1405-1407 W 251ST ST 90710

Certificate Information: 1405-1407 W 251ST ST 90710

Application / Permit
19010-10000-06339
Plan Check / Job No.
B19LA27432
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2-STORY DUPLEX WITH ATTACHED 4-CAR GARAGE. AT REAR
Permit Issued
Issued on 8/5/2020
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 MONICA RAMIREZ
Corrections Issued 2/18/2020 MONICA RAMIREZ
Quality Review Completed 2/22/2020 STANLEY RAAP
Building Plans Picked Up 2/27/2020 APPLICANT
Green Plans Picked Up 4/9/2020 APPLICANT
Applicant returned to address corrections 7/15/2020 MONICA RAMIREZ
Applicant returned to address corrections 7/30/2020 MONICA RAMIREZ
Plan Check Approved 8/5/2020 MONICA RAMIREZ
Issued 8/5/2020 APPLICANT
CofO in Progress 3/8/2022 EUGENE CASSIDY
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 4/8/2020 DONALD CRICHLOW
Address approval Cleared 4/15/2020 ERIK BEASLEY
Highway dedication Cleared 4/15/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 5/6/2020 ERIK BEASLEY
Sewer availability Cleared 5/6/2020 ERIK BEASLEY
Hydrant and Access approval Cleared 5/8/2020 GEORGE SUCHAND
Low Impact Development Cleared 6/30/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/3/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 9/14/2020 Partial Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 9/23/2020 Approved JOHN KLARIN
Insulation 10/19/2020 Partial Inspection JOHN KLARIN
PLUMBING-Rough 10/19/2020 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 12/16/2020 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 12/16/2020 Approved JOHN KLARIN
Green Building Rough 12/16/2020 Approved JOHN KLARIN
HVAC-Rough 12/16/2020 Approved JOHN KLARIN
METHANE-Rough 12/16/2020 Approved JOHN KLARIN
PLUMBING-Rough 12/16/2020 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 12/16/2020 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 1/6/2021 Conditional Approval EUGENE CASSIDY
ELECTRICAL-Rough 1/6/2021 Approved EUGENE CASSIDY
HVAC-Rough 1/6/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 1/6/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 1/6/2021 Partial Approval EUGENE CASSIDY
Insulation 1/22/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 1/22/2021 Approved JOHN KLARIN
Drywall Nailing 2/3/2021 Approved JOHN KLARIN
ELECTRICAL-Final 11/5/2021 Approved JOHN KLARIN
Green Building Final 11/5/2021 Not Ready for Inspection JOHN KLARIN
HVAC-Final 11/5/2021 Corrections Issued JOHN KLARIN
PLUMBING-Final 11/5/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/25/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 1/25/2022 Not Ready for Inspection EUGENE CASSIDY
Final 1/25/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 1/25/2022 Approved EUGENE CASSIDY
Green Building Final 1/25/2022 Corrections Issued EUGENE CASSIDY
HVAC-Final 1/25/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Barrier 1/25/2022 Approved EUGENE CASSIDY
METHANE-Subgrade 1/25/2022 Approved EUGENE CASSIDY
PLUMBING-Final 1/25/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/25/2022 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 1/25/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 1/25/2022 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 1/25/2022 Approved EUGENE CASSIDY
Final 2/7/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 2/7/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Approved EUGENE CASSIDY
Service/Power Release 2/7/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 2/7/2022 Not Ready for Inspection EUGENE CASSIDY
Final 2/28/2022 Corrections Issued EUGENE CASSIDY
Service/Power Release 2/28/2022 Conditional Approval EUGENE CASSIDY
Smoke Detectors 2/28/2022 Approved EUGENE CASSIDY
Final 3/7/2022 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 3/7/2022 Approved EUGENE CASSIDY
Service/Power Release 3/7/2022 Approved EUGENE CASSIDY