1131 W BROWNING BLVD 90037
Certificate Information: 1131 W BROWNING BLVD 90037
- Application / Permit
- 19010-10000-06352
- Plan Check / Job No.
- B19LA27447
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 1/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | SELLA BENYAMIN |
| Corrections Issued | 2/4/2020 | SELLA BENYAMIN |
| Quality Review Completed | 2/4/2020 | STEVEN KIM |
| Building Plans Picked Up | 2/7/2020 | APPLICANT |
| Plan Check Approved | 6/26/2020 | SELLA BENYAMIN |
| Issued | 12/12/2022 | APPLICANT |
| CofO in Progress | 6/3/2024 | SABAS ALONSO |
| CofO Issued | 6/6/2024 | DEROLD HAUFF |
| Permit Finaled | 6/6/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 2/12/2020 | VIVIAN LAO |
| Trees in Parkway | Cleared | 2/18/2020 | JOHN KIM |
| ZI | Cleared | 2/21/2020 | JASON CHAN |
| ZI | Cleared | 2/21/2020 | JASON CHAN |
| Address approval | Cleared | 5/28/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/1/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 6/4/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/8/2020 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 6/15/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/31/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 8/3/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 8/3/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/3/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 8/3/2023 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 8/3/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 8/18/2023 | Approved | STUART CHAPMAN |
| Shower Pan | 8/18/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/22/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/22/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/22/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/22/2023 | Partial Approval | SABAS ALONSO |
| Verify Sprinkler Sign Off | 8/22/2023 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/28/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 8/28/2023 | Approved | SABAS ALONSO |
| Insulation | 9/6/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 9/14/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/17/2023 | Approved | JOSH MEISTER |
| Underground Mechanical | 12/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/17/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 1/25/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/16/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 4/16/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 4/16/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 4/16/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 5/2/2024 | Approved | SABAS ALONSO |
| Final | 5/2/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 5/2/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 5/2/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 5/21/2024 | Approved | SABAS ALONSO |
| Final | 5/21/2024 | Corrections Issued | SABAS ALONSO |
| Gas Test | 5/21/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 5/21/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 5/21/2024 | Approved | SABAS ALONSO |
| Final | 5/23/2024 | OK to Issue CofO | SABAS ALONSO |