764 W ELBERON AVE 90731
Certificate Information: 764 W ELBERON AVE 90731
- Application / Permit
- 19010-10000-06528
- Plan Check / Job No.
- B19LA27610
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY NEW SFR COMPLY WITH DEPARTMENT ORDER effective date 09/25/2012. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 2/23/2021
- Issuing Office
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | JESSE ARELLANO |
| Corrections Issued | 2/1/2020 | JESSE ARELLANO |
| Quality Review Completed | 2/12/2020 | BILL STUTSMAN |
| Green Plans Picked Up | 2/14/2020 | APPLICANT |
| Applicant returned to address corrections | 10/29/2020 | JESSE ARELLANO |
| Plan Check Approved | 1/12/2021 | JESSE ARELLANO |
| Issued | 2/23/2021 | APPLICANT |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| CofO in Progress | 4/28/2022 | ANSON MAGLASANG |
| CofO in Progress | 5/2/2022 | ANSON MAGLASANG |
| CofO in Progress | 8/16/2022 | ANSON MAGLASANG |
| Permit Finaled | 8/16/2022 | DEROLD HAUFF |
| CofO Issued | 8/16/2022 | DEROLD HAUFF |
| Permit Finaled | 8/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 3/6/2020 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 3/13/2020 | JOHN CONNEALLY |
| Sewer availability | Cleared | 3/13/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 3/16/2020 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 3/16/2020 | ERIK BEASLEY |
| Low Impact Development | Cleared | 9/9/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/28/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/13/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 4/13/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 4/28/2021 | Approved | JOHN KLARIN |
| Piling/Pier/Caisson | 4/28/2021 | Approved | JOHN KLARIN |
| Insulation | 5/6/2021 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 5/6/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2021 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/29/2021 | Conditional Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 6/29/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 6/29/2021 | Partial Approval | JOHN KLARIN |
| HVAC-Rough | 6/29/2021 | Approved | JOHN KLARIN |
| MERV13>=Rough | 6/29/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 6/29/2021 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 6/29/2021 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/12/2021 | Partial Approval | JOHN KLARIN |
| Interior/Exterior Lathing | 8/12/2021 | Approved | JOHN KLARIN |
| Shower Pan | 8/12/2021 | Approved | JOHN KLARIN |
| Verify Rec and Parks Fee Memo | 8/12/2021 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 8/12/2021 | Approved | JOHN KLARIN |
| Insulation | 8/16/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 8/19/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 8/19/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/20/2021 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Final | 12/13/2021 | Corrections Issued | ANSON MAGLASANG |
| Gas Test | 12/13/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Final | 12/13/2021 | Corrections Issued | ANSON MAGLASANG |
| MERV13>=Final | 12/13/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Final | 12/13/2021 | Corrections Issued | ANSON MAGLASANG |
| Service/Power Release | 12/13/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 1/11/2022 | Not Ready for Inspection | DONALD CRICHLOW |
| Final | 1/11/2022 | Not Ready for Inspection | DONALD CRICHLOW |
| Green Building Final | 1/11/2022 | Not Ready for Inspection | DONALD CRICHLOW |
| MERV13>=Final | 1/11/2022 | Not Ready for Inspection | DONALD CRICHLOW |
| SGSOV-Seismic Gas S/O Valve | 1/11/2022 | SGSOV Not Ready | DONALD CRICHLOW |
| Service/Power Release | 1/11/2022 | Not Ready for Inspection | DONALD CRICHLOW |
| Smoke Detectors | 1/11/2022 | Not Ready for Inspection | DONALD CRICHLOW |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Not Ready | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 3/17/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 3/17/2022 | Approved | EUGENE CASSIDY |
| HVAC-Final | 3/17/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Final | 3/17/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 3/17/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/27/2022 | Approved | ANSON MAGLASANG |
| Final | 4/27/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| MERV13>=Final | 4/27/2022 | Approved | ANSON MAGLASANG |
| Service/Power Release | 4/27/2022 | Approved | ANSON MAGLASANG |
| Smoke Detectors | 4/27/2022 | Approved | ANSON MAGLASANG |
| Special/Order Compliance | 5/2/2022 | Corrections Issued | ANSON MAGLASANG |
| Special/Order Compliance | 5/11/2022 | Corrections Issued | ANSON MAGLASANG |
| Final | 8/11/2022 | OK to Issue CofO | ANSON MAGLASANG |