855-855 1/2 N JUNE ST 90038

Certificate Information: 855-855 1/2 N JUNE ST 90038

Application / Permit
19010-10001-01694
Plan Check / Job No.
B20LA00351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
SUPPLEMENTAL TO PERMIT #19010-10000-01694 TO INCLUDE "U" OCCUPANCY IN STRUCTURAL INVENTORY, CONVERT EXISTING UNCOVERED DECK ON SECOND FLOOR TO COVERED DECK, AND (2) 10' X 10'-7.5" ADDITIONS ON THE THIRD FLOOR TO CREATE (1) BEDROOM FOR EACH UNIT.
Permit Issued
Issued on 1/29/2020
Issuing Office
Valley
Current Status
Permit Finaled on 10/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2020 APPLICANT
Assigned to Plan Check Engineer 1/8/2020 MICHAEL LOPEZ
Corrections Issued 1/8/2020 MICHAEL LOPEZ
Plan Check Approved 1/27/2020 MICHAEL LOPEZ
Issued 1/29/2020 LADBS
Permit Finaled 10/26/2020 BRIAN SULLIVAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/21/2020 CELINA MORENO
Green Code Cleared 1/21/2020 MICHAEL LOPEZ
Low Impact Development Cleared 1/27/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/27/2020 JEANIE LAM

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 57 W PALM STREET      ALTADENA, CA 910014368
Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 1/31/2020 Partial Approval ROBERT CORNELL
BUILDING-Rough-Frame 10/26/2020 Approved BRIAN SULLIVAN
Final 10/26/2020 Permit Finaled BRIAN SULLIVAN
Footing/Foundation/Slab 10/26/2020 Approved BRIAN SULLIVAN
Green Building Final 10/26/2020 Approved BRIAN SULLIVAN
Green Building Rough 10/26/2020 Approved BRIAN SULLIVAN
METHANE-Barrier 10/26/2020 Approved BRIAN SULLIVAN
METHANE-Final 10/26/2020 Approved BRIAN SULLIVAN
METHANE-Rough 10/26/2020 Approved BRIAN SULLIVAN
METHANE-Subgrade 10/26/2020 Approved BRIAN SULLIVAN
Smoke Detectors 10/26/2020 Approved BRIAN SULLIVAN