1961 W AVALON ST 90039

Certificate Information: 1961 W AVALON ST 90039

Application / Permit
19010-10000-06599
Plan Check / Job No.
B19LA27651
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25'-8" X 27'-2" (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/22/2024
Issuing Office
Metro
Current Status
Issued on 2/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/2/2020 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 SELLA BENYAMIN
Corrections Issued 2/10/2020 SELLA BENYAMIN
Quality Review Completed 2/12/2020 STEVEN KIM
Building Plans Picked Up 2/14/2020 APPLICANT
Green Plans Picked Up 2/28/2020 APPLICANT
Applicant returned to address corrections 5/14/2021 SELLA BENYAMIN
Applicant returned to address corrections 1/20/2023 SELLA BENYAMIN
Plan Check Approved 10/3/2023 SELLA BENYAMIN
Issued 2/22/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/25/2020 JAMES MORALEZ
Street width determination Cleared 2/25/2020 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 3/12/2020 CECILIO NAVARRO
Sewer availability Cleared 3/12/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 7/29/2022 GILBERT URREA
Address approval Cleared 12/27/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 12/27/2022 JEANETTE VONG
ZA Case Cleared 12/29/2022 DALIA MOKAYED
BHO/Hillside ordinance Cleared 1/31/2023 CHRISTOPHER ROCHA
Street Frontage Cleared 1/31/2023 CHRISTOPHER ROCHA
Low Impact Development Cleared 9/28/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 9/29/2023 DAVID VO

Contact Information

Contractor J Z J B Cnst Inv; Lic. No.: 1013600-B 345 W LORAINE ST 3      GLENDALE, CA 91202
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/6/2024 Partial Inspection THOMAS LOGRASSO
Underground Mechanical 4/30/2024 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 5/7/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/10/2024 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/10/2024 Approved HAMIK HARTOUNIAN
Pre-Inspection 5/10/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 2/7/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Wood Construction 2/12/2025 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/7/2025 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 3/7/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/18/2025 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 3/18/2025 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 3/21/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 3/28/2025 Approved HAMIK HARTOUNIAN
Special/Order Compliance 3/28/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/3/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/7/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 4/7/2025 Approved HAMIK HARTOUNIAN
Shower Pan 4/7/2025 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 4/7/2025 Approved HAMIK HARTOUNIAN
Insulation 4/18/2025 Corrections Issued HAMIK HARTOUNIAN
Drywall Nailing 4/24/2025 Approved ALEX COLIN
Insulation 4/24/2025 Approved ALEX COLIN
Interior/Exterior Lathing 5/7/2025 Approved REGINA MENDEZ
Gas Test 9/3/2025 Not Ready for Inspection LILIANA PORTILLO
Sewer 9/3/2025 Not Ready for Inspection LILIANA PORTILLO
Underground Mechanical 9/3/2025 Not Ready for Inspection LILIANA PORTILLO
Underground Mechanical 9/17/2025 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 4/28/2026 Approved HAMIK HARTOUNIAN
HVAC-Final 4/28/2026 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 4/28/2026 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 6/1/2026 Approved WILLIAM SIERRA
Final 6/1/2026 Corrections Issued WILLIAM SIERRA
Green Building Final 6/1/2026 Not Ready for Inspection WILLIAM SIERRA
HVAC-Final 6/1/2026 Approved WILLIAM SIERRA
PLUMBING-Final 6/1/2026 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 6/1/2026 SGSOV Approved WILLIAM SIERRA
Service/Power Release 6/1/2026 Not Ready for Inspection WILLIAM SIERRA
Smoke Detectors 6/1/2026 Approved WILLIAM SIERRA