1405-1407 W 251ST ST 90710
Certificate Information: 1405-1407 W 251ST ST 90710
- Application / Permit
- 19010-10000-06339
- Plan Check / Job No.
- B19LA27432
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 4-CAR GARAGE. AT REAR
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | MONICA RAMIREZ |
| Corrections Issued | 2/18/2020 | MONICA RAMIREZ |
| Quality Review Completed | 2/22/2020 | STANLEY RAAP |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Green Plans Picked Up | 4/9/2020 | APPLICANT |
| Applicant returned to address corrections | 7/15/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 7/30/2020 | MONICA RAMIREZ |
| Plan Check Approved | 8/5/2020 | MONICA RAMIREZ |
| Issued | 8/5/2020 | APPLICANT |
| CofO in Progress | 3/8/2022 | EUGENE CASSIDY |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
| CofO Issued | 3/11/2022 | DEROLD HAUFF |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 4/8/2020 | DONALD CRICHLOW |
| Address approval | Cleared | 4/15/2020 | ERIK BEASLEY |
| Highway dedication | Cleared | 4/15/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 5/6/2020 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 5/8/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 6/30/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/3/2020 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 9/14/2020 | Partial Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 9/23/2020 | Approved | JOHN KLARIN |
| Insulation | 10/19/2020 | Partial Inspection | JOHN KLARIN |
| PLUMBING-Rough | 10/19/2020 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Partial Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2020 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/16/2020 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 12/16/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 12/16/2020 | Approved | JOHN KLARIN |
| HVAC-Rough | 12/16/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 12/16/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 12/16/2020 | Not Ready for Inspection | JOHN KLARIN |
| Verify Sprinkler Sign Off | 12/16/2020 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/6/2021 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/6/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 1/6/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 1/6/2021 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/6/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 1/22/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 1/22/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 2/3/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 11/5/2021 | Approved | JOHN KLARIN |
| Green Building Final | 11/5/2021 | Not Ready for Inspection | JOHN KLARIN |
| HVAC-Final | 11/5/2021 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 11/5/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/25/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 1/25/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/25/2022 | Approved | EUGENE CASSIDY |
| Green Building Final | 1/25/2022 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 1/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 1/25/2022 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 1/25/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/25/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 1/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 1/25/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 1/25/2022 | Approved | EUGENE CASSIDY |
| Final | 2/7/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/7/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 2/7/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 2/7/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/28/2022 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 2/28/2022 | Conditional Approval | EUGENE CASSIDY |
| Smoke Detectors | 2/28/2022 | Approved | EUGENE CASSIDY |
| Final | 3/7/2022 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 3/7/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 3/7/2022 | Approved | EUGENE CASSIDY |