3904 N GOODLAND AVE 91604
Certificate Information: 3904 N GOODLAND AVE 91604
- Application / Permit
- 19010-20000-00074
- Plan Check / Job No.
- B19VN00268
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE ONE STORY (N) ACCESSORY DWELLING UNIT [PER GCS 65852.2(e)(1)(A)]_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 2/9/2022
- Issuing Office
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | ALYSSA N NARCISO |
| Corrections Issued | 2/8/2019 | ALYSSA N NARCISO |
| Quality Review Completed | 2/12/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 2/15/2019 | APPLICANT |
| Green Plans Picked Up | 3/1/2019 | APPLICANT |
| Applicant returned to address corrections | 12/16/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 3/9/2021 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 5/4/2021 | DAWN MC NULTY |
| Applicant returned to address corrections | 5/5/2021 | DAWN MC NULTY |
| Applicant returned to address corrections | 8/26/2021 | DAWN MC NULTY |
| Applicant returned to address corrections | 11/10/2021 | DAWN MC NULTY |
| Plan Check Approved | 12/22/2021 | DAWN MC NULTY |
| Issued | 2/9/2022 | APPLICANT |
| CofO in Progress | 3/20/2025 | JUAN VALENZUELA |
| CofO in Progress | 3/20/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
| CofO Issued | 4/17/2025 | RUBEN SALAS |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/21/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/21/2019 | RIDWAN HARDY |
| Green Code | Cleared | 12/19/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 2/11/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 7/30/2020 | ORVAL HERNANDEZ-MARCI |
| Address approval | Cleared | 8/20/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 8/20/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 8/20/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/21/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 5/13/2021 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 6/4/2021 | ADRIAN CASTRO |
| Work Adjacent to Public Way | Cleared | 6/10/2021 | GABRIEL ROBLES |
| Excavation more than 5-ft deep | Cleared | 8/27/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 8/27/2021 | ALYSSA N NARCISO |
| Grading Pre-Inspection | Cleared | 8/27/2021 | ALYSSA N NARCISO |
| Disturb/Remove Protected Trees | Cleared | 9/22/2021 | ALYSSA N NARCISO |
Contact Information
| Architect | Brouse,, Jon Robert; Lic. No.: C22200 | 12930 VENTURA BLVD SUITE 214 STUDIO CITY, CA 91604 |
| Engineer | Mercado,, Lizandro; Lic. No.: S4331 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 1453 14TH ST STE A SANTA MONICA, CA 90404 |
| Geologist | , ; Lic. No.: GEO2257 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
| Geologist | Van, Meter, James L.; Lic. No.: EG2031 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/13/2022 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/16/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/24/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/1/2022 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 12/20/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2023 | Partial Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 1/13/2023 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 1/13/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 10/11/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/19/2023 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/14/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 12/21/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 3/6/2024 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Grounding or Bonding | 3/6/2024 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 3/6/2024 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 3/6/2024 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 3/13/2024 | Approved | JOHN COLEMAN |
| Green Building Rough | 3/13/2024 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 3/13/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 4/23/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 4/25/2024 | Approved | JOHN COLEMAN |
| Drywall Nailing | 5/14/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 10/28/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 11/25/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 11/25/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 11/25/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Reinforced Concrete Frame | 11/25/2024 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Service/Power Release | 11/25/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 11/25/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 12/13/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 12/20/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Final | 12/20/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 12/20/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/20/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 3/4/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 3/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 3/4/2025 | Approved | CHRISTOPHE COCHRAN |