022 | Partial Approval | JEFFREY PARD |
| Interior/Exterior Lathing | 9/15/2022 | Partial Approval | JEFFREY PARD |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Partial Approval | JEFFREY PARD |
| Interior/Exterior Lathing | 9/29/2022 | Partial Approval | JEFFREY PARD |
| Interior/Exterior Lathing | 9/30/2022 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 10/19/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 11/4/2022 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 11/17/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 1/6/2023 | No Access for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 1/10/2023 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 1/19/2023 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 1/20/2023 | Corrections Issued | JEFFREY PARD |
| HVAC-Rough | 2/16/2023 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 2/21/2023 | Corrections Issued | JEFFREY PARD |
| HVAC-Rough | 3/3/2023 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 3/16/2023 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/20/2023 | Corrections Issued | JEFFREY PARD |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 3/20/2023 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/8/2023 | Approved | JEFFREY PARD |
| Green Building Rough | 5/8/2023 | Approved | JEFFREY PARD |
| Pre-Inspection | 5/9/2023 | Approved | JEFFREY PARD |
| Wood Frame | 5/9/2023 | Approved | JEFFREY PARD |
| Insulation | 5/12/2023 | Not Ready for Inspection | HENRY KIM |
| Insulation | 5/15/2023 | Approved | JEFFREY PARD |
| Drywall Nailing | 6/21/2023 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/21/2023 | Approved | JEFFREY PARD |
| Shower Pan | 6/21/2023 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 4/17/2024 | Approved | JEFFREY PARD |
| Underground Mechanical | 5/1/2024 | Approved | JEFFREY PARD |
| HVAC-Final | 11/18/2025 | Approved | JEFFREY PARD |
| PLUMBING-Final | 11/18/2025 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Final | 12/9/2025 | Approved | JEFFREY PARD |
| Final | 12/9/2025 | OK to Issue CofO | JEFFREY PARD |
| Gas Test | 12/9/2025 | Approved | JEFFREY PARD |
| Green Building Final | 12/9/2025 | Approved | JEFFREY PARD |
| PLUMBING-Final | 12/9/2025 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 12/9/2025 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 12/9/2025 | Approved | JEFFREY PARD |
| Smoke Detectors | 12/9/2025 | Approved | JEFFREY PARD |
| Special/Order Compliance | 2/18/2026 | Corrections Issued | JEFFREY PARD |