11303 W KELOWNA ST 91342

Certificate Information: 11303 W KELOWNA ST 91342

Application / Permit
19010-20000-00111
Plan Check / Job No.
B19VN00407
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) IRREGULAR SHAPE 18'4" X 30'5" DETACHED ACCESSORY DWELLING UNIT PER AB494 AND SB229. ALL WORKS ARE PER DESIGN. See comment
Permit Issued
Issued on 9/13/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 ALDOUS CHIC
Green Plans Picked Up 1/24/2019 APPLICANT
Corrections Issued 1/28/2019 ALDOUS CHIC
Quality Review Completed 1/28/2019 ABDUL CHEGENI
Building Plans Picked Up 1/30/2019 APPLICANT
Applicant returned to address corrections 4/22/2019 ALDOUS CHIC
Plan Check Approved 8/28/2019 ALDOUS CHIC
Issued 9/13/2019 LADBS
CofO in Progress 1/27/2021 MICHEL ABAJAN
Permit Finaled 2/20/2021 MICHAEL SMITH
CofO Issued 2/20/2021 MICHAEL SMITH
Permit Finaled 2/20/2021 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/15/2019 ALDOUS CHIC
Address approval Cleared 3/21/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/21/2019 GUILLERMO PETRA
Green Code Cleared 3/21/2019 PARISA ZAHABI
Roof/Waste drainage to street Cleared 3/21/2019 GUILLERMO PETRA
Sewer availability Cleared 3/21/2019 GUILLERMO PETRA
Disturb/Remove Protected Trees Cleared 3/28/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 4/12/2019 GEORGE SUCHAND
Construction near power lines Cleared 8/14/2019 RIDWAN HARDY
Low Impact Development Cleared 8/19/2019 ORVAL HERNANDEZ-MARCI

Contact Information

Contractor Owner-Builder       ,
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/3/2019 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 1/6/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/7/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 4/7/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/5/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 5/5/2020 Not Ready for Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 5/5/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/26/2020 Approved MICHEL ABAJAN
Green Building Rough 5/26/2020 Approved MICHEL ABAJAN
Insulation 5/27/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/27/2020 Approved MICHEL ABAJAN
Drywall Nailing 6/8/2020 Approved MATTHEW NUCKOLLS
Shower Pan 7/13/2020 Approved MICHEL ABAJAN
Final 9/30/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 9/30/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/30/2020 SGSOV Approved MICHEL ABAJAN
Service/Power Release 9/30/2020 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 9/30/2020 Approved MICHEL ABAJAN
Final 1/27/2021 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 1/27/2021 Approved MICHEL ABAJAN