4404 E BOWMAN BLVD 90032
Certificate Information: 4404 E BOWMAN BLVD 90032
- Application / Permit
- 19010-10000-06458
- Plan Check / Job No.
- B19LA27535
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU WITH BASEMENT AND GARAGE PER PLANNING CASE ADM-2023-2353-QC(2 OF 4)
- Permit Issued
- Issued on 4/28/2023
- Issuing Office
- Metro
- Current Status
- Issued on 4/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 2/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | ALBERT SERVIN |
| Corrections Issued | 2/25/2020 | ALBERT SERVIN |
| Quality Review Completed | 2/26/2020 | KEN GILL |
| Applicant returned to address corrections | 3/10/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 3/25/2020 | ALBERT SERVIN |
| Building Plans Picked Up | 4/1/2020 | APPLICANT |
| Applicant returned to address corrections | 5/21/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 10/19/2021 | ALBERT SERVIN |
| Applicant returned to address corrections | 10/21/2021 | ALBERT SERVIN |
| Plan Check Approved | 4/27/2023 | ALBERT SERVIN |
| Issued | 4/28/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2020 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 3/10/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | JEANIE LAM |
| Sewer availability | Cleared | 3/10/2020 | JEANIE LAM |
| Green Code | Cleared | 3/19/2020 | ALBERT SERVIN |
| Green Code | Cleared | 3/19/2020 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 3/24/2023 | GILBERT URREA |
| "D" conditions | Cleared | 4/5/2023 | DALIA MOKAYED |
| "Q" conditions | Cleared | 4/5/2023 | DALIA MOKAYED |
| ZI | Cleared | 4/5/2023 | DALIA MOKAYED |
| GPI Written Notices | Cleared | 4/6/2023 | ALBERT SERVIN |
| BHO/Hillside ordinance | Cleared | 4/7/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 4/7/2023 | TREVOR QUAN |
| Low Impact Development | Cleared | 4/11/2023 | ORVAL HERNANDEZ-MARCI |
| Miscellaneous | Cleared | 4/26/2023 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 4/26/2023 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
| Geologist | Foster,, John Hugh; Lic. No.: EG1134 | 14146 SAARINEN IRVINE, CA 92606 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/22/2023 | Not Ready for Inspection | AMY COLIN |
| PLUMBING-Rough | 5/22/2023 | Partial Approval | AMY COLIN |
| Pre-Inspection | 5/22/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 5/24/2023 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 5/24/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 5/26/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 7/14/2023 | Not Ready for Inspection | AMY COLIN |
| Footing/Foundation/Slab | 7/31/2023 | Corrections Issued | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2023 | Corrections Issued | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 7/8/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/16/2024 | Corrections Issued | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 7/22/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/2/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/2/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 8/2/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 8/2/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Rough-Elec/Plmb/HVAC | 8/2/2024 | Corrections Issued | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 8/2/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/13/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/13/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 8/13/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/13/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/5/2025 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 3/5/2025 | Corrections Issued | LILIANA PORTILLO |
| Wood Frame | 3/10/2025 | Partial Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/28/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/28/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 3/28/2025 | Approved | LILIANA PORTILLO |
| Insulation | 3/28/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 3/28/2025 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 3/28/2025 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 4/22/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/22/2025 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/15/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 2/4/2026 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/22/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 4/22/2026 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/22/2026 | Approved | LILIANA PORTILLO |
| Gas Test | 4/22/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 4/22/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 4/22/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/22/2026 | SGSOV Not Ready | LILIANA PORTILLO |
| Service/Power Release | 4/22/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 4/22/2026 | Approved | LILIANA PORTILLO |