10611 S BROADWAY 90003
Certificate Information: 10611 S BROADWAY 90003
- Application / Permit
- 19010-10000-06127
- Plan Check / Job No.
- B19LA27251
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Proposed 2 story single family dwelling. 1 of 2
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | MICHAEL LOPEZ |
| Green Plans Picked Up | 1/17/2020 | APPLICANT |
| Corrections Issued | 1/22/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 1/30/2020 | ALLEN MANALANSAN |
| Building Plans Picked Up | 1/31/2020 | APPLICANT |
| Plan Check Approved | 3/3/2020 | MICHAEL LOPEZ |
| Issued | 3/4/2020 | LADBS |
| CofO in Progress | 12/4/2020 | EUGENE CASSIDY |
| No Progress | 12/30/2020 | ANSON MAGLASANG |
| CofO in Progress | 2/11/2021 | ANSON MAGLASANG |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
| CofO Issued | 2/11/2021 | DEROLD HAUFF |
| Permit Finaled | 2/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2020 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 1/31/2020 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 2/19/2020 | EMIL KYUPELYAN |
| CPC | Cleared | 2/27/2020 | RUBEN VASQUEZ |
| Frnt yard landscape/Water mgmt | Cleared | 2/27/2020 | RUBEN VASQUEZ |
| Green Code | Cleared | 2/27/2020 | MICHAEL LOPEZ |
| Green Code | Cleared | 2/27/2020 | VIVIAN LAO |
| Highway dedication | Cleared | 3/2/2020 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 3/3/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 3/3/2020 | JAMES MORALEZ |
Contact Information
| Contractor | F S Z Bros General Contractors Inc; Lic. No.: 794097-B | 9036 IMPERIAL HWY DOWNEY, CA 90242 |
| Engineer | Sanchez,, Pablo Beltran; Lic. No.: C86223 | 1840 S GAFFEY ST 382 SAN PEDRO, CA 90731 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/20/2020 | Approved | BRIAN CHRISTIAN |
| Excavation/Setback/Form/Re-Bar | 4/27/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/17/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/17/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/17/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 7/17/2020 | Conditional Approval | EUGENE CASSIDY |
| MERV13>=Rough | 7/17/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/17/2020 | Approved | EUGENE CASSIDY |
| Verify Rec and Parks Fee Memo | 7/17/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/17/2020 | Approved | EUGENE CASSIDY |
| Insulation | 7/23/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/31/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/31/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 8/5/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/5/2020 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 10/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/21/2020 | Approved | EUGENE CASSIDY |
| Green Building Final | 10/21/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 10/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Final | 10/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 10/21/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/21/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 10/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 10/21/2020 | Approved | EUGENE CASSIDY |
| Final | 11/18/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 11/18/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 11/18/2020 | Approved | EUGENE CASSIDY |
| Service/Power Release | 11/18/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/4/2020 | Approved | EUGENE CASSIDY |
| Final | 12/4/2020 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 12/4/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/4/2020 | Approved | EUGENE CASSIDY |
| Service/Power Release | 12/4/2020 | Approved | EUGENE CASSIDY |