3904 N GOODLAND AVE 91604

Certificate Information: 3904 N GOODLAND AVE 91604

Application / Permit
19010-20000-00074
Plan Check / Job No.
B19VN00268
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE ONE STORY (N) ACCESSORY DWELLING UNIT [PER GCS 65852.2(e)(1)(A)]_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
CofO Issued on 4/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 ALYSSA N NARCISO
Corrections Issued 2/8/2019 ALYSSA N NARCISO
Quality Review Completed 2/12/2019 OMID HEDAYAT
Building Plans Picked Up 2/15/2019 APPLICANT
Green Plans Picked Up 3/1/2019 APPLICANT
Applicant returned to address corrections 12/16/2020 DAWN MC NULTY
Applicant returned to address corrections 3/9/2021 ALYSSA N NARCISO
Applicant returned to address corrections 5/4/2021 DAWN MC NULTY
Applicant returned to address corrections 5/5/2021 DAWN MC NULTY
Applicant returned to address corrections 8/26/2021 DAWN MC NULTY
Applicant returned to address corrections 11/10/2021 DAWN MC NULTY
Plan Check Approved 12/22/2021 DAWN MC NULTY
Issued 2/9/2022 APPLICANT
CofO in Progress 3/20/2025 JUAN VALENZUELA
CofO in Progress 3/20/2025 CHRISTOPHE COCHRAN
Permit Finaled 4/17/2025 RUBEN SALAS
CofO Issued 4/17/2025 RUBEN SALAS
Permit Finaled 4/17/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 9/21/2019 RIDWAN HARDY
Construction within easement Cleared 9/21/2019 RIDWAN HARDY
Green Code Cleared 12/19/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 2/11/2020 GEORGE SUCHAND
Low Impact Development Cleared 7/30/2020 ORVAL HERNANDEZ-MARCI
Address approval Cleared 8/20/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 8/20/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 8/20/2020 GUILLERMO PETRA
Sewer availability Cleared 8/21/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/25/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 5/13/2021 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 6/4/2021 ADRIAN CASTRO
Work Adjacent to Public Way Cleared 6/10/2021 GABRIEL ROBLES
Excavation more than 5-ft deep Cleared 8/27/2021 CALOSHA APPROVED
GPI Written Notices Cleared 8/27/2021 ALYSSA N NARCISO
Grading Pre-Inspection Cleared 8/27/2021 ALYSSA N NARCISO
Disturb/Remove Protected Trees Cleared 9/22/2021 ALYSSA N NARCISO

Contact Information

Architect Brouse,, Jon Robert; Lic. No.: C22200 12930 VENTURA BLVD SUITE 214      STUDIO CITY, CA 91604
Engineer Mercado,, Lizandro; Lic. No.: S4331 12467 W WASHINGTON BLVD      LOS ANGELES, CA 90066
Engineer Obando,, Gaspar Eduardo; Lic. No.: C71382 1453 14TH ST STE A      SANTA MONICA, CA 90404
Geologist , ; Lic. No.: GEO2257 6634 VALJEAN AVE      VAN NUYS, CA 91406
Geologist Van, Meter, James L.; Lic. No.: EG2031 6634 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/13/2022 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 6/16/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 6/24/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/1/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 12/20/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Partial Approval ROBERT GOLD
Deputy Drilled-In Anchors 1/13/2023 Conditional Approval DAVID MATSON
Deputy Wood Construction 1/13/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Approved CHRISTOPHE COCHRAN
Sewer 10/11/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 10/19/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/14/2023 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 12/21/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/6/2024 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Not Ready for Inspection JOHN COLEMAN
Grounding or Bonding 3/6/2024 Approved JOHN COLEMAN
PLUMBING-Rough 3/6/2024 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 3/6/2024 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 3/13/2024 Approved JOHN COLEMAN
Green Building Rough 3/13/2024 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 3/13/2024 Approved JOHN COLEMAN
Interior/Exterior Lathing 4/23/2024 Approved CHRISTOPHE COCHRAN
Insulation 4/25/2024 Approved JOHN COLEMAN
Drywall Nailing 5/14/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Gas Test 10/28/2024 Approved CHRISTOPHE COCHRAN
Drywall Nailing 11/25/2024 Approved CHRISTOPHE COCHRAN
Final 11/25/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 11/25/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Reinforced Concrete Frame 11/25/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Ready CHRISTOPHE COCHRAN
Service/Power Release 11/25/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 11/25/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 12/13/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 12/20/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Final 12/20/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 12/20/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 12/20/2024 Approved CHRISTOPHE COCHRAN
Final 3/4/2025 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 3/4/2025 Approved CHRISTOPHE COCHRAN
Service/Power Release 3/4/2025 Approved CHRISTOPHE COCHRAN