1131 W BROWNING BLVD 90037

Certificate Information: 1131 W BROWNING BLVD 90037

Application / Permit
19010-10000-06352
Plan Check / Job No.
B19LA27447
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Green Plans Picked Up 1/16/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 SELLA BENYAMIN
Corrections Issued 2/4/2020 SELLA BENYAMIN
Quality Review Completed 2/4/2020 STEVEN KIM
Building Plans Picked Up 2/7/2020 APPLICANT
Plan Check Approved 6/26/2020 SELLA BENYAMIN
Issued 12/12/2022 APPLICANT
CofO in Progress 6/3/2024 SABAS ALONSO
CofO Issued 6/6/2024 DEROLD HAUFF
Permit Finaled 6/6/2024 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 2/12/2020 VIVIAN LAO
Trees in Parkway Cleared 2/18/2020 JOHN KIM
ZI Cleared 2/21/2020 JASON CHAN
ZI Cleared 2/21/2020 JASON CHAN
Address approval Cleared 5/28/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 5/29/2020 CECILIO NAVARRO
Sewer availability Cleared 6/1/2020 CECILIO NAVARRO
Low Impact Development Cleared 6/4/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/8/2020 RENZ SORIANO
Hydrant and Access approval Cleared 6/15/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/16/2023 Approved SABAS ALONSO
Underground Mechanical 3/31/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/19/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 8/3/2023 Corrections Issued SABAS ALONSO
Green Building Rough 8/3/2023 Approved SABAS ALONSO
HVAC-Rough 8/3/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 8/3/2023 Corrections Issued SABAS ALONSO
Shower Pan 8/3/2023 Corrections Issued SABAS ALONSO
PLUMBING-Rough 8/18/2023 Approved STUART CHAPMAN
Shower Pan 8/18/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/22/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 8/22/2023 Approved SABAS ALONSO
HVAC-Rough 8/22/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 8/22/2023 Partial Approval SABAS ALONSO
Verify Sprinkler Sign Off 8/22/2023 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 8/28/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 8/28/2023 Approved SABAS ALONSO
Insulation 9/6/2023 Approved JOSH MEISTER
Drywall Nailing 9/14/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 10/17/2023 Approved JOSH MEISTER
Underground Mechanical 12/18/2023 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 1/17/2024 Partial Approval SABAS ALONSO
Underground Mechanical 1/25/2024 Approved SABAS ALONSO
ELECTRICAL-Final 4/16/2024 Corrections Issued SABAS ALONSO
Green Building Final 4/16/2024 Approved SABAS ALONSO
HVAC-Final 4/16/2024 Approved SABAS ALONSO
PLUMBING-Final 4/16/2024 Approved SABAS ALONSO
ELECTRICAL-Final 5/2/2024 Approved SABAS ALONSO
Final 5/2/2024 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 5/2/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 5/2/2024 Approved SABAS ALONSO
ELECTRICAL-Final 5/21/2024 Approved SABAS ALONSO
Final 5/21/2024 Corrections Issued SABAS ALONSO
Gas Test 5/21/2024 Approved SABAS ALONSO
PLUMBING-Final 5/21/2024 Approved SABAS ALONSO
Service/Power Release 5/21/2024 Approved SABAS ALONSO
Final 5/23/2024 OK to Issue CofO SABAS ALONSO