2652 S MANSFIELD AVE 90016

Certificate Information: 2652 S MANSFIELD AVE 90016

Application / Permit
19010-10000-06386
Plan Check / Job No.
B19LA27485
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/19/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Green Plans Picked Up 1/23/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 SELLA BENYAMIN
Corrections Issued 2/4/2020 SELLA BENYAMIN
Quality Review Completed 2/4/2020 STEVEN KIM
Building Plans Picked Up 2/10/2020 APPLICANT
Plan Check Approved 3/5/2020 SELLA BENYAMIN
Issued 3/19/2020 LADBS
Refund in Progress 11/30/2020 SELENIA GARCIA
Refund Closed 11/30/2020 SELENIA GARCIA
Issued 11/30/2020 SELENIA GARCIA
CofO in Progress 5/26/2021 STUART CHAPMAN
Permit Finaled 6/16/2021 DEROLD HAUFF
CofO Issued 6/16/2021 DEROLD HAUFF
Permit Finaled 6/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/21/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/21/2020 THOMAS LANG
Green Code Cleared 2/21/2020 VIVIAN LAO
Permit Cleared 2/21/2020 THOMAS LANG
Sewer availability Cleared 2/21/2020 THOMAS LANG
Hydrant and Access approval Cleared 2/24/2020 GEORGE SUCHAND
Trees in Parkway Cleared 2/28/2020 ADRIAN SANCHEZ
Low Impact Development Cleared 3/4/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/5/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Stream Development Inc; Lic. No.: 1062718-B 669 N 3RD AVENUE      UPLAND, CA 91786

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/17/2020 Partial Inspection ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 7/21/2020 Partial Inspection DAVID CHAN
Footing/Foundation/Slab 7/21/2020 Partial Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 7/24/2020 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 7/24/2020 Not Ready for Inspection DAVID CHAN
Underground Mechanical 7/29/2020 Partial Approval DAVID CHAN
Excavation/Setback/Form/Re-Bar 8/7/2020 Approved DAVID CHAN
Pre-Inspection 8/7/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 8/14/2020 Approved DAVID CHAN
Structural Steel Frame 8/14/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 8/24/2020 Not Ready for Inspection DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 8/27/2020 Partial Approval DAVID CHAN
Structural Steel Frame 8/27/2020 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Partial Approval STUART CHAPMAN
Underground Mechanical 9/4/2020 Partial Approval STUART CHAPMAN
Underground Mechanical 9/8/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/23/2020 Partial Approval DAVID CHAN
Wood Frame 9/28/2020 Partial Approval DAVID CHAN
ELECTRICAL-Rough 10/5/2020 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Partial Approval JOSEPH MCGARRY
HVAC-Rough 10/5/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 10/5/2020 Not Ready for Inspection JOSEPH MCGARRY
Deputy Wood Construction 10/6/2020 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 10/7/2020 Partial Inspection DONALD CRICHLOW
HVAC-Rough 10/8/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 10/9/2020 Approved DAVID CHAN
HVAC-Rough 10/9/2020 Approved DAVID CHAN
ELECTRICAL-Rough 10/13/2020 Approved DAVID CHAN
HVAC-Rough 10/13/2020 Approved DAVID CHAN
PLUMBING-Rough 10/13/2020 Not Ready for Inspection DAVID CHAN
PLUMBING-Rough 10/16/2020 Approved DAVID CHAN
PLUMBING-Rough 10/21/2020 Approved DAVID CHAN
Shower Pan 10/21/2020 Corrections Issued DAVID CHAN
Shower Pan 10/29/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 11/2/2020 Not Ready for Inspection DAVID CHAN
Interior/Exterior Lathing 11/2/2020 Not Ready for Inspection DAVID CHAN
Verify Sprinkler Sign Off 11/2/2020 Not Ready for Inspection DAVID CHAN
Interior/Exterior Lathing 11/6/2020 Not Ready for Inspection DAVID CHAN
Wood Frame 11/6/2020 Not Ready for Inspection DAVID CHAN
BUILDING-Rough-Frame 11/12/2020 Partial Approval DAVID CHAN
Green Building Rough 11/12/2020 Not Ready for Inspection DAVID CHAN
Insulation 11/12/2020 Not Ready for Inspection DAVID CHAN
Interior/Exterior Lathing 11/12/2020 Partial Approval DAVID CHAN
Verify Sprinkler Sign Off 11/12/2020 Not Ready for Inspection DAVID CHAN
BUILDING-Rough-Frame 11/17/2020 Corrections Issued SCOTT FINNILA
Insulation 11/17/2020 Partial Inspection SCOTT FINNILA
Insulation 11/20/2020 Conditional Approval DAVID CHAN
BUILDING-Rough-Frame 11/24/2020 Approved DAVID CHAN
Drywall Nailing 11/24/2020 Partial Approval DAVID CHAN
Green Building Rough 11/24/2020 Approved DAVID CHAN
Verify Sprinkler Sign Off 11/24/2020 Approved DAVID CHAN
Deputy Wood Construction 11/25/2020 No Access for Inspection ELMER BLAND
Drywall Nailing 11/30/2020 Not Ready for Inspection DAVID CHAN
Wood Frame 11/30/2020 Approved DAVID CHAN
Deputy Wood Construction 12/2/2020 No Access for Inspection ELMER BLAND
Drywall Nailing 12/4/2020 Approved DAVID CHAN
Interior/Exterior Lathing 12/4/2020 Approved DAVID CHAN
ELECTRICAL-Final 1/22/2021 Corrections Issued DAVID FEILER
HVAC-Final 1/22/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Final 1/26/2021 Approved DAVID FEILER
HVAC-Final 1/26/2021 Not Ready for Inspection DAVID FEILER
HVAC-Final 2/2/2021 Approved STUART CHAPMAN
PLUMBING-Final 2/2/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 2/5/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Final 2/25/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Final 3/17/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Approved STUART CHAPMAN
Final 3/31/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Final 3/31/2021 Approved STUART CHAPMAN
Service/Power Release 3/31/2021 Approved STUART CHAPMAN
Smoke Detectors 3/31/2021 Approved STUART CHAPMAN
Final 5/25/2021 OK to Issue CofO STUART CHAPMAN