2821 S VIRGINIA ROAD 90016

Certificate Information: 2821 S VIRGINIA ROAD 90016

Application / Permit
19010-10000-06138
Plan Check / Job No.
B19LA27270
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 3-STORY SFD WITH 2-CAR GARAGE AT FRONT OF LOT
Permit Issued
Issued on 12/30/2020
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/17/2020 SINA KHOSRAVI
Corrections Issued 1/22/2020 SINA KHOSRAVI
Quality Review Completed 1/26/2020 YOUNG KIM
Applicant returned to address corrections 3/11/2020 SINA KHOSRAVI
Green Plans Picked Up 10/5/2020 APPLICANT
Applicant returned to address corrections 11/5/2020 SINA KHOSRAVI
Plan Check Approved 11/6/2020 SINA KHOSRAVI
Building Plans Picked Up 11/9/2020 APPLICANT
Issued 12/30/2020 APPLICANT
CofO in Progress 10/21/2022 STUART CHAPMAN
Permit Finaled 10/29/2022 DEROLD HAUFF
CofO Issued 10/29/2022 DEROLD HAUFF
Permit Finaled 10/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/11/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 2/11/2020 ERIK BEASLEY
Sewer availability Cleared 2/11/2020 ERIK BEASLEY
Green Code Cleared 3/5/2020 NEGAR NEJAD
Hydrant and Access approval Cleared 3/13/2020 JOHN CONNEALLY
Low Impact Development Cleared 8/2/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/14/2020 ROSA SILVA

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: C22356 3435 WILSHIRE BLVD #2905      LOS ANGELES, CA 90010
Contractor Advanced Construction; Lic. No.: 801955-B 18841 PASADERO DRIVE      TARZANA, CA 91356
Engineer Hakemi,, Fahim; Lic. No.: S5160 26982 MARBELLA      MISSION VIEJO, CA 92691

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/28/2021 Approved STUART CHAPMAN
Underground Mechanical 2/18/2021 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 3/9/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 5/25/2021 Not Ready for Inspection STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 6/4/2021 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 6/4/2021 Approved KATHRYN BUTTERWORTH
Drywall Nailing 7/7/2021 Corrections Issued KATHRYN BUTTERWORTH
Green Building Rough 7/7/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Drywall Nailing 7/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 7/29/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/30/2021 Partial Approval DAVID FEILER
Verify Sprinkler Sign Off 7/30/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 10/4/2021 Partial Approval STUART CHAPMAN
Green Building Rough 10/4/2021 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 10/4/2021 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 10/29/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 10/29/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval STUART CHAPMAN
Green Building Rough 10/29/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 10/29/2021 Approved STUART CHAPMAN
PLUMBING-Rough 10/29/2021 Not Ready for Inspection STUART CHAPMAN
Rough-Elec/Plmb/HVAC 10/29/2021 Partial Approval STUART CHAPMAN
Verify Sprinkler Sign Off 10/29/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 11/5/2021 Approved STUART CHAPMAN
Green Building Rough 11/5/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 11/5/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 11/5/2021 Approved STUART CHAPMAN
Insulation 11/19/2021 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 11/19/2021 Partial Approval STUART CHAPMAN
Drywall Nailing 12/14/2021 Not Ready for Inspection STUART CHAPMAN
Drywall Nailing 1/21/2022 Partial Inspection ALFREDO BALANDRA
Sewer 2/8/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 4/19/2022 Corrections Issued STUART CHAPMAN
PLUMBING-Final 4/19/2022 Corrections Issued STUART CHAPMAN
Drywall Nailing 7/18/2022 Approved STUART CHAPMAN
Final 7/18/2022 Not Ready for Inspection STUART CHAPMAN
Green Building Final 7/18/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/18/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 7/18/2022 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 7/18/2022 Approved STUART CHAPMAN
HVAC-Final 7/19/2022 Approved STUART CHAPMAN
Final 7/27/2022 Corrections Issued STUART CHAPMAN
Service/Power Release 7/27/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 10/21/2022 Approved STUART CHAPMAN
Final 10/21/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 10/21/2022 Approved STUART CHAPMAN
PLUMBING-Final 10/21/2022 Approved STUART CHAPMAN
Service/Power Release 10/21/2022 Approved STUART CHAPMAN