1420 N KINGSLEY DR 90027
Certificate Information: 1420 N KINGSLEY DR 90027
- Application / Permit
- 19010-20000-00122
- Plan Check / Job No.
- B19VN00433
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SFD/GAR
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 9/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | CHON CHIO KUO |
| Green Plans Picked Up | 1/24/2019 | APPLICANT |
| Corrections Issued | 1/28/2019 | CHON CHIO KUO |
| Quality Review Completed | 1/28/2019 | STEVEN KIM |
| Building Plans Picked Up | 1/28/2019 | APPLICANT |
| Applicant returned to address corrections | 9/18/2019 | CHON CHIO KUO |
| Plan Check Approved | 10/3/2019 | CHON CHIO KUO |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 4/7/2022 | BRIAN SULLIVAN |
| CofO Issued-Status Void | 4/19/2022 | DEROLD HAUFF |
| Permit Finaled-Status Void | 4/19/2022 | DEROLD HAUFF |
| Re-Activate Permit | 9/15/2022 | MICHAEL SMITH |
| CofO Corrected | 9/21/2022 | MICHAEL SMITH |
| Permit Finaled | 9/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2019 | ELENA LOPEZ |
| Highway dedication | Cleared | 3/29/2019 | ELENA LOPEZ |
| Permit | Cleared | 3/29/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 3/29/2019 | ELENA LOPEZ |
| Frnt yard landscape/Water mgmt | Cleared | 6/3/2019 | DIANA JIMENEZ |
| Hydrant and Access approval | Cleared | 6/3/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 9/6/2019 | SARAH YOUSSEF |
| Green Code | Cleared | 9/12/2019 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 9/23/2019 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/5/2020 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/13/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 5/18/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 5/20/2020 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 5/22/2020 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2020 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 7/17/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 7/17/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/10/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 8/10/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 8/10/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/17/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 8/17/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 8/17/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2020 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 8/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 8/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/22/2020 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 10/28/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 11/10/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| HVAC-Rough | 11/10/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| ELECTRICAL-Rough | 11/16/2020 | Approved | COREY HUPP |
| HVAC-Rough | 11/17/2020 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 12/3/2020 | Partial Approval | BRIAN SULLIVAN |
| Special/Order Compliance | 12/28/2020 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 1/25/2021 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Wood Construction | 1/27/2021 | Conditional Approval | ROBERT CORNELL |
| BUILDING-Rough-Frame | 2/1/2021 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2021 | Approved | BRIAN SULLIVAN |
| Wood Frame | 2/1/2021 | Conditional Approval | BRIAN SULLIVAN |
| Insulation | 2/10/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 2/10/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Insulation | 2/12/2021 | Conditional Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 2/12/2021 | Conditional Approval | SCOTT FINNILA |
| Drywall Nailing | 3/1/2021 | Partial Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/1/2021 | Approved | JOSEPH MCGARRY |
| Shower Pan | 3/1/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 3/15/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 3/31/2021 | Approved | BRIAN SULLIVAN |
| Sewer | 3/31/2021 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 3/31/2021 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 9/21/2021 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Final | 9/21/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/20/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 12/20/2021 | Corrections Issued | BRIAN SULLIVAN |
| Final | 12/20/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 12/20/2021 | Approved | BRIAN SULLIVAN |
| Green Building Final | 12/20/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 12/20/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 12/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 12/20/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 12/20/2021 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 12/20/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 1/3/2022 | Partial Approval | CRAIG DAVIS |
| HVAC-Final | 1/3/2022 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 2/4/2022 | Corrections Issued | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 2/4/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 2/4/2022 | Approved | BRIAN SULLIVAN |
| Final | 4/7/2022 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2022 | SGSOV Approved | BRIAN SULLIVAN |