3566 N EAGLE ROCK BLVD 1-2 90065

Certificate Information: 3566 N EAGLE ROCK BLVD 1-2 90065

Application / Permit
19010-10000-06423
Plan Check / Job No.
B19LA27521
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX W ATTACHED GARAGE AT FRONT OF LOT.
Permit Issued
Issued on 9/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Green Plans Picked Up 2/11/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 YOUNG KIM
Corrections Issued 2/17/2020 YOUNG KIM
Quality Review Completed 2/27/2020 QUAN NGHIEM
Building Plans Picked Up 3/2/2020 APPLICANT
Applicant returned to address corrections 10/7/2020 YOUNG KIM
Applicant returned to address corrections 10/8/2020 YOUNG KIM
Applicant returned to address corrections 10/19/2020 YOUNG KIM
Applicant returned to address corrections 10/22/2020 YOUNG KIM
Applicant returned to address corrections 4/6/2021 YOUNG KIM
Applicant returned to address corrections 4/8/2021 YOUNG KIM
Applicant returned to address corrections 6/10/2021 YOUNG KIM
Applicant returned to address corrections 9/23/2021 YOUNG KIM
Applicant returned to address corrections 9/29/2021 YOUNG KIM
Applicant returned to address corrections 1/25/2022 YOUNG KIM
Applicant returned to address corrections 8/16/2022 YOUNG KIM
Plan Check Approved 8/30/2022 YOUNG KIM
Issued 9/27/2022 APPLICANT
CofO in Progress 9/20/2024 THOMAS LOGRASSO
Permit Finaled 9/25/2024 RUBEN SALAS
CofO Issued 9/25/2024 RUBEN SALAS
Permit Finaled 9/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/26/2020 CECILIO NAVARRO
Highway dedication Cleared 3/26/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/2/2020 CECILIO NAVARRO
Sewer availability Cleared 10/2/2020 CECILIO NAVARRO
Permit Cleared 10/27/2020 JAMES MORALEZ
Hydrant and Access approval Cleared 10/30/2020 KURT CORRAL
GPI Written Notices Cleared 9/29/2021 YOUNG KIM
Grading Pre-Inspection Cleared 10/8/2021 PATRICK MISCHLICH
Low Impact Development Cleared 11/16/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/6/2021 JEANETTE VONG
Frnt yard landscape/Water mgmt Cleared 7/25/2022 JAZMIN ROQUE
Miscellaneous Cleared 7/25/2022 JAZMIN ROQUE
Supp. Use District POD/CDO/TDO Cleared 7/25/2022 JAZMIN ROQUE
Green Code Cleared 8/16/2022 YOUNG KIM

Contact Information

Contractor Marc'S Construction Inc; Lic. No.: 1074627-B 5690 FULLERTON AVE APT 2      BUENA PARK, CA 90621
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/5/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 12/5/2022 Partial Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 12/22/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/22/2022 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 1/12/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 1/30/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Wood Construction 2/6/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 2/24/2023 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 3/21/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/19/2023 Partial Approval RICHARD DOCKUS
Deputy Wood Construction 5/19/2023 Partial Approval JEFFREY MEAD
HVAC-Rough 5/22/2023 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 6/5/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 6/5/2023 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 6/5/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/25/2023 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 7/25/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 7/25/2023 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/4/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 8/4/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/4/2023 Partial Approval HAMIK HARTOUNIAN
MERV13>=Rough 8/4/2023 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 8/4/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/10/2023 Approved HAMIK HARTOUNIAN
Insulation 8/14/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Partial Approval KATHRYN BUTTERWORTH
Insulation 8/21/2023 Approved KATHRYN BUTTERWORTH
Deputy Wood Construction 8/22/2023 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 9/6/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 9/11/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/22/2023 Approved KATHRYN BUTTERWORTH
Shower Pan 11/22/2023 Approved KATHRYN BUTTERWORTH
Sewer 1/19/2024 Corrections Issued HAMIK HARTOUNIAN
Sewer 1/31/2024 Approved HAMIK HARTOUNIAN
Underground Mechanical 1/31/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 6/27/2024 Corrections Issued SCOTT FINNILA
PLUMBING-Final 6/27/2024 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 7/29/2024 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 7/29/2024 Approved THOMAS LOGRASSO
HVAC-Final 9/12/2024 Approved THOMAS LOGRASSO
Final 9/17/2024 Corrections Issued THOMAS LOGRASSO
MERV13>=Final 9/17/2024 Approved THOMAS LOGRASSO
PLUMBING-Final 9/17/2024 Approved THOMAS LOGRASSO
Service/Power Release 9/17/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 9/20/2024 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 9/20/2024 Approved THOMAS LOGRASSO
Service/Power Release 9/20/2024 Approved THOMAS LOGRASSO