7875 W GRANITO DR 90046

Certificate Information: 7875 W GRANITO DR 90046

Application / Permit
19010-20000-00247
Plan Check / Job No.
B19VN00996
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED 2-CAR CARPORT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 8/6/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2019 APPLICANT
Assigned to Plan Check Engineer 2/14/2019 NILOOFAR MEHRAIN
Corrections Issued 2/20/2019 NILOOFAR MEHRAIN
Quality Review Completed 2/22/2019 CHON CHIO KUO
Building Plans Picked Up 2/25/2019 APPLICANT
Green Plans Picked Up 2/25/2019 APPLICANT
Applicant returned to address corrections 5/8/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/20/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/16/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/3/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/26/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/18/2020 NILOOFAR MEHRAIN
Plan Check Approved 4/7/2020 NILOOFAR MEHRAIN
Issued 8/6/2020 APPLICANT
CofO in Progress 8/4/2023 STUART CHAPMAN
No Progress 8/7/2023 STUART CHAPMAN
CofO in Progress 8/15/2023 STUART CHAPMAN
Permit Finaled 8/29/2023 DEROLD HAUFF
CofO Issued 8/29/2023 DEROLD HAUFF
Permit Finaled 8/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 3/5/2019 TREVOR MARTIN
Miscellaneous Cleared 3/5/2019 TREVOR MARTIN
Miscellaneous Cleared 3/5/2019 TREVOR MARTIN
Miscellaneous Cleared 3/5/2019 TREVOR MARTIN
Miscellaneous Cleared 3/5/2019 TREVOR MARTIN
Miscellaneous Cleared 3/5/2019 TREVOR MARTIN
Miscellaneous Cleared 3/5/2019 TREVOR MARTIN
Tract Map conditions Cleared 3/5/2019 TREVOR MARTIN
Permit Cleared 3/8/2019 ZIXUAN CHEN
Trees in Parkway Cleared 3/11/2019 ADRIAN SANCHEZ
GPI Written Notices Cleared 5/8/2019 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 5/8/2019 NILOOFAR MEHRAIN
Address approval Cleared 5/10/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/10/2019 JEANETTE VONG
Sewer availability Cleared 5/10/2019 JEANETTE VONG
Hydrant and Access approval Cleared 6/5/2019 ROBERT DUFF
Work Adjacent to Public Way Cleared 7/22/2019 BOK GOH
Low Impact Development Cleared 2/28/2020 MARTIN FRAGOSO
Green Code Cleared 3/5/2020 MICHAEL AYERS
Miscellaneous Cleared 7/8/2020 NOAH MCCOY
ZA Case Cleared 7/8/2020 NOAH MCCOY
BHO/Hillside ordinance Cleared 7/24/2020 NGOC KIEM
BHO/Hillside ordinance Cleared 7/24/2020 NGOC KIEM
Roof/Waste drainage to street Cleared 7/24/2020 NGOC KIEM
BHO/Hillside ordinance Cleared 7/28/2020 ELAINE LEI

Contact Information

Contractor Hill Pete Construction Company Inc; Lic. No.: 470065-B 4626 ALBUQUERQUE ST 2ND FLOOR      SAN DIEGO, CA 92109
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Zweigler,, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206
Geologist Zweigler,, Robert Ingraham; Lic. No.: EG1210 196 DIRT ROAD      THOUSAND OAKS, CA 91361

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 1/19/2021 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/21/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/21/2021 Partial Inspection RAUL BARAJAS
Piling/Pier/Caisson 1/21/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/9/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 2/9/2021 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 2/9/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/18/2021 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 2/18/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/26/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 2/26/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 3/3/2021 Partial Approval RAUL BARAJAS
Sewer 3/3/2021 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 3/9/2021 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/11/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 3/11/2021 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 3/17/2021 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 3/17/2021 Partial Inspection RAUL BARAJAS
Underground Mechanical 3/17/2021 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/18/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/15/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 4/15/2021 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/28/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 4/28/2021 Partial Inspection RAUL BARAJAS
ELECTRICAL-Rough 5/12/2021 Approved RAUL BARAJAS
PLUMBING-Rough 5/12/2021 Partial Approval RAUL BARAJAS
Sewer 5/12/2021 Partial Approval RAUL BARAJAS
Underground Mechanical 5/12/2021 Approved RAUL BARAJAS
Underground Mechanical 6/1/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 6/7/2021 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 6/9/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 6/9/2021 Partial Approval RAUL BARAJAS
Sewer 6/9/2021 Partial Approval RAUL BARAJAS
Underground Mechanical 6/9/2021 Approved RAUL BARAJAS
Deputy Reinf. Concrete 6/22/2021 Conditional Approval THOMAS LOGRASSO
Deputy Reinf. Concrete 6/23/2021 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/23/2021 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 6/23/2021 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/24/2021 Conditional Approval JOHN HAMILTON
Excavation/Setback/Form/Re-Bar 7/1/2021 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 7/1/2021 Partial Approval RICHARD STEINBACH
Grounding or Bonding 7/1/2021 Partial Approval RICHARD STEINBACH
Deputy Other (see comments) 7/13/2021 No Access for Inspection ELMER BLAND
Deputy Shotcrete 7/13/2021 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Conditional Approval RICHARD STEINBACH
Deputy Steel/Welding 7/26/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 7/27/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 7/28/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 7/29/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 7/30/2021 Conditional Approval RICHARD STEINBACH
Deputy Steel/Welding 8/2/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/3/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/4/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/5/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/6/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/9/2021 Conditional Approval RAUL BARAJAS
PLUMBING-Rough 8/9/2021 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 8/10/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/11/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/12/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/13/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/16/2021 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/16/2021 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 8/16/2021 Not Ready for Inspection RAUL BARAJAS
Deputy Steel/Welding 8/17/2021 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/18/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/18/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/19/2021 Conditional Approval RAUL BARAJAS
Deputy Steel/Welding 8/20/2021 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/25/2021 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Approved RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 12/17/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 1/28/2022 Approved RAUL BARAJAS
HVAC-Rough 2/10/2022 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 2/16/2022 Partial Approval RAUL BARAJAS
Green Building Rough 2/18/2022 Partial Approval RAUL BARAJAS
Rough-Elec/Plmb/HVAC 2/18/2022 Partial Approval RAUL BARAJAS
Verify Sprinkler Sign Off 2/18/2022 Partial Approval RAUL BARAJAS
Insulation 2/25/2022 Approved RAUL BARAJAS
Drywall Nailing 3/10/2022 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 4/5/2022 Approved RAUL BARAJAS
Gas Test 4/6/2022 Approved RAUL BARAJAS
PLUMBING-Rough 4/6/2022 Approved RAUL BARAJAS
Sewer 4/6/2022 Approved RAUL BARAJAS
HVAC-Rough 4/7/2022 Approved RAUL BARAJAS
ELECTRICAL-Rough 4/8/2022 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 4/12/2022 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/12/2022 Approved RAUL BARAJAS
Green Building Rough 4/12/2022 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 4/12/2022 Approved RAUL BARAJAS
Wood Frame 4/12/2022 Approved RAUL BARAJAS
Insulation 4/13/2022 Approved RAUL BARAJAS
Drywall Nailing 4/27/2022 Approved RAUL BARAJAS
Special/Order Compliance 5/11/2022 Partial Inspection RAUL BARAJAS
Interior/Exterior Lathing 5/24/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 5/27/2022 Approved RAUL BARAJAS
Interior/Exterior Lathing 9/6/2022 Approved BRIAN SULLIVAN
Shower Pan 9/6/2022 Approved BRIAN SULLIVAN
Service/Power Release 10/3/2022 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 10/6/2022 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 11/3/2022 Corrections Issued BRIAN SULLIVAN
Service/Power Release 11/10/2022 Partial Inspection RAUL BARAJAS
Service/Power Release 12/1/2022 Approved RAUL BARAJAS
Service/Power Release 1/19/2023 Approved RAUL BARAJAS
PLUMBING-Final 2/1/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Final 2/6/2023 Corrections Issued STUART CHAPMAN
Gas Test 3/14/2023 Approved RAUL BARAJAS
ELECTRICAL-Final 3/17/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 4/6/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 4/6/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/6/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 4/6/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Reinforced Concrete Frame 4/6/2023 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 4/6/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 4/6/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/27/2023 Approved STUART CHAPMAN
Final 4/27/2023 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 4/27/2023 Approved STUART CHAPMAN
Green Building Final 4/27/2023 Approved STUART CHAPMAN
Reinforced Concrete Frame 4/27/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/27/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 4/27/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 8/2/2023 Approved STUART CHAPMAN
Final 8/2/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 8/2/2023 Approved STUART CHAPMAN
PLUMBING-Final 8/2/2023 Approved STUART CHAPMAN
Special/Order Compliance 8/7/2023 Corrections Issued STUART CHAPMAN