16706 W ROSCOE BLVD 91406

Certificate Information: 16706 W ROSCOE BLVD 91406

Application / Permit
19010-10000-06142
Plan Check / Job No.
B19LA27273
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(3) Airport Building
Work Description
NEW ONE STORY AIRCRAFT HANGERS WITH SINGLE-STORY SUPPORT OFFICES.
Permit Issued
Issued on 9/25/2020
Issuing Office
Current Status
CofO Issued on 9/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/27/2019 GARO TELMI
Corrections Issued 1/6/2020 GARO TELMI
Quality Review Completed 1/16/2020 KEN GILL
Building Plans Picked Up 1/21/2020 APPLICANT
Disabled Access Plans Picked Up 2/11/2020 APPLICANT
Applicant returned to address corrections 3/11/2020 GARO TELMI
Applicant returned to address corrections 4/8/2020 GARO TELMI
Applicant returned to address corrections 4/21/2020 GARO TELMI
Applicant returned to address corrections 4/24/2020 GARO TELMI
Green Plans Picked Up 8/18/2020 APPLICANT
Plan Check Approved 9/15/2020 GARO TELMI
Issued 9/25/2020 APPLICANT
TCO Issued (Expire Date: 02-12-2022) 8/16/2021 JEFFREY DURAN
CofO in Progress 9/29/2021 RICKEY JACKSON
Permit Finaled 9/29/2021 RICKEY JACKSON
CofO Issued 9/29/2021 RICKEY JACKSON
Permit Finaled 9/29/2021 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 1/29/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/29/2020 ADRIAN CASTRO
Miscellaneous Cleared 1/29/2020 PABLO ESTRADA
Hydrant and Access approval Cleared 3/4/2020 ROBERT DUFF
Miscellaneous Cleared 4/2/2020 HERMINIGILDO AGUSTIN
ZI Cleared 4/2/2020 HERMINIGILDO AGUSTIN
ZI Cleared 4/2/2020 HERMINIGILDO AGUSTIN
Driveway location Cleared 4/6/2020 SHEILA AHORAIAN
Internal circulation Cleared 4/6/2020 SHEILA AHORAIAN
Green Code Cleared 4/14/2020 KHEDER ALRAZAA
"Q" conditions Cleared 5/5/2020 VINCENT QUITORIANO
Miscellaneous Cleared 5/5/2020 VINCENT QUITORIANO
Miscellaneous Cleared 5/5/2020 VINCENT QUITORIANO
Prkng lot landscape/Water mgmt Cleared 5/5/2020 VINCENT QUITORIANO
Site Plan review Cleared 5/5/2020 VINCENT QUITORIANO
ZI Cleared 5/5/2020 VINCENT QUITORIANO
"T" removal Cleared 5/6/2020 VINCENT QUITORIANO
Metro Rail approval Cleared 5/15/2020 GARO TELMI
City owned building/parcel Cleared 6/17/2020 HAROOT AVANESIAN
DAS Clearance Cleared 6/24/2020 GARO TELMI
Airport buildings Cleared 7/7/2020 ANDREW KO
Fire Marshall Fire Life Safety Cleared 7/7/2020 ANDREW KO
Low Impact Development Cleared 8/17/2020 AMMAR ELTAWIL
Body shop Cleared 8/21/2020 SCAQMD APPROVED
Building over 3-story or 36-ft Cleared 8/21/2020 CALOSHA APPROVED
Combustion equipment Cleared 8/21/2020 SCAQMD APPROVED
Internal combustion engine Cleared 8/21/2020 SCAQMD APPROVED
Solvents/fuels Cleared 8/21/2020 SCAQMD APPROVED
Drainage to Storm Drain Cleared 9/8/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 9/8/2020 ADRIAN CASTRO
Sewer availability Cleared 9/8/2020 ADRIAN CASTRO
Highway dedication Cleared 9/10/2020 ADRIAN CASTRO
Permit Cleared 9/10/2020 ADRIAN CASTRO
Trees in Parkway Cleared 9/14/2020 JOHN KIM

Contact Information

Contractor Viole' T Construction Co Inc; Lic. No.: 283354-B 18716 OXNARD ST      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/9/2020 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/9/2020 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/16/2020 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 10/21/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 10/22/2020 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/22/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 10/23/2020 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 10/23/2020 No Access for Inspection JEFFREY FULTON
Footing/Foundation/Slab 11/5/2020 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/6/2020 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Concrete 11/12/2020 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 11/12/2020 Partial Inspection JEFFREY FULTON
Structural Steel Frame 11/12/2020 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/16/2020 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/20/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 11/23/2020 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 12/7/2020 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/8/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 12/15/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/15/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/16/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/17/2020 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 12/18/2020 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 1/4/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/4/2021 Partial Inspection JEFFREY FULTON
Structural Steel Frame 1/4/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/4/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/18/2021 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 2/18/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 2/18/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 2/24/2021 Partial Inspection JEFFREY FULTON
Insulation 2/24/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/2/2021 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 3/2/2021 Partial Approval DANIEL VARNUM
Insulation 3/16/2021 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 3/16/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 3/22/2021 Approved HAMID PISHEHVAR
Insulation 3/22/2021 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 4/9/2021 Partial Inspection JEFFREY FULTON
Structural Steel Frame 4/13/2021 Partial Inspection JEFFREY FULTON
Special/Order Compliance 5/12/2021 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 5/18/2021 Partial Inspection JEFFREY FULTON
Special/Order Compliance 5/20/2021 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 5/24/2021 Approved ROBERT DAVIS
Footing/Foundation/Slab 6/4/2021 Partial Inspection JEFFREY FULTON
Special/Order Compliance 7/26/2021 Partial Inspection JEFFREY FULTON
Final 8/3/2021 Partial Inspection JEFFREY FULTON
Final 8/6/2021 Partial Inspection JEFFREY FULTON
Final 8/9/2021 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 8/9/2021 Approved JEFFREY FULTON
Green Building Final 8/9/2021 Approved JEFFREY FULTON
Green Building Rough 8/9/2021 Approved JEFFREY FULTON
Reinforced Masonry Frame 8/9/2021 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV No Gas JEFFREY FULTON
Smoke Detectors 8/9/2021 Approved JEFFREY FULTON
Special/Order Compliance 8/9/2021 Approved JEFFREY FULTON
Verify Sprinkler Sign Off 8/9/2021 Approved JEFFREY FULTON
Final 9/29/2021 OK to Issue CofO RICKEY JACKSON