1258 W LEIGHTON AVE A-C 90037

Certificate Information: 1258 W LEIGHTON AVE A-C 90037

Application / Permit
19010-10000-06314
Plan Check / Job No.
B19LA27407
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 3 STORY 3 UNIT APARTMENT BUILDING W/ROOF DECK AT REAR OF LOT
Permit Issued
Issued on 3/9/2021
Issuing Office
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 LAMAR DAVIS
Corrections Issued 1/27/2020 LAMAR DAVIS
Quality Review Completed 2/7/2020 HERNAN ARREOLA
Disabled Access Plans Picked Up 2/7/2020 APPLICANT
Applicant returned to address corrections 2/24/2020 LAMAR DAVIS
Green Plans Picked Up 8/4/2020 APPLICANT
Applicant returned to address corrections 8/26/2020 LAMAR DAVIS
Applicant returned to address corrections 10/1/2020 LAMAR DAVIS
Plan Check Approved 10/5/2020 LAMAR DAVIS
Issued 3/9/2021 APPLICANT
Building Plans Picked Up 3/12/2021 APPLICANT
CofO in Progress 12/29/2023 JAMES POWERS
CofO Issued 12/29/2023 ERNESTO CORRAL
Permit Finaled 12/29/2023 ERNESTO CORRAL

Permit Application Clearance Information

Miscellaneous Cleared 2/24/2020 LAMAR DAVIS
Address approval Cleared 2/27/2020 JUAN ASHTON
Trees in Parkway Cleared 4/7/2020 JOHN KIM
DAS Clearance Cleared 4/13/2020 RONALD ALLEN
Building over 3-story or 36-ft Cleared 4/22/2020 CALOSHA APPROVED
Frnt yard landscape/Water mgmt Cleared 6/5/2020 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 6/8/2020 PAMELA TENEZA
Sewer availability Cleared 6/8/2020 PAMELA TENEZA
Green Code Cleared 6/11/2020 DONALD CRICHLOW
Hydrant and Access approval Cleared 7/1/2020 KURT CORRAL
Low Impact Development Cleared 7/8/2020 SARAH YOUSSEF
Permit Cleared 7/9/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 7/9/2020 JEANIE LAM
Fire Marshall Fire Life Safety Cleared 7/31/2020 VIDAL GARCIA

Contact Information

Contractor Apel Construction Inc; Lic. No.: 1051980-B 644 NORTH FULLER AVE 454      LOS ANGELES, CA 90036
Engineer Kim,, Hosang; Lic. No.: C67288 10632 BALCOM AVE      GRANADA HILLS, CA 91344
Engineer Rogers,, Jerome Alan; Lic. No.: L5336 135 N SAN GABRIEL AVE 100      SAN GABRIEL, CA 91776
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/18/2021 Not Ready for Inspection JAMES POWERS
Piling/Pier/Caisson 10/2/2021 Off-Hour Fees Due
Footing/Foundation/Slab 10/4/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval JAMES POWERS
Green Building Rough 11/15/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 11/15/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/27/2021 Partial Approval JAMES POWERS
Green Building Rough 12/27/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 12/27/2021 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 5/16/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/23/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 5/23/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/25/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/25/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 5/25/2022 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 6/1/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Approved JAMES POWERS
Interior/Exterior Lathing 6/10/2022 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 6/16/2022 Approved JAMES POWERS
Insulation 11/14/2022 Corrections Issued RAFAEL ESPINOZA
Insulation 11/17/2022 Not Ready for Inspection JAMES POWERS
Insulation 11/21/2022 Not Ready for Inspection GREGORY POMISH
Insulation 11/23/2022 Approved JAMES POWERS
Drywall Nailing 12/15/2022 Approved JAMES POWERS
Pre-Inspection 1/9/2023 Not Ready for Inspection JAMES POWERS
Pre-Inspection 12/15/2023 Not Ready for Inspection JAMES POWERS
Final 12/21/2023 OK for TCO JAMES POWERS
Footing/Foundation/Slab 12/21/2023 Approved JAMES POWERS
Green Building Final 12/21/2023 Approved JAMES POWERS
Reinforced Masonry Frame 12/21/2023 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/21/2023 SGSOV Approved JAMES POWERS
Smoke Detectors 12/21/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 12/21/2023 Approved JAMES POWERS
Wood Frame 12/21/2023 Approved JAMES POWERS
Final 12/27/2023 OK to Issue CofO JAMES POWERS