2652 S MANSFIELD AVE 90016
Certificate Information: 2652 S MANSFIELD AVE 90016
- Application / Permit
- 19010-10000-06386
- Plan Check / Job No.
- B19LA27485
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/19/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 1/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | SELLA BENYAMIN |
| Corrections Issued | 2/4/2020 | SELLA BENYAMIN |
| Quality Review Completed | 2/4/2020 | STEVEN KIM |
| Building Plans Picked Up | 2/10/2020 | APPLICANT |
| Plan Check Approved | 3/5/2020 | SELLA BENYAMIN |
| Issued | 3/19/2020 | LADBS |
| Refund in Progress | 11/30/2020 | SELENIA GARCIA |
| Refund Closed | 11/30/2020 | SELENIA GARCIA |
| Issued | 11/30/2020 | SELENIA GARCIA |
| CofO in Progress | 5/26/2021 | STUART CHAPMAN |
| Permit Finaled | 6/16/2021 | DEROLD HAUFF |
| CofO Issued | 6/16/2021 | DEROLD HAUFF |
| Permit Finaled | 6/16/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/21/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2020 | THOMAS LANG |
| Green Code | Cleared | 2/21/2020 | VIVIAN LAO |
| Permit | Cleared | 2/21/2020 | THOMAS LANG |
| Sewer availability | Cleared | 2/21/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 2/24/2020 | GEORGE SUCHAND |
| Trees in Parkway | Cleared | 2/28/2020 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 3/4/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/5/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Stream Development Inc; Lic. No.: 1062718-B | 669 N 3RD AVENUE UPLAND, CA 91786 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/17/2020 | Partial Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 7/21/2020 | Partial Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 7/21/2020 | Partial Inspection | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 7/24/2020 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 7/24/2020 | Not Ready for Inspection | DAVID CHAN |
| Underground Mechanical | 7/29/2020 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 8/7/2020 | Approved | DAVID CHAN |
| Pre-Inspection | 8/7/2020 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 8/14/2020 | Approved | DAVID CHAN |
| Structural Steel Frame | 8/14/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2020 | Not Ready for Inspection | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2020 | Partial Approval | DAVID CHAN |
| Structural Steel Frame | 8/27/2020 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 9/4/2020 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 9/8/2020 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2020 | Partial Approval | DAVID CHAN |
| Wood Frame | 9/28/2020 | Partial Approval | DAVID CHAN |
| ELECTRICAL-Rough | 10/5/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2020 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 10/5/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/5/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deputy Wood Construction | 10/6/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 10/7/2020 | Partial Inspection | DONALD CRICHLOW |
| HVAC-Rough | 10/8/2020 | Corrections Issued | DAVID CHAN |
| ELECTRICAL-Rough | 10/9/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 10/9/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Rough | 10/13/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 10/13/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 10/13/2020 | Not Ready for Inspection | DAVID CHAN |
| PLUMBING-Rough | 10/16/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 10/21/2020 | Approved | DAVID CHAN |
| Shower Pan | 10/21/2020 | Corrections Issued | DAVID CHAN |
| Shower Pan | 10/29/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 11/2/2020 | Not Ready for Inspection | DAVID CHAN |
| Interior/Exterior Lathing | 11/2/2020 | Not Ready for Inspection | DAVID CHAN |
| Verify Sprinkler Sign Off | 11/2/2020 | Not Ready for Inspection | DAVID CHAN |
| Interior/Exterior Lathing | 11/6/2020 | Not Ready for Inspection | DAVID CHAN |
| Wood Frame | 11/6/2020 | Not Ready for Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 11/12/2020 | Partial Approval | DAVID CHAN |
| Green Building Rough | 11/12/2020 | Not Ready for Inspection | DAVID CHAN |
| Insulation | 11/12/2020 | Not Ready for Inspection | DAVID CHAN |
| Interior/Exterior Lathing | 11/12/2020 | Partial Approval | DAVID CHAN |
| Verify Sprinkler Sign Off | 11/12/2020 | Not Ready for Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 11/17/2020 | Corrections Issued | SCOTT FINNILA |
| Insulation | 11/17/2020 | Partial Inspection | SCOTT FINNILA |
| Insulation | 11/20/2020 | Conditional Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 11/24/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 11/24/2020 | Partial Approval | DAVID CHAN |
| Green Building Rough | 11/24/2020 | Approved | DAVID CHAN |
| Verify Sprinkler Sign Off | 11/24/2020 | Approved | DAVID CHAN |
| Deputy Wood Construction | 11/25/2020 | No Access for Inspection | ELMER BLAND |
| Drywall Nailing | 11/30/2020 | Not Ready for Inspection | DAVID CHAN |
| Wood Frame | 11/30/2020 | Approved | DAVID CHAN |
| Deputy Wood Construction | 12/2/2020 | No Access for Inspection | ELMER BLAND |
| Drywall Nailing | 12/4/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 12/4/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Final | 1/22/2021 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 1/22/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 1/26/2021 | Approved | DAVID FEILER |
| HVAC-Final | 1/26/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Final | 2/2/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 2/2/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 2/5/2021 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 2/25/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 3/17/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2021 | SGSOV Approved | STUART CHAPMAN |
| Final | 3/31/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 3/31/2021 | Approved | STUART CHAPMAN |
| Service/Power Release | 3/31/2021 | Approved | STUART CHAPMAN |
| Smoke Detectors | 3/31/2021 | Approved | STUART CHAPMAN |
| Final | 5/25/2021 | OK to Issue CofO | STUART CHAPMAN |