5440 W FRANKLIN AVE 90027
Certificate Information: 5440 W FRANKLIN AVE 90027
- Application / Permit
- 19010-10002-03315
- Plan Check / Job No.
- B20LA15282
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- FOUNDATION ONLY PERMIT PER IB/P/BC 2020-097 FOR A NEW MIXED USE BUILDING UNDER PERMIT NO. 19010-10000-03315.
- Permit Issued
- Issued on 12/14/2020
- Issuing Office
- Current Status
- Permit Finaled on 11/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2020 | KESETE HAREGOT |
| Plan Check Approved | 12/11/2020 | KESETE HAREGOT |
| Issued | 12/14/2020 | APPLICANT |
| Permit Finaled | 11/15/2024 | EDWIN GREGORYONA |
Permit Application Clearance Information
| Green Code | Cleared | 8/27/2020 | KESETE HAREGOT |
| DAS Clearance | Cleared | 8/28/2020 | KESETE HAREGOT |
| Hydrant and Access approval | Cleared | 8/28/2020 | KURT CORRAL |
| "D" conditions | Cleared | 8/31/2020 | RUBEN VASQUEZ |
| CPC | Cleared | 8/31/2020 | RUBEN VASQUEZ |
| Frnt yard landscape/Water mgmt | Cleared | 8/31/2020 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 8/31/2020 | ANDRES COVARRUBIAS |
| Opn space landscape/Water mgmt | Cleared | 8/31/2020 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 8/31/2020 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 8/31/2020 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 8/31/2020 | RUBEN VASQUEZ |
| ZA Case | Cleared | 8/31/2020 | RUBEN VASQUEZ |
| Address approval | Cleared | 9/4/2020 | ELAINE LEI |
| Bicycle Parking | Cleared | 9/4/2020 | ELAINE LEI |
| Encroachment in public way | Cleared | 9/4/2020 | ELAINE LEI |
| Highway dedication | Cleared | 9/4/2020 | ELAINE LEI |
| Permit | Cleared | 9/4/2020 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 9/4/2020 | ELAINE LEI |
| Sewer availability | Cleared | 9/4/2020 | ELAINE LEI |
| DCP conditions approval | Cleared | 9/9/2020 | JAMES MCCARTHY |
| Density Bonus 12.22.A.25 | Cleared | 9/9/2020 | JAMES MCCARTHY |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2020 | ELAINE LEI |
| Fire Marshall Fire Life Safety | Cleared | 9/11/2020 | VIDAL GARCIA |
| Building over 3-story or 36-ft | Cleared | 9/18/2020 | CALOSHA APPROVED |
| Trees in Parkway | Cleared | 10/6/2020 | JOHN KIM |
| Work Adjacent to Public Way | Cleared | 10/27/2020 | BOK GOH |
Contact Information
| Architect | Opasinski,, Ewa; Lic. No.: C33952 | 4600 DON LORENZO DRIVE # 15 LOS ANGELES, CA 90008 |
| Contractor | Dynamic Design Build Inc; Lic. No.: 747205-B | 11777 SAN VICENTE BLVD STE 800 LOS ANGELES, CA 90049 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
| Engineer | Krief,, Dan Dov; Lic. No.: C76041 | 1166 S POINT VIEW STREET LOS ANGELES, CA 90035 |
| Engineer | Nelson,, William Mc Kee; Lic. No.: S3417 | 5 DELLWOOD DOVE CANYON, CA 92679 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/21/2020 | Approved | EDWIN GREGORYONA |
| Deputy Grading | 12/23/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 12/28/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 12/29/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 12/30/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 12/31/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 1/5/2021 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 2/10/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 3/23/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 3/24/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 4/5/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 4/6/2021 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 4/8/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 4/22/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 4/23/2021 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 5/5/2021 | Partial Inspection | EDWIN GREGORYONA |
| Deputy Grading | 5/13/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/17/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 5/18/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/19/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/25/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/26/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/27/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 5/28/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/1/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 6/2/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 6/2/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 6/7/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/8/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 6/10/2021 | Partial Approval | JONATHAN QUACH |
| Deputy Grading | 6/16/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 6/18/2021 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 6/18/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/22/2021 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 6/22/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/23/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/24/2021 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 6/24/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 6/25/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 7/1/2021 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 7/2/2021 | Partial Approval | DANIEL COLLINS |
| Deputy Grading | 7/8/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Grading | 7/19/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Grading | 7/20/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Grading | 7/21/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 7/22/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Grading | 7/23/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 7/26/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 7/28/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 7/29/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 7/29/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Grading | 8/2/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 8/11/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/16/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 8/17/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/18/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/19/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/20/2021 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/21/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Shotcrete | 11/16/2021 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 3/9/2022 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Shotcrete | 5/13/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 5/16/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 5/17/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 5/17/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 4/24/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 12/4/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 12/4/2023 | Partial Approval | EDWIN GREGORYONA |