4425 1/2 E MONT EAGLE PL 90041

Certificate Information: 4425 1/2 E MONT EAGLE PL 90041

Application / Permit
19010-10001-01756
Plan Check / Job No.
B20LA05123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Supplemental (ref. 19010-10000-01756) permit to change engineer of record and revise plans.
Permit Issued
Issued on 7/27/2020
Issuing Office
Current Status
Permit Finaled on 8/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 RODOLFO ARIAS
Corrections Issued 3/23/2020 RODOLFO ARIAS
Quality Review Completed 3/23/2020 KEN GILL
Building Plans Picked Up 4/21/2020 APPLICANT
Applicant returned to address corrections 4/24/2020 RODOLFO ARIAS
Applicant returned to address corrections 5/7/2020 RODOLFO ARIAS
Applicant returned to address corrections 5/8/2020 RODOLFO ARIAS
Applicant returned to address corrections 6/12/2020 RODOLFO ARIAS
Applicant returned to address corrections 6/16/2020 RODOLFO ARIAS
Plan Check Approved 7/27/2020 RODOLFO ARIAS
Issued 7/27/2020 APPLICANT
Permit Finaled 8/4/2023 HAMIK HARTOUNIAN

Permit Application Clearance Information

Low Impact Development Cleared 6/12/2020 MARTIN FRAGOSO
Green Code Cleared 6/15/2020 RODOLFO ARIAS

Contact Information

Contractor Sunshine Builders Inc; Lic. No.: 1008306-B 7120 HAVENHURST AVE STE 113      VAN NUYS, CA 91406
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/10/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/13/2020 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/18/2020 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/18/2020 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/23/2020 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/23/2020 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/23/2020 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 11/23/2020 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 11/23/2020 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/4/2020 Approved OSVALDO PARAMO
HVAC-Rough 12/4/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/4/2020 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 12/4/2020 Approved OSVALDO PARAMO
Shower Pan 12/4/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/8/2020 Approved HAMIK HARTOUNIAN
Insulation 12/11/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/18/2020 Approved HAMIK HARTOUNIAN
Final 11/1/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/1/2022 Corrections Issued HAMIK HARTOUNIAN