4615-4615 1/4 W ST CHARLES PL 90019

Certificate Information: 4615-4615 1/4 W ST CHARLES PL 90019

Application / Permit
19010-10000-06401
Plan Check / Job No.
B19LA27503
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 3-story 4-unit multiresidential building with attached gargae
Permit Issued
Issued on 12/16/2020
Issuing Office
Metro
Current Status
CofO Corrected on 6/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 ARSALAN SHABESTARI
Disabled Access Plans Picked Up 1/31/2020 APPLICANT
Corrections Issued 2/20/2020 ARSALAN SHABESTARI
Quality Review Completed 2/28/2020 HERNAN ARREOLA
Applicant returned to address corrections 4/13/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 4/29/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 6/16/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 7/22/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 7/27/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 8/19/2020 ARSALAN SHABESTARI
Green Plans Picked Up 9/28/2020 APPLICANT
Applicant returned to address corrections 11/23/2020 ARSALAN SHABESTARI
Plan Check Approved 12/3/2020 ARSALAN SHABESTARI
Issued 12/16/2020 APPLICANT
Building Plans Picked Up 10/6/2021 APPLICANT
CofO Issued-Status Void 5/31/2024 ERNESTO CORRAL
Permit Finaled-Status Void 5/31/2024 ERNESTO CORRAL
Re-Activate Permit 6/6/2024 EDWIN GREGORYONA
CofO Corrected 6/7/2024 ERNESTO CORRAL
Permit Finaled 6/7/2024 ERNESTO CORRAL

Permit Application Clearance Information

Hold Cleared 2/19/2020 LOURDES RAMIRO
Address approval Cleared 3/10/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/10/2020 ELAINE LEI
Hydrant and Access approval Cleared 3/10/2020 ROBERT DUFF
ZA Case Cleared 3/10/2020 JASON CHAN
Green Code Cleared 3/20/2020 VIVIAN LAO
Frnt yard landscape/Water mgmt Cleared 5/19/2020 TERRI OSBORNE
Permit Cleared 5/27/2020 RENZ SORIANO
Sewer availability Cleared 6/10/2020 RENZ SORIANO
DAS Clearance Cleared 9/10/2020 ARSALAN SHABESTARI
Low Impact Development Cleared 10/18/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/23/2020 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 1/4/2022 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 1/14/2022 Approved EDWIN GREGORYONA
METHANE-Subgrade 1/21/2022 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 1/31/2022 Approved EDWIN GREGORYONA
Deputy Shotcrete 2/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/8/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/8/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Methane Barrier 2/9/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 2/23/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 2/23/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 2/23/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 2/23/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Other (see comments) 3/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 3/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 3/16/2022 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 3/16/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/22/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 3/22/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 3/22/2022 Partial Inspection EDWIN GREGORYONA
METHANE-Subgrade 3/22/2022 Partial Inspection EDWIN GREGORYONA
Deputy Other (see comments) 3/25/2022 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 3/25/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 3/25/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 3/25/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 3/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 3/25/2022 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 4/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 4/8/2022 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 4/12/2022 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 4/13/2022 Partial Approval EDWIN GREGORYONA
METHANE-Rough 4/13/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Subgrade 4/13/2022 Approved EDWIN GREGORYONA
Deputy Methane Barrier 4/14/2022 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 4/19/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/21/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 4/21/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 4/21/2022 Approved EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/19/2022 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/23/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/7/2022 Partial Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 6/22/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/12/2022 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 10/12/2022 Approved EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 11/17/2022 Conditional Approval MICHAEL ROSENBERG
Interior/Exterior Lathing 12/8/2022 Approved EDWIN GREGORYONA
Deputy Methane Barrier 2/28/2023 Conditional Approval MICHAEL ROSENBERG
METHANE-Rough 3/3/2023 Approved EDWIN GREGORYONA
Green Building Rough 3/17/2023 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/17/2023 Approved EDWIN GREGORYONA
Wood Frame 3/17/2023 Approved EDWIN GREGORYONA
Insulation 4/4/2023 Approved EDWIN GREGORYONA
Drywall Nailing 4/19/2023 Approved EDWIN GREGORYONA
Special/Order Compliance 4/19/2023 Corrections Issued EDWIN GREGORYONA
Interior/Exterior Lathing 5/1/2023 No Access for Inspection LARRY ARNICK
Interior/Exterior Lathing 5/3/2023 Partial Approval EDWIN GREGORYONA
Pre-Inspection 3/12/2024 Approved EDWIN GREGORYONA
Final 3/22/2024 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 3/22/2024 Approved EDWIN GREGORYONA
Green Building Final 3/22/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 3/22/2024 Approved EDWIN GREGORYONA
Final 4/11/2024 Partial Inspection EDWIN GREGORYONA
Final 5/15/2024 Conditional Approval EDWIN GREGORYONA