3128 S HUTCHISON AVE 90034

Certificate Information: 3128 S HUTCHISON AVE 90034

Application / Permit
19010-10000-06395
Plan Check / Job No.
B19LA27498
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story SFD (27' 4" x 33' 7", 1965 sqft) with attached 1-car garage and rooftop deck at rear lot NFPA 13D Fire Spinkler is required . 2 OF 2
Permit Issued
Issued on 8/4/2023
Issuing Office
Metro
Current Status
CofO Corrected on 2/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 HELEN NGUYEN
Green Plans Picked Up 2/13/2020 APPLICANT
Corrections Issued 2/21/2020 HELEN NGUYEN
Quality Review Completed 2/23/2020 YOUNG KIM
Applicant returned to address corrections 2/24/2022 HELEN NGUYEN
Plan Check Approved 8/4/2023 NGHI SU
Issued 8/4/2023 APPLICANT
CofO in Progress 2/21/2025 MEL KHACHATOURIAN
CofO Issued-Status Void 2/21/2025 RICHARD STEINBACH
Permit Finaled-Status Void 2/21/2025 RICHARD STEINBACH
Re-Activate Permit 2/25/2025 RICHARD STEINBACH
CofO Corrected 2/25/2025 RICHARD STEINBACH
Permit Finaled 2/25/2025 RICHARD STEINBACH

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/24/2023 GILBERT URREA
Address approval Cleared 3/10/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 3/24/2023 AMAAN MALIK
Low Impact Development Cleared 3/24/2023 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/24/2023 AMAAN MALIK
Sewer availability Cleared 3/24/2023 AMAAN MALIK
Specific Plan Cleared 5/2/2023 MOHAMMAD HASAN
Zoning Information File Cleared 6/2/2023 EDMOND LEE
Specific Plan Cleared 7/12/2023 KYLE WINSTON
SB8 RUD Cleared 7/20/2023 JASON WELLS

Contact Information

Contractor Owner-Builder       ,
Engineer Goitom,, Tesfai; Lic. No.: C38166 7011 STEARNS ST      LONG BEACH, CA 90815
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/2/2023 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 10/17/2023 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 10/26/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 10/26/2023 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Partial Approval MEL KHACHATOURIAN
Green Building Rough 11/30/2023 Not Ready for Inspection MEL KHACHATOURIAN
MERV13>=Rough 11/30/2023 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 11/30/2023 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 1/17/2024 Corrections Issued MEL KHACHATOURIAN
ELECTRICAL-Rough 1/17/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 1/17/2024 Not Ready for Inspection MEL KHACHATOURIAN
MERV13>=Rough 1/17/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 1/17/2024 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 1/17/2024 Not Ready for Inspection MEL KHACHATOURIAN
Deputy Wood Construction 1/19/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 2/21/2024 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 2/23/2024 Corrections Issued MEL KHACHATOURIAN
Green Building Rough 2/23/2024 Approved MEL KHACHATOURIAN
MERV13>=Rough 2/23/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 2/23/2024 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 2/23/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 3/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 3/12/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 3/12/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 3/26/2024 Approved JESUS PINEDA
Insulation 3/26/2024 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 3/26/2024 Partial Approval JESUS PINEDA
Special/Order Compliance 3/26/2024 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 3/26/2024 Approved JESUS PINEDA
Insulation 4/1/2024 Approved MEL KHACHATOURIAN
Drywall Nailing 4/3/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 4/19/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 5/29/2024 Not Ready for Inspection MEL KHACHATOURIAN
Final 6/4/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Final 6/4/2024 Not Ready for Inspection MEL KHACHATOURIAN
MERV13>=Final 6/4/2024 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Not Ready MEL KHACHATOURIAN
Service/Power Release 6/4/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 6/4/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Final 6/13/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 6/20/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Final 6/20/2024 Corrections Issued MEL KHACHATOURIAN
PLUMBING-Final 6/27/2024 Partial Approval MEL KHACHATOURIAN
Underground Mechanical 9/18/2024 Approved STEPHANIE SWANSON
Pre-Inspection 10/15/2024 No Access for Inspection MEL KHACHATOURIAN
Sewer 10/15/2024 No Access for Inspection MEL KHACHATOURIAN
Final 11/26/2024 Corrections Issued MEL KHACHATOURIAN
Green Building Final 11/26/2024 Approved MEL KHACHATOURIAN
MERV13>=Final 11/26/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Not Ready MEL KHACHATOURIAN
Service/Power Release 11/26/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 11/26/2024 Approved MEL KHACHATOURIAN
Final 12/4/2024 No Access for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 12/4/2024 SGSOV Not Ready MEL KHACHATOURIAN
Service/Power Release 12/4/2024 No Access for Inspection MEL KHACHATOURIAN
Final 12/6/2024 Conditional Approval MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Approved MEL KHACHATOURIAN
Final 12/23/2024 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Final 1/7/2025 Approved BOBBY KEY
PLUMBING-Final 1/7/2025 Approved BOBBY KEY
Service/Power Release 1/7/2025 Approved BOBBY KEY
Pre-Inspection 1/27/2025 Approved MEL KHACHATOURIAN
Special/Order Compliance 1/28/2025 Not Ready for Inspection MEL KHACHATOURIAN
Final 2/24/2025 OK to Issue CofO MEL KHACHATOURIAN
Service/Power Release 2/24/2025 Approved MEL KHACHATOURIAN