4854 E BUCHANAN ST 90042

Certificate Information: 4854 E BUCHANAN ST 90042

Application / Permit
19010-10000-06359
Plan Check / Job No.
B19LA27455
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Proposed 1 story single family dwelling with an attached 2-car garage. ***REQD TO BE SPRINKLERED PER NFPA 13D*** 1 of 3
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 4/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 MICHAEL LOPEZ
Corrections Issued 2/19/2020 MICHAEL LOPEZ
Quality Review Completed 2/20/2020 QUAN NGHIEM
Green Plans Picked Up 7/17/2020 APPLICANT
Applicant returned to address corrections 6/22/2021 MICHAEL LOPEZ
Applicant returned to address corrections 11/1/2021 MICHAEL LOPEZ
Applicant returned to address corrections 2/15/2022 MICHAEL LOPEZ
Plan Check Approved 3/1/2022 MICHAEL LOPEZ
Issued 3/2/2022 APPLICANT
Building Plans Picked Up 3/3/2022 APPLICANT
CofO in Progress 4/9/2025 DAVID WILLIAMS
Permit Finaled 4/13/2025 DEROLD HAUFF
CofO Issued 4/13/2025 DEROLD HAUFF
Permit Finaled 4/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/1/2020 KURT CORRAL
Trees in Parkway Cleared 6/25/2020 JOHN KIM
BHO/Hillside ordinance Cleared 7/8/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/8/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 7/10/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 7/10/2020 CECILIO NAVARRO
Permit Cleared 7/10/2020 CECILIO NAVARRO
Sewer availability Cleared 7/13/2020 CECILIO NAVARRO
Green Code Cleared 7/16/2020 COLIN LOREDO
Low Impact Development Cleared 7/31/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/23/2020 CELINA MORENO
Excavation more than 5-ft deep Cleared 2/15/2022 CALOSHA APPROVED
GPI Written Notices Cleared 2/15/2022 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 2/15/2022 ROBERT HUGHES

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Allen C; Lic. No.: GE2781 11823 SLAUSON AVE STE 46      SANTA FE SPRINGS, CA 90670
Engineer Madrigal,, Juan Jose; Lic. No.: S5379 1447 S VALLEY CENTER AVE      GLENDORA, CA 91740
Engineer Millot,, Gilberto; Lic. No.: C53464 860 N VICEROY AVE      COVINA, CA 91723

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/15/2023 Approved ROY SPAULDING
Footing/Foundation/Slab 11/15/2023 Approved ROY SPAULDING
Light Gage Steel Frame 11/21/2023 Approved ROY SPAULDING
Deputy Reinf. Concrete 11/22/2023 Conditional Approval ROY SPAULDING
Light Gage Steel Frame 11/29/2023 Approved ROY SPAULDING
Deputy Reinf. Concrete 11/30/2023 Conditional Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 12/19/2023 Approved ROY SPAULDING
Footing/Foundation/Slab 12/19/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 1/12/2024 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 1/12/2024 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/16/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/22/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 3/22/2024 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 3/22/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/26/2024 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 3/26/2024 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 3/26/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 3/26/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 4/1/2024 Approved BRENDAN MORELLI
Insulation 4/1/2024 Approved BRENDAN MORELLI
Interior/Exterior Lathing 4/1/2024 Partial Approval BRENDAN MORELLI
Drywall Nailing 4/10/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/25/2024 Approved ALIZAH MAYAGOITIA
Shower Pan 4/25/2024 Approved ALIZAH MAYAGOITIA
Sewer 8/20/2024 Approved ALIZAH MAYAGOITIA
Final 1/24/2025 Corrections Issued OSVALDO PARAMO
Green Building Final 1/24/2025 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 1/24/2025 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 1/24/2025 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 3/26/2025 Approved DAVID WILLIAMS
HVAC-Final 3/26/2025 Approved DAVID WILLIAMS
Final 4/8/2025 OK to Issue CofO DAVID WILLIAMS
Green Building Final 4/8/2025 Approved DAVID WILLIAMS
PLUMBING-Final 4/8/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV No Gas DAVID WILLIAMS
Service/Power Release 4/8/2025 Approved DAVID WILLIAMS
Smoke Detectors 4/8/2025 Approved DAVID WILLIAMS