11464 W OXNARD ST 1-5 91606

Certificate Information: 11464 W OXNARD ST 1-5 91606

Application / Permit
19010-20000-00060
Plan Check / Job No.
B19VN00234
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
3-STORY 5 UNIT APT WITH ATTACHED PARKING GARAGE.
Permit Issued
Issued on 11/26/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 RODNEY SAMIIAN
Corrections Issued 2/7/2019 RODNEY SAMIIAN
Disabled Access Plans Picked Up 2/11/2019 APPLICANT
Quality Review Completed 2/13/2019 ABDUL CHEGENI
Building Plans Picked Up 2/15/2019 APPLICANT
Green Plans Picked Up 2/15/2019 APPLICANT
Plan Check Approved 10/10/2019 RODNEY SAMIIAN
Issued 11/26/2019 LADBS
CofO in Progress 7/6/2021 CAMERON CHABAN
Permit Finaled 7/7/2021 RICKEY JACKSON
CofO Issued 7/7/2021 RICKEY JACKSON
Permit Finaled 7/7/2021 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 6/20/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 6/20/2019 MARKOS PEREZ-BRAN
Highway dedication Cleared 6/20/2019 MARKOS PEREZ-BRAN
Permit Cleared 6/20/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 6/20/2019 MARKOS PEREZ-BRAN
Fire Marshall Fire Life Safety Cleared 7/3/2019 MENOA AGHAJANI
Hydrant and Access approval Cleared 7/3/2019 JEREMY CARTER
Low Impact Development Cleared 7/18/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 8/20/2019 APEKSHYA BAJRACHARYA
"Q" conditions Cleared 8/21/2019 STEVEN WECHSLER
CPC Cleared 8/21/2019 STEVEN WECHSLER
DAS Clearance Cleared 8/21/2019 RODNEY SAMIIAN
Frnt yard landscape/Water mgmt Cleared 8/21/2019 MARITZA PRZEKOP
Green Code Cleared 9/5/2019 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Phukunhaphan,, Justin Jed; Lic. No.: C84727 334 E. CIELO WAY      PLACENTIA, CA 92870

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/7/2020 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 2/7/2020 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 2/14/2020 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 2/21/2020 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 2/26/2020 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Partial Inspection ANDREW DORSO
Green Building Rough 6/2/2020 Not Ready for Inspection ANDREW DORSO
Insulation 6/2/2020 Partial Inspection ANDREW DORSO
Interior/Exterior Lathing 6/2/2020 Not Ready for Inspection ANDREW DORSO
Structural Steel Frame 6/2/2020 Partial Approval ANDREW DORSO
Verify Sprinkler Sign Off 6/2/2020 Not Ready for Inspection ANDREW DORSO
Wood Frame 6/2/2020 Partial Inspection ANDREW DORSO
Green Building Rough 7/28/2020 Approved ANDREW DORSO
Insulation 7/28/2020 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 7/28/2020 Corrections Issued ANDREW DORSO
Verify Sprinkler Sign Off 7/28/2020 Approved ANDREW DORSO
Wood Frame 7/28/2020 Not Ready for Inspection ANDREW DORSO
Interior/Exterior Lathing 8/18/2020 Corrections Issued ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 9/9/2020 Approved JOHN KITCKO
Insulation 9/9/2020 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 9/9/2020 Partial Approval JOHN KITCKO
Light Gage Steel Frame 9/9/2020 Partial Approval JOHN KITCKO
Wood Frame 9/9/2020 Partial Approval JOHN KITCKO
Insulation 9/21/2020 Approved JOHN KITCKO
Drywall Nailing 10/8/2020 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 10/13/2020 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 10/14/2020 Conditional Approval JOHN KITCKO
Drywall Nailing 10/20/2020 Approved JOHN KITCKO
Green Building Final 10/23/2020 Not Ready for Inspection JOHN KITCKO
Final 6/4/2021 Partial Inspection CAMERON CHABAN
Footing/Foundation/Slab 6/4/2021 Approved CAMERON CHABAN
Green Building Final 6/4/2021 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 6/4/2021 SGSOV Approved CAMERON CHABAN
Smoke Detectors 6/4/2021 Approved CAMERON CHABAN
Structural Steel Frame 6/4/2021 Approved CAMERON CHABAN
Wood Frame 6/4/2021 Approved CAMERON CHABAN
Final 6/23/2021 Partial Inspection CAMERON CHABAN
Final 7/1/2021 OK to Issue CofO CAMERON CHABAN