801 E E ST 90744
Certificate Information: 801 E E ST 90744
- Application / Permit
- 19010-10002-01761
- Plan Check / Job No.
- B19LA16133
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- EARLY START PERMIT FOR FOUNDATION ONLY. (NEW WAREHOUSE W/MEZZANINE FOR COLD STORAGE).
- Permit Issued
- Issued on 8/9/2019
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 10/28/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 8/7/2019 | JOE VO |
| Issued | 8/9/2019 | LADBS |
| CofO in Progress | 10/19/2020 | JOEY BUCHANAN |
| CofO in Progress | 10/19/2020 | JOEY BUCHANAN |
| CofO Issued-Status Void | 10/20/2020 | NICK LAROCCA |
| Permit Finaled-Status Void | 10/20/2020 | NICK LAROCCA |
| Re-Activate Permit | 10/27/2020 | HENRY BAGHDASSARIAN |
| Permit Finaled | 10/28/2020 | HENRY BAGHDASSARIAN |
| CofO Corrected | 10/28/2020 | HENRY BAGHDASSARIAN |
| Permit Finaled | 10/28/2020 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/5/2019 | ANNA VAN |
| Abandoned oil well | Cleared | 8/5/2019 | ROBERT DUFF |
| Clean Up Green Up | Cleared | 8/5/2019 | ANNA VAN |
| DAS Clearance | Cleared | 8/5/2019 | JOE VO |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2019 | ERIK BEASLEY |
| Highway dedication | Cleared | 8/5/2019 | ALINE MILLER |
| Hydrant and Access approval | Cleared | 8/5/2019 | ROBERT DUFF |
| Low Impact Development | Cleared | 8/5/2019 | SARAH YOUSSEF |
| Miscellaneous | Cleared | 8/5/2019 | JOE VO |
| Permit | Cleared | 8/5/2019 | ERIK BEASLEY |
| Prkng lot landscape/Water mgmt | Cleared | 8/5/2019 | ANNA VAN |
| Roof/Waste drainage to street | Cleared | 8/5/2019 | ALINE MILLER |
| Sewer availability | Cleared | 8/5/2019 | ERIK BEASLEY |
| Site Plan review | Cleared | 8/5/2019 | ANNA VAN |
| ZA Case | Cleared | 8/5/2019 | ANNA VAN |
| ZI | Cleared | 8/5/2019 | ANNA VAN |
| Green Code | Cleared | 8/6/2019 | JOE VO |
| Project located in CRA area | Cleared | 8/6/2019 | JIM URQUHART |
| Trees in Parkway | Cleared | 8/9/2019 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Alston Construction Company Inc; Lic. No.: 759899-B | 3500 LENOX RD STE 501 ATLANTA, GA 30326 |
| Engineer | Bushra,, Rafeek L; Lic. No.: S4490 | 2564 W WOODLAND DR ANAHEIM, CA 92801 |
| Engineer | Conaway,, Johnny Ray; Lic. No.: C19689 | PO BOX 155 OAK VIEW, CA 93022 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/12/2019 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 8/12/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/14/2019 | Conditional Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/23/2019 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/26/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Other (see comments) | 8/27/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 8/27/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 8/29/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/29/2019 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/3/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 9/6/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/9/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 9/10/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/16/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Other (see comments) | 9/17/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 9/17/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 9/20/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/22/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/23/2019 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/24/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/25/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/28/2019 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/30/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 11/4/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Methane Barrier | 11/5/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/8/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/14/2019 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/18/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/19/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/20/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/21/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/22/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/25/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/2/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/3/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 12/3/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/5/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/6/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/9/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/10/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/11/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/12/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/13/2019 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 12/16/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 12/16/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/16/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/17/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 12/18/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/18/2019 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 12/18/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/19/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 12/20/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/20/2019 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/31/2019 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/6/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/7/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 1/8/2020 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 1/9/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/9/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/10/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/14/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/21/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/24/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/27/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/28/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/29/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 1/30/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 1/31/2020 | Approved | RAFAEL ESPINOZA |
| Drywall Nailing | 2/14/2020 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 2/14/2020 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 2/24/2020 | Approved | JOEY BUCHANAN |
| Masonry Wall/Backfill | 2/24/2020 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 4/13/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 4/13/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 4/14/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 4/14/2020 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 4/15/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 4/15/2020 | Approved | JOEY BUCHANAN |
| Deputy Fireproofing | 4/27/2020 | Approved | JOEY BUCHANAN |
| Final | 10/19/2020 | OK to Issue CofO | JOEY BUCHANAN |