150 W CENTER WAY Unit 31 90045

Certificate Information: 150 W CENTER WAY Unit 31 90045

Application / Permit
19010-10006-01115
Plan Check / Job No.
B24LA02585
Group
Building
Type
Nonbldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(3) Airport Building
Work Description
**Eplan LAX PROJECT - APM Deferred Submittal for 1GW3 (19010-10000-01115) for Alstom electrical equipment anchorage for traffic lights, CWECs, and tilt down poles.
Permit Issued
Issued on 4/24/2024
Issuing Office
Metro
Current Status
Permit Finaled on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2024 APPLICANT
Assigned to Plan Check Engineer 2/15/2024 GARO TELMI
Corrections Issued 2/19/2024 GARO TELMI
Quality Review Completed 2/21/2024 CHARLES CHANG
Plan Check Approved 4/23/2024 GARO TELMI
Issued 4/24/2024 APPLICANT
Permit Finaled 8/6/2024 NICK LAROCCA

Permit Application Clearance Information

Project Permit Cleared 2/26/2024 MERCEDES ORTIZ

Contact Information

Contractor Fluor Flatiron Balfour Beatty Dragados; Lic. No.: 1036344-B 205 W. DEWEY ST      GOLDSBORO, NC 27530
Engineer Hattar,, Cliff; Lic. No.: S5384 115 SOURCE      IRVINE, CA 92618

Inspector Information

NICK LAROCCA, (213) 473-2153 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

No Data Available.