1332 S HARBOR BLVD berth76-77 90731
Certificate Information: 1332 S HARBOR BLVD berth76-77 90731
- Application / Permit
- 19010-10011-01499
- Plan Check / Job No.
- B23LA12672
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- Repair and Maintenance to (E) Decks associated with buildings under 19010-10000-01499. Revisions to permit drawings to include maintenance for two existing overwater decks (berth 76 and berth 77) located over the port of la waterfront. 1. North deck#1 is 8,882 sf with concrete & wood structure and 2. South deck#2 is 16,749 sf with concrete structure. Maintenance is limited to new decking and substructure, replacing guardrails, and improving accessibility to both decks. No area increase is proposed other than the cantilevered accessible walkway on the south deck. Drawings update under delta 9 - bulletin #9.
- Permit Issued
- Issued on 10/11/2023
- Issuing Office
- Current Status
- Issued on 10/11/2023
Permit Application Status History
| Submitted | 7/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | HERNAN ARREOLA |
| Corrections Issued | 7/25/2023 | HERNAN ARREOLA |
| Quality Review Completed | 8/14/2023 | PETER KIM |
| Plan Check Approved | 9/29/2023 | HERNAN ARREOLA |
| Issued | 10/11/2023 | APPLICANT |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 8/28/2023 | HERNAN ARREOLA |
| "Q" conditions | Cleared | 8/31/2023 | JASON CHAN |
| DAS Clearance | Cleared | 9/7/2023 | Armen Jivalagian |
| Coastal Zone | Cleared | 9/12/2023 | YINGSHI HUANG |
| Port of LA Approval | Cleared | 9/15/2023 | MELISSA HARNE |
Contact Information
| Architect | Pullman,, Alan Wayne; Lic. No.: NA26936 | , |
| Contractor | Curtom-Matt; Lic. No.: 631020-B | , |
| Contractor | Matt Construction Corporation; Lic. No.: 631020-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/27/2026 | Approved | DAVID TSAU |
| Pre-Inspection | 7/13/2026 | Partial Inspection | DAVID TSAU |
| Piling/Pier/Caisson | 7/21/2026 | Partial Inspection | DAVID TSAU |
| Wood Frame | 7/22/2026 | Partial Approval | DAVID TSAU |