1007-1009 E 73RD ST 90001

Certificate Information: 1007-1009 E 73RD ST 90001

Application / Permit
19010-10000-06336
Plan Check / Job No.
B19LA27429
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 69'0"X25'0" 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT & 2-CAR ATTACHED GARAGE AT REAR.NFPA 13D FIRE SPRINKLERS REQ'D THROUGHOUT
Permit Issued
Issued on 7/13/2020
Issuing Office
Current Status
CofO Issued on 1/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Green Plans Picked Up 1/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 MARVEL DELACRUZ
Corrections Issued 2/1/2020 MARVEL DELACRUZ
Quality Review Completed 2/3/2020 GUANG MIN TUNG
Building Plans Picked Up 2/7/2020 APPLICANT
Applicant returned to address corrections 6/18/2020 MARVEL DELACRUZ
Plan Check Approved 7/13/2020 HERNAN ARREOLA
Issued 7/13/2020 APPLICANT
CofO in Progress 1/1/2021 ALEJANDRO DE ARTOLA
Permit Finaled 1/15/2021 DEROLD HAUFF
CofO Issued 1/15/2021 DEROLD HAUFF
Permit Finaled 1/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/18/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 2/18/2020 EMIL KYUPELYAN
Highway dedication Cleared 2/18/2020 EMIL KYUPELYAN
Permit Cleared 2/18/2020 EMIL KYUPELYAN
Sewer availability Cleared 2/18/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 2/21/2020 GEORGE SUCHAND
Green Code Cleared 5/7/2020 MARVEL DELACRUZ
Trees in Parkway Cleared 5/12/2020 JOHN KIM
ZI Cleared 5/18/2020 TERRI OSBORNE
Low Impact Development Cleared 5/29/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/2/2020 RENZ SORIANO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/22/2020 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 7/22/2020 Approved JOSEPH MCGARRY
Deputy Reinf. Concrete 7/24/2020 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/14/2020 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 8/14/2020 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 8/17/2020 Partial Approval ALEJANDRO DE ARTOLA
Sewer 8/17/2020 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 8/17/2020 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/18/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/27/2020 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 9/15/2020 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Approved DAVID FEILER
BUILDING-Rough-Frame 10/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/16/2020 Approved ALEJANDRO DE ARTOLA
Green Building Rough 10/16/2020 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 10/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 10/16/2020 Partial Approval ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 10/16/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/19/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Green Building Rough 10/19/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 10/19/2020 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 10/19/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/19/2020 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/27/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 10/27/2020 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/27/2020 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/28/2020 Approved ALEJANDRO DE ARTOLA
Green Building Rough 10/28/2020 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/18/2020 Approved ALEJANDRO DE ARTOLA
Final 12/18/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Gas Test 12/18/2020 Approved ALEJANDRO DE ARTOLA
Green Building Final 12/18/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/18/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/18/2020 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/18/2020 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/18/2020 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/18/2020 Approved ALEJANDRO DE ARTOLA
Final 12/30/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/30/2020 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/30/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/31/2020 Approved ALEJANDRO DE ARTOLA
Final 12/31/2020 OK to Issue CofO ALEJANDRO DE ARTOLA