3555 S OVERLAND AVE 90034
Certificate Information: 3555 S OVERLAND AVE 90034
- Application / Permit
- 19010-10005-05733
- Plan Check / Job No.
- B26VN03973
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- SUPPLEMENTAL PERMIT FOR 19010-20000-05733 TO CONVERT RETAIL SPACE INTO (N) RESTAURANT **ePlan** (TENANT IMPROVEMENT TO BE FILED AS SEPARATE PERMIT)
- Permit Issued
- Issued on 6/2/2026
- Issuing Office
- Current Status
- Permit Finaled on 7/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2026 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2026 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/22/2026 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/3/2026 | OMID HEDAYAT |
| Applicant returned to address corrections | 4/8/2026 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 5/1/2026 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/2/2026 | NILOOFAR MEHRAIN |
| Issued | 6/2/2026 | APPLICANT |
| Permit Finaled | 7/9/2026 | PAUL DAVIDSON |
Permit Application Clearance Information
| DAS Clearance | Cleared | 3/5/2026 | Omid Hedayat |
| Highway dedication | Cleared | 3/26/2026 | KATHLEEN LEE |
| ZA Case | Cleared | 4/8/2026 | YINGSHI HUANG |
| ZA Case | Cleared | 4/8/2026 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2026 | DERRICK MAGEE |
| Specific Plan | Cleared | 4/10/2026 | KYLE WINSTON |
| ZA Case | Cleared | 4/10/2026 | YINGSHI HUANG |
| ZI | Cleared | 4/10/2026 | KYLE WINSTON |
| Fire Marshall Fire Life Safety | Cleared | 5/1/2026 | ANDREW KO |
| Hydrant and Access approval | Cleared | 5/1/2026 | RUEL COLE |
| Sewer availability | Cleared | 5/21/2026 | STEVE MELGAR |
Contact Information
| Architect | Reed,, John G; Lic. No.: C14523 | 657 ROSE AVENUE VENICE, CA 90291 |
| Contractor | Helio Group; Lic. No.: 1004478-B | , |
| Contractor | Helio; Lic. No.: 1004478-B | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/11/2026 | Conditional Approval | PAUL DAVIDSON |
| Drywall Nailing | 6/24/2026 | Approved | PAUL DAVIDSON |
| Final | 7/9/2026 | Permit Finaled | PAUL DAVIDSON |
| Reinforced Concrete Frame | 7/9/2026 | Approved | PAUL DAVIDSON |
| Reinforced Masonry Frame | 7/9/2026 | Approved | PAUL DAVIDSON |
| Smoke Detectors | 7/9/2026 | Approved | PAUL DAVIDSON |