408 N EAST RUSTIC ROAD 90402
Certificate Information: 408 N EAST RUSTIC ROAD 90402
- Application / Permit
- 19010-10000-06418
- Plan Check / Job No.
- B19LA27518
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2 STORY OVER BASEMENT SFD WITH ATTACHED GARAGE. Fire sprinkler NFPA13D
- Permit Issued
- Issued on 7/10/2020
- Issuing Office
- Current Status
- CofO Issued on 4/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | SHANGQIN XIE |
| Corrections Issued | 2/20/2020 | SHANGQIN XIE |
| Quality Review Completed | 2/29/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 3/19/2020 | SHANGQIN XIE |
| Applicant returned to address corrections | 3/31/2020 | SHANGQIN XIE |
| Applicant returned to address corrections | 5/1/2020 | SHANGQIN XIE |
| Applicant returned to address corrections | 6/23/2020 | SHANGQIN XIE |
| Green Plans Picked Up | 6/29/2020 | APPLICANT |
| Plan Check Approved | 7/7/2020 | SHANGQIN XIE |
| Issued | 7/10/2020 | APPLICANT |
| Building Plans Picked Up | 7/10/2020 | APPLICANT |
| CofO in Progress | 4/14/2022 | JOHN KIDWELL |
| Permit Finaled | 4/20/2022 | DANIEL ORRANTE |
| CofO Issued | 4/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/19/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 3/19/2020 | RENZ SORIANO |
| Green Code | Cleared | 4/1/2020 | NEGAR NEJAD |
| Watercourse | Cleared | 5/12/2020 | MAHELET GEBEYHU |
| Address approval | Cleared | 5/13/2020 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 5/13/2020 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 5/13/2020 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 5/13/2020 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 5/20/2020 | KURT CORRAL |
| Permit | Cleared | 5/21/2020 | CECILIO NAVARRO |
| Coastal Zone | Cleared | 6/5/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 6/5/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 6/5/2020 | NOAH MCCOY |
| Miscellaneous | Cleared | 6/5/2020 | NOAH MCCOY |
| Low Impact Development | Cleared | 6/30/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/1/2020 | DALE WILLIAMS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Engineer | Uhles,, Scott Delane; Lic. No.: C72391 | 2909 ARIZONA AVE 5 SANTA MONICA, CA 90404 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 12/17/2020 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/17/2020 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/21/2020 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 1/19/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/17/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Masonry Wall/Backfill | 2/17/2021 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 2/24/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/2/2021 | Conditional Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/8/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 3/9/2021 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 3/12/2021 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 3/16/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/22/2021 | Partial Approval | PIERRE VEGA |
| ELECTRICAL-Rough | 3/26/2021 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 3/26/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 4/1/2021 | Conditional Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 5/27/2021 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Conditional Approval | JOHN KIDWELL |
| Deputy Wood Construction | 6/7/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 6/22/2021 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 7/2/2021 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 7/22/2021 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 7/27/2021 | Partial Approval | PIERRE VEGA |
| ELECTRICAL-Rough | 8/3/2021 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 8/3/2021 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/4/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 8/6/2021 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/9/2021 | Approved | JOHN KIDWELL |
| FLOOD-Proofing Certificate | 8/9/2021 | Approved | JOHN KIDWELL |
| Green Building Rough | 8/9/2021 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 8/9/2021 | Approved | JOHN KIDWELL |
| HVAC-Rough | 8/11/2021 | Approved | JOHN KIDWELL |
| Drywall Nailing | 8/27/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 8/27/2021 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 10/13/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Shower Pan | 10/15/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 11/1/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 12/16/2021 | Approved | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 12/17/2021 | Approved | STEPHANIE SWANSON |
| Sewer | 1/27/2022 | Approved | MICHAEL PELHAM |
| Underground Mechanical | 1/27/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| Gas Test | 3/16/2022 | Corrections Issued | JOHN KIDWELL |
| Gas Test | 3/23/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 3/25/2022 | Approved | JOHN KIDWELL |
| Service/Power Release | 3/25/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 3/29/2022 | Approved | JOHN KIDWELL |
| Final | 3/30/2022 | Corrections Issued | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 3/30/2022 | Approved | JOHN KIDWELL |
| Green Building Final | 4/7/2022 | Approved | JOHN KIDWELL |
| HVAC-Final | 4/7/2022 | Approved | JOHN KIDWELL |
| Final | 4/13/2022 | OK to Issue CofO | JOHN KIDWELL |