2929 S LA BREA AVE 90016
Certificate Information: 2929 S LA BREA AVE 90016
- Application / Permit
- 19010-10000-06133
- Plan Check / Job No.
- B19LA27264
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED THREE STORY SINGLE FAMILY DWELLING .
- Permit Issued
- Issued on 5/21/2021
- Issuing Office
- Current Status
- CofO Issued on 4/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | ARMEN JIVALAGIAN |
| Corrections Issued | 2/19/2020 | ARMEN JIVALAGIAN |
| Quality Review Completed | 2/25/2020 | TIEN JEN WANG |
| Green Plans Picked Up | 3/17/2020 | APPLICANT |
| Applicant returned to address corrections | 4/3/2020 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 4/8/2020 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 8/26/2020 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 10/7/2020 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/12/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 2/3/2021 | ARMEN JIVALAGIAN |
| Plan Check Approved | 2/4/2021 | ARMEN JIVALAGIAN |
| Issued | 5/21/2021 | APPLICANT |
| Building Plans Picked Up | 6/8/2021 | APPLICANT |
| CofO in Progress | 4/20/2023 | JOSE AVILA |
| Permit Finaled | 4/24/2023 | DEROLD HAUFF |
| CofO Issued | 4/24/2023 | DEROLD HAUFF |
| Permit Finaled | 4/24/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/22/2020 | GEORGE SUCHAND |
| Construction near power lines | Cleared | 7/20/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/20/2020 | RIDWAN HARDY |
| Address approval | Cleared | 8/4/2020 | RENZ SORIANO |
| Frnt yard landscape/Water mgmt | Cleared | 8/4/2020 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2020 | RENZ SORIANO |
| Permit | Cleared | 8/6/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 8/6/2020 | RENZ SORIANO |
| Driveway location | Cleared | 8/12/2020 | MOHAMMAD HASAN |
| Trees in Parkway | Cleared | 8/25/2020 | JOHN KIM |
| Highway dedication | Cleared | 8/31/2020 | RENZ SORIANO |
| Low Impact Development | Cleared | 10/6/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/6/2020 | RENZ SORIANO |
| Green Code | Cleared | 2/4/2021 | VIVIAN LAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 1453 14TH ST STE A SANTA MONICA, CA 90404 |
| Engineer | Shah,, Satish Sobhagchand; Lic. No.: C56112 | 7611 BLACK STAR LN LA PALMA, CA 90623 |
| Engineer | Upasani,, Mohan B; Lic. No.: GE2301 | 20 SOVENTE IRVINE, CA 92606 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/20/2021 | Partial Inspection | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 7/27/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/10/2021 | Partial Approval | DAVID FEILER |
| Deputy Steel/Welding | 8/23/2021 | Conditional Approval | CALEB MEISTER |
| Deputy Steel/Welding | 8/24/2021 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Steel/Welding | 8/24/2021 | Conditional Approval | JESUS PINEDA |
| Underground Mechanical | 9/3/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 9/28/2021 | Approved | SCOTT FINNILA |
| Footing/Foundation/Slab | 9/28/2021 | Approved | SCOTT FINNILA |
| Structural Steel Frame | 9/28/2021 | Approved | SCOTT FINNILA |
| Deputy Steel/Welding | 10/13/2021 | Conditional Approval | JUSTIN HAWLEY |
| Deputy Steel/Welding | 10/15/2021 | Approved | LILIANA PORTILLO |
| Deputy Steel/Welding | 10/21/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 11/1/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2021 | Corrections Issued | STUART CHAPMAN |
| Wood Frame | 11/19/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Wood Construction | 11/23/2021 | Conditional Approval | JOSE AVILA |
| Deputy Steel/Welding | 12/1/2021 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Approved | JOSE AVILA |
| Wood Frame | 12/7/2021 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 12/28/2021 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 1/26/2022 | Corrections Issued | JOSE AVILA |
| Insulation | 1/26/2022 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 1/26/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 1/31/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 2/8/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 2/8/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/9/2022 | Corrections Issued | JOSE AVILA |
| Wood Frame | 2/9/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 2/18/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 2/18/2022 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 2/18/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/22/2022 | Partial Approval | JOSE AVILA |
| Green Building Rough | 2/22/2022 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 2/22/2022 | Approved | JOSE AVILA |
| Insulation | 3/8/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 5/4/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/13/2022 | Approved | JOSE AVILA |
| Shower Pan | 7/13/2022 | Corrections Issued | JOSE AVILA |
| Shower Pan | 7/25/2022 | Approved | JOSE AVILA |
| Sewer | 9/12/2022 | Approved | JOSE AVILA |
| Underground Mechanical | 9/16/2022 | Corrections Issued | JOSE AVILA |
| Wood Frame | 9/16/2022 | Approved | JOSE AVILA |
| Underground Mechanical | 9/23/2022 | Approved | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Approved | JOSE AVILA |
| Service/Power Release | 10/17/2022 | Partial Inspection | JOSE AVILA |
| Deputy Drilled-In Anchors | 10/18/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 11/8/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 11/8/2022 | Corrections Issued | JOSE AVILA |
| Service/Power Release | 11/8/2022 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Final | 11/29/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 11/29/2022 | Partial Approval | JOSE AVILA |
| Service/Power Release | 11/29/2022 | Not Ready for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 1/11/2023 | Approved | JOSE AVILA |
| Green Building Final | 1/11/2023 | Approved | JOSE AVILA |
| HVAC-Final | 1/11/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/11/2023 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 1/11/2023 | Approved | JOSE AVILA |
| Service/Power Release | 1/23/2023 | Approved | JOSE AVILA |
| Final | 3/16/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/16/2023 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 3/16/2023 | Not Ready for Inspection | JOSE AVILA |
| Final | 4/7/2023 | Partial Approval | JOSE AVILA |
| Final | 4/20/2023 | OK to Issue CofO | JOSE AVILA |