25200-25200 1/4 S FRAMPTON AVE 90710

Certificate Information: 25200-25200 1/4 S FRAMPTON AVE 90710

Application / Permit
19010-10000-06320
Plan Check / Job No.
B19LA27410
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW TWO STORY DUPLEX WITH GARAGE. FRONT BUILDING. FULLY SPRINKLERED.
Permit Issued
Issued on 10/2/2020
Issuing Office
Current Status
CofO Issued on 4/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 SAMUEL GONZALEZ
Corrections Issued 2/3/2020 SAMUEL GONZALEZ
Quality Review Completed 2/5/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 7/31/2020 APPLICANT
Plan Check Approved 8/27/2020 SAMUEL GONZALEZ
Plan Check Approved 9/14/2020 SAMUEL GONZALEZ
Building Plans Picked Up 9/14/2020 APPLICANT
Issued 10/2/2020 APPLICANT
CofO in Progress 4/6/2022 EUGENE CASSIDY
Permit Finaled 4/12/2022 DEROLD HAUFF
CofO Issued 4/12/2022 DEROLD HAUFF
Permit Finaled 4/12/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/27/2020 JEANIE LAM
Low Impact Development Cleared 5/27/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/8/2020 CHINH DINH
Hydrant and Access approval Cleared 7/6/2020 MATTHEW CRAIG
Green Code Cleared 7/29/2020 SAMUEL GONZALEZ
"Q" conditions Cleared 7/30/2020 KENTON TRINH
Opn space landscape/Water mgmt Cleared 7/30/2020 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 7/31/2020 PAMELA TENEZA
Sewer availability Cleared 7/31/2020 PAMELA TENEZA

Contact Information

Architect Tavasci,, Robert J; Lic. No.: C26023 3351 ORANGEWOOD AVENUE      ROSSMOOR, CA 90720
Contractor Owner-Builder       ,
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Smith,, Bradley Warren; Lic. No.: S2842 PO BOX 1064      OJAI, CA 93024

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/12/2020 Approved JOHN KLARIN
Footing/Foundation/Slab 11/12/2020 Partial Approval JOHN KLARIN
METHANE-Barrier 11/12/2020 Not Ready for Inspection JOHN KLARIN
METHANE-Subgrade 11/12/2020 Partial Approval JOHN KLARIN
Underground Mechanical 11/12/2020 Partial Approval JOHN KLARIN
Deputy Reinf. Concrete 11/13/2020 Approved JOHN KLARIN
Deputy Methane Barrier 11/16/2020 Corrections Issued JOHN KLARIN
Deputy Methane Barrier 11/17/2020 No Access for Inspection ELMER BLAND
Deputy Methane Barrier 11/18/2020 No Access for Inspection ELMER BLAND
Deputy Methane Barrier 11/19/2020 No Access for Inspection ELMER BLAND
Deputy Methane Barrier 11/20/2020 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 11/20/2020 Conditional Approval JOHN KLARIN
Excavation/Setback/Form/Re-Bar 11/20/2020 Off-Hour Fees Due
Deputy Methane Barrier 11/23/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 11/24/2020 Approved JOHN KLARIN
METHANE-Barrier 11/24/2020 Approved JOHN KLARIN
METHANE-Subgrade 11/24/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Partial Approval EUGENE CASSIDY
Pre-Inspection 1/13/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Approved JOHN KLARIN
HVAC-Rough 2/18/2021 Approved JOHN KLARIN
PLUMBING-Rough 2/18/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 2/24/2021 Approved JOHN KLARIN
METHANE-Rough 2/24/2021 Approved JOHN KLARIN
PLUMBING-Rough 2/24/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/1/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 3/1/2021 Corrections Issued EUGENE CASSIDY
Shower Pan 3/1/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 3/1/2021 Partial Approval EUGENE CASSIDY
Wood Frame 3/1/2021 Corrections Issued EUGENE CASSIDY
Insulation 3/5/2021 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 3/5/2021 Not Ready for Inspection JOHN KLARIN
Interior/Exterior Lathing 3/10/2021 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 3/23/2021 Approved JOHN KLARIN
Green Building Rough 3/23/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 3/23/2021 Approved JOHN KLARIN
Verify Sprinkler Sign Off 3/23/2021 Approved JOHN KLARIN
Wood Frame 3/23/2021 Approved JOHN KLARIN
Insulation 4/1/2021 Approved JOHN KLARIN
Drywall Nailing 4/8/2021 Corrections Issued JOHN KLARIN
Sewer 5/28/2021 Approved JOHN KLARIN
Gas Test 6/4/2021 Approved JOHN KLARIN
Underground Mechanical 6/15/2021 Partial Approval JOHN KLARIN
Underground Mechanical 8/23/2021 Approved JOHN KLARIN
ELECTRICAL-Final 9/16/2021 No Access for Inspection CRAIG DAVIS
ELECTRICAL-Final 9/20/2021 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 10/14/2021 Corrections Issued JOHN KLARIN
PLUMBING-Final 10/15/2021 Not Ready for Inspection JOHN KLARIN
Verify Rec and Parks Fee Memo 10/15/2021 Approved JOHN KLARIN
HVAC-Final 10/18/2021 Corrections Issued JOHN KLARIN
Drywall Nailing 11/15/2021 Not Ready for Inspection JOHN KLARIN
Final 11/15/2021 Corrections Issued JOHN KLARIN
Green Building Final 11/15/2021 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Not Ready JOHN KLARIN
Service/Power Release 11/15/2021 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 11/15/2021 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/2/2021 SGSOV Not Ready JOHN KLARIN
Drywall Nailing 1/6/2022 Conditional Approval JOHN KLARIN
Final 1/6/2022 Corrections Issued JOHN KLARIN
Green Building Final 1/6/2022 Not Ready for Inspection JOHN KLARIN
HVAC-Final 1/6/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/6/2022 SGSOV Not Ready JOHN KLARIN
Service/Power Release 1/6/2022 Corrections Issued JOHN KLARIN
Smoke Detectors 1/6/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 1/22/2022 Off-Hour Fees Due
HVAC-Final 1/22/2022 Off-Hour Fees Due
PLUMBING-Final 1/22/2022 Off-Hour Fees Due
Service/Power Release 1/22/2022 Off-Hour Fees Due
Drywall Nailing 1/26/2022 Not Ready for Inspection EUGENE CASSIDY
Final 1/26/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 1/26/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved EUGENE CASSIDY
Service/Power Release 1/26/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 1/26/2022 Not Ready for Inspection EUGENE CASSIDY
Drywall Nailing 2/1/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
Final 2/1/2022 Corrections Issued EUGENE CASSIDY
Gas Test 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 2/1/2022 Approved EUGENE CASSIDY
HVAC-Final 2/1/2022 Approved EUGENE CASSIDY
PLUMBING-Final 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 2/1/2022 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 2/1/2022 Approved EUGENE CASSIDY
Final 2/7/2022 Corrections Issued EUGENE CASSIDY
Service/Power Release 2/7/2022 Not Ready for Inspection EUGENE CASSIDY
Gas Test 2/9/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/10/2022 Approved EUGENE CASSIDY
Final 2/14/2022 Not Ready for Inspection EUGENE CASSIDY
Service/Power Release 2/14/2022 Approved EUGENE CASSIDY
Special/Order Compliance 3/18/2022 Corrections Issued ANSON MAGLASANG
Final 3/23/2022 Corrections Issued EUGENE CASSIDY
Final 3/30/2022 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 3/30/2022 Approved EUGENE CASSIDY
Final 4/5/2022 OK to Issue CofO EUGENE CASSIDY