20529 W BIRMINGHAM WAY 91326

Certificate Information: 20529 W BIRMINGHAM WAY 91326

Application / Permit
19010-20000-00015
Plan Check / Job No.
B19VN00028
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
THREE STORY SFD WITH ATTACH 3 CAR GARAGE_STANDARD PLAN # 648 PLAN_3XB _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 5/30/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2019 APPLICANT
Green Plans Picked Up 1/16/2019 APPLICANT
Assigned to Plan Check Engineer 1/17/2019 DAWN MC NULTY
Corrections Issued 1/22/2019 DAWN MC NULTY
Quality Review Completed 1/23/2019 CHON CHIO KUO
Building Plans Picked Up 1/25/2019 APPLICANT
Plan Check Approved 5/30/2019 DAWN MC NULTY
Issued 5/30/2019 LADBS
CofO in Progress 7/24/2020 SEAN WIRCH
CofO Issued 7/24/2020 DONALD SUNSERI
Permit Finaled 7/24/2020 DONALD SUNSERI

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/9/2019 ROBERT DUFF
Address approval Cleared 4/11/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/11/2019 LEE GUILBEAUX
Permit Cleared 4/11/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/11/2019 LEE GUILBEAUX
Sewer availability Cleared 4/11/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/11/2019 LEE GUILBEAUX
"T" removal Cleared 4/16/2019 MARITZA PRZEKOP
CPC Cleared 4/16/2019 MARITZA PRZEKOP
Miscellaneous Cleared 4/16/2019 MARITZA PRZEKOP
Miscellaneous Cleared 4/16/2019 MARITZA PRZEKOP
Miscellaneous Cleared 4/16/2019 MARITZA PRZEKOP
Miscellaneous Cleared 4/16/2019 MARITZA PRZEKOP
Private street Cleared 4/16/2019 MARITZA PRZEKOP
Specific Plan Cleared 4/16/2019 MARITZA PRZEKOP
Tract Map conditions Cleared 4/16/2019 MARITZA PRZEKOP
ZA Case Cleared 4/16/2019 MARITZA PRZEKOP
ZA Case Cleared 4/16/2019 MARITZA PRZEKOP
Low Impact Development Cleared 4/29/2019 AMMAR ELTAWIL
Green Code Cleared 5/2/2019 MICHAEL AYERS

Contact Information

Architect Gorrill, Ernest Bernard; Lic. No.: C13407 419 E BAY ST      COSTA MESA, CA 92627
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN: GATES/LEGAL    HORSHAM, PA 19044
Engineer Kim, Kevin Chae; Lic. No.: C53821 2349 N CAMPUS AVENUE      UPLAND, CA 91784
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505
Engineer Wong, Ramon Roman Ii; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/16/2019 Approved BRUCE ROZAK
Footing/Foundation/Slab 9/3/2019 Not Ready for Inspection DONALD SUNSERI
Footing/Foundation/Slab 9/5/2019 Approved DONALD SUNSERI
Underground Mechanical 10/1/2019 Approved BRUCE ROZAK
Sewer 10/23/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 11/14/2019 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 12/17/2019 Not Ready for Inspection BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 12/18/2019 Partial Approval DONALD SUNSERI
Deputy Steel/Welding 1/7/2020 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 1/31/2020 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 2/14/2020 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/2/2020 Approved SEAN WIRCH
ELECTRICAL-Rough 3/12/2020 Approved SEAN WIRCH
HVAC-Rough 3/12/2020 Approved SEAN WIRCH
PLUMBING-Rough 3/12/2020 Not Ready for Inspection SEAN WIRCH
BUILDING-Rough-Frame 3/13/2020 Approved SEAN WIRCH
Green Building Rough 3/13/2020 Approved SEAN WIRCH
Verify Sprinkler Sign Off 3/13/2020 Approved SEAN WIRCH
Drywall Nailing 4/2/2020 Approved DONALD SUNSERI
Interior/Exterior Lathing 4/2/2020 Approved DONALD SUNSERI
Interior/Exterior Lathing 4/20/2020 Approved SEAN WIRCH
Gas Test 5/11/2020 Approved SEAN WIRCH
Service/Power Release 6/2/2020 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 6/8/2020 SGSOV Approved SEAN WIRCH
ELECTRICAL-Final 6/19/2020 Approved SEAN WIRCH
HVAC-Final 6/19/2020 Approved SEAN WIRCH
ELECTRICAL-Final 7/17/2020 Approved SEAN WIRCH
HVAC-Final 7/17/2020 Approved SEAN WIRCH
Final 7/23/2020 OK to Issue CofO SEAN WIRCH
Green Building Final 7/23/2020 Approved SEAN WIRCH
PLUMBING-Final 7/23/2020 Approved SEAN WIRCH
Smoke Detectors 7/23/2020 Approved SEAN WIRCH