4357 S KENYON AVE 90066
Certificate Information: 4357 S KENYON AVE 90066
- Application / Permit
- 19010-10002-04979
- Plan Check / Job No.
- B20LA09458
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 19010-10001-04979 REDUCE THE SIZE OF ADU AND STORAGE AND UPDATE PLOT PLAN LAYOUT
- Permit Issued
- Issued on 6/30/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 11/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | FERNANDO FLORES |
| Corrections Issued | 6/15/2020 | FERNANDO FLORES |
| Quality Review Completed | 6/18/2020 | STANLEY RAAP |
| Plan Check Approved | 6/24/2020 | FERNANDO FLORES |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Issued | 6/30/2020 | LADBS |
| Permit Finaled | 11/17/2020 | JOHNNY MIRANDA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Diallo Construction; Lic. No.: 965438-B | 535 S ALEXANDRIA AVENUE #308 LOS ANGELES, CA 90020 |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2020 | Approved | JOHNNY MIRANDA |
| Wood Frame | 7/16/2020 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 7/23/2020 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 7/27/2020 | Approved | JOHNNY MIRANDA |
| Wood Frame | 7/27/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 7/29/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 7/30/2020 | Approved | CRAIG DAVIS |
| Final | 9/1/2020 | Corrections Issued | JOHNNY MIRANDA |
| Final | 9/3/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 9/21/2020 | Corrections Issued | JOHNNY MIRANDA |
| Final | 9/24/2020 | Corrections Issued | JOHNNY MIRANDA |
| Final | 10/9/2020 | No Access for Inspection | DAVID HEINE |
| Final | 11/17/2020 | Permit Finaled | JOHNNY MIRANDA |