1258 W LEIGHTON AVE A-C 90037
Certificate Information: 1258 W LEIGHTON AVE A-C 90037
- Application / Permit
- 19010-10000-06314
- Plan Check / Job No.
- B19LA27407
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 3 STORY 3 UNIT APARTMENT BUILDING W/ROOF DECK AT REAR OF LOT
- Permit Issued
- Issued on 3/9/2021
- Issuing Office
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | LAMAR DAVIS |
| Corrections Issued | 1/27/2020 | LAMAR DAVIS |
| Quality Review Completed | 2/7/2020 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 2/7/2020 | APPLICANT |
| Applicant returned to address corrections | 2/24/2020 | LAMAR DAVIS |
| Green Plans Picked Up | 8/4/2020 | APPLICANT |
| Applicant returned to address corrections | 8/26/2020 | LAMAR DAVIS |
| Applicant returned to address corrections | 10/1/2020 | LAMAR DAVIS |
| Plan Check Approved | 10/5/2020 | LAMAR DAVIS |
| Issued | 3/9/2021 | APPLICANT |
| Building Plans Picked Up | 3/12/2021 | APPLICANT |
| CofO in Progress | 12/29/2023 | JAMES POWERS |
| CofO Issued | 12/29/2023 | ERNESTO CORRAL |
| Permit Finaled | 12/29/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/24/2020 | LAMAR DAVIS |
| Address approval | Cleared | 2/27/2020 | JUAN ASHTON |
| Trees in Parkway | Cleared | 4/7/2020 | JOHN KIM |
| DAS Clearance | Cleared | 4/13/2020 | RONALD ALLEN |
| Building over 3-story or 36-ft | Cleared | 4/22/2020 | CALOSHA APPROVED |
| Frnt yard landscape/Water mgmt | Cleared | 6/5/2020 | KENTON TRINH |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2020 | PAMELA TENEZA |
| Sewer availability | Cleared | 6/8/2020 | PAMELA TENEZA |
| Green Code | Cleared | 6/11/2020 | DONALD CRICHLOW |
| Hydrant and Access approval | Cleared | 7/1/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 7/8/2020 | SARAH YOUSSEF |
| Permit | Cleared | 7/9/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/9/2020 | JEANIE LAM |
| Fire Marshall Fire Life Safety | Cleared | 7/31/2020 | VIDAL GARCIA |
Contact Information
| Contractor | Apel Construction Inc; Lic. No.: 1051980-B | 644 NORTH FULLER AVE 454 LOS ANGELES, CA 90036 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 10632 BALCOM AVE GRANADA HILLS, CA 91344 |
| Engineer | Rogers,, Jerome Alan; Lic. No.: L5336 | 135 N SAN GABRIEL AVE 100 SAN GABRIEL, CA 91776 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/18/2021 | Not Ready for Inspection | JAMES POWERS |
| Piling/Pier/Caisson | 10/2/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 10/4/2021 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2021 | Partial Approval | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Partial Approval | JAMES POWERS |
| Green Building Rough | 11/15/2021 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 11/15/2021 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Partial Approval | JAMES POWERS |
| Green Building Rough | 12/27/2021 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 12/27/2021 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 5/16/2022 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/23/2022 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 5/23/2022 | Not Ready for Inspection | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2022 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/25/2022 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 5/25/2022 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 6/1/2022 | Conditional Approval | ERNESTO CORRAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2022 | Approved | JAMES POWERS |
| Interior/Exterior Lathing | 6/10/2022 | Not Ready for Inspection | JAMES POWERS |
| Interior/Exterior Lathing | 6/16/2022 | Approved | JAMES POWERS |
| Insulation | 11/14/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Insulation | 11/17/2022 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 11/21/2022 | Not Ready for Inspection | GREGORY POMISH |
| Insulation | 11/23/2022 | Approved | JAMES POWERS |
| Drywall Nailing | 12/15/2022 | Approved | JAMES POWERS |
| Pre-Inspection | 1/9/2023 | Not Ready for Inspection | JAMES POWERS |
| Pre-Inspection | 12/15/2023 | Not Ready for Inspection | JAMES POWERS |
| Final | 12/21/2023 | OK for TCO | JAMES POWERS |
| Footing/Foundation/Slab | 12/21/2023 | Approved | JAMES POWERS |
| Green Building Final | 12/21/2023 | Approved | JAMES POWERS |
| Reinforced Masonry Frame | 12/21/2023 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 12/21/2023 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 12/21/2023 | Approved | JAMES POWERS |
| Wood Frame | 12/21/2023 | Approved | JAMES POWERS |
| Final | 12/27/2023 | OK to Issue CofO | JAMES POWERS |