1007-1009 E 73RD ST 90001
Certificate Information: 1007-1009 E 73RD ST 90001
- Application / Permit
- 19010-10000-06336
- Plan Check / Job No.
- B19LA27429
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 69'0"X25'0" 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT & 2-CAR ATTACHED GARAGE AT REAR.NFPA 13D FIRE SPRINKLERS REQ'D THROUGHOUT
- Permit Issued
- Issued on 7/13/2020
- Issuing Office
- Current Status
- CofO Issued on 1/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 1/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | MARVEL DELACRUZ |
| Corrections Issued | 2/1/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 2/3/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/7/2020 | APPLICANT |
| Applicant returned to address corrections | 6/18/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 7/13/2020 | HERNAN ARREOLA |
| Issued | 7/13/2020 | APPLICANT |
| CofO in Progress | 1/1/2021 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/15/2021 | DEROLD HAUFF |
| CofO Issued | 1/15/2021 | DEROLD HAUFF |
| Permit Finaled | 1/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2020 | EMIL KYUPELYAN |
| Highway dedication | Cleared | 2/18/2020 | EMIL KYUPELYAN |
| Permit | Cleared | 2/18/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 2/18/2020 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 2/21/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 5/7/2020 | MARVEL DELACRUZ |
| Trees in Parkway | Cleared | 5/12/2020 | JOHN KIM |
| ZI | Cleared | 5/18/2020 | TERRI OSBORNE |
| Low Impact Development | Cleared | 5/29/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/2/2020 | RENZ SORIANO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/22/2020 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 7/22/2020 | Approved | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 7/24/2020 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/14/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/14/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 8/17/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 8/17/2020 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/17/2020 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 9/15/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2020 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 10/16/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/16/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/16/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/16/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 10/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 10/16/2020 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/19/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/19/2020 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/19/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 10/19/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/19/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/27/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/27/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/27/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/28/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/28/2020 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/18/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Gas Test | 12/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/18/2020 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/30/2020 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/30/2020 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/30/2020 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/31/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/31/2020 | OK to Issue CofO | ALEJANDRO DE ARTOLA |