1903 N LAKE SHORE AVE 90039
Certificate Information: 1903 N LAKE SHORE AVE 90039
- Application / Permit
- 19010-10000-06597
- Plan Check / Job No.
- B19LA27651
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Metro
- Current Status
- Issued on 2/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | SELLA BENYAMIN |
| Corrections Issued | 2/10/2020 | SELLA BENYAMIN |
| Quality Review Completed | 2/12/2020 | STEVEN KIM |
| Building Plans Picked Up | 2/14/2020 | APPLICANT |
| Green Plans Picked Up | 2/28/2020 | APPLICANT |
| Applicant returned to address corrections | 5/14/2021 | SELLA BENYAMIN |
| Applicant returned to address corrections | 1/20/2023 | SELLA BENYAMIN |
| Plan Check Approved | 10/3/2023 | SELLA BENYAMIN |
| Issued | 2/22/2024 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/25/2020 | JAMES MORALEZ |
| Street width determination | Cleared | 2/25/2020 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 3/12/2020 | CECILIO NAVARRO |
| Address approval | Cleared | 2/17/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 7/29/2022 | GILBERT URREA |
| BHO/Hillside ordinance | Cleared | 12/27/2022 | JEANETTE VONG |
| ZA Case | Cleared | 12/29/2022 | DALIA MOKAYED |
| BHO/Hillside ordinance | Cleared | 1/31/2023 | CHRISTOPHER ROCHA |
| Permit | Cleared | 1/31/2023 | CHRISTOPHER ROCHA |
| Street Frontage | Cleared | 1/31/2023 | CHRISTOPHER ROCHA |
| Trees in Parkway | Cleared | 8/30/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 9/28/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 9/29/2023 | DAVID VO |
Contact Information
| Contractor | J Z J B Cnst Inv; Lic. No.: 1013600-B | 345 W LORAINE ST 3 GLENDALE, CA 91202 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/19/2024 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/19/2024 | Corrections Issued | SCOTT FINNILA |
| Special/Order Compliance | 5/17/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 9/25/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/17/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 11/5/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 11/13/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 12/3/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/3/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/23/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 2/12/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Partial Approval | WILLIAM SIERRA |
| Masonry Wall/Backfill | 2/19/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Rough | 3/7/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/7/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/18/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/18/2025 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/21/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 3/21/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/28/2025 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/3/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 4/7/2025 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 4/7/2025 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 4/7/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/18/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/24/2025 | Approved | ALEX COLIN |
| Insulation | 4/24/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 5/7/2025 | Approved | REGINA MENDEZ |
| Gas Test | 9/3/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 9/3/2025 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/3/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/28/2026 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 4/28/2026 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 4/28/2026 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 6/1/2026 | Approved | FREDDIE RIVERA |
| Final | 6/1/2026 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/1/2026 | Approved | FREDDIE RIVERA |
| Green Building Final | 6/1/2026 | Approved | FREDDIE RIVERA |
| HVAC-Final | 6/1/2026 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 6/1/2026 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/1/2026 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 6/1/2026 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 6/1/2026 | Approved | FREDDIE RIVERA |