2954 W 8TH ST 90005
Certificate Information: 2954 W 8TH ST 90005
- Application / Permit
- 19010-10000-06117
- Plan Check / Job No.
- B19LA27215
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 7 STORY WITH 1 LEVEL SUBTERRANEAN PARKING (5 LEVELS OF TYPE IIIA OVER 2 LEVELS OF TYPE IA, OVER 1 LEVEL TYPE 1A BASEMENT), 28 UNIT (3 UNITS ELI) APARTMENT BUILDING. AFFORDABLE HOUSING USING TOC TIER 3 INCENTIVES. INSTALL AUTOMATIC FIRE SPRINKLERS.
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Metro
- Current Status
- Issued on 7/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | ALBERT SERVIN |
| Corrections Issued | 2/18/2020 | ALBERT SERVIN |
| Quality Review Completed | 2/20/2020 | KEN GILL |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 2/28/2020 | APPLICANT |
| Applicant returned to address corrections | 4/29/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 5/11/2020 | ALBERT SERVIN |
| Green Plans Picked Up | 7/9/2020 | APPLICANT |
| Applicant returned to address corrections | 12/2/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 2/10/2021 | ALBERT SERVIN |
| Applicant returned to address corrections | 2/16/2021 | ALBERT SERVIN |
| Applicant returned to address corrections | 2/17/2021 | ALBERT SERVIN |
| Applicant returned to address corrections | 3/25/2021 | ALBERT SERVIN |
| Applicant returned to address corrections | 6/14/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 6/16/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 7/6/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 6/26/2023 | PRANITA SHAH |
| Plan Check Approved | 7/28/2023 | PRANITA SHAH |
| Issued | 7/16/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2020 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 3/13/2020 | JOHN CONNEALLY |
| Internal circulation | Cleared | 7/7/2020 | PETE EYRE |
| Green Code | Cleared | 7/8/2020 | COLIN LOREDO |
| Permit | Cleared | 7/21/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2020 | RENZ SORIANO |
| Highway dedication | Cleared | 2/22/2021 | RENZ SORIANO |
| Building over 3-story or 36-ft | Cleared | 3/25/2021 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 3/25/2021 | CALOSHA APPROVED |
| Density Bonus 12.22.A.31 | Cleared | 9/1/2021 | NICHOLAS KAWAZOE |
| Fire Marshall Fire Life Safety | Cleared | 1/31/2022 | MENOA AGHAJANI |
| Sewer availability | Cleared | 2/24/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 2/25/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 3/2/2022 | AMAAN MALIK |
| Frnt yard landscape/Water mgmt | Cleared | 5/2/2022 | RICHARD REASER |
| Miscellaneous | Cleared | 5/2/2022 | RICHARD REASER |
| Opn space landscape/Water mgmt | Cleared | 5/2/2022 | RICHARD REASER |
| Redevelopment Project Area | Cleared | 5/23/2022 | DAVID URITA |
| DAS Clearance | Cleared | 6/22/2023 | ALBERT SERVIN |
Contact Information
| Architect | Ko,, Michael Myungsoo; Lic. No.: C22356 | 3435 WILSHIRE BLVD #2905 LOS ANGELES, CA 90010 |
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Engineer | Pukkanasut,, Jirayus; Lic. No.: C73728 | 1424 ROLLING HILLS DR FULLERTON, CA 92835 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/18/2024 | Partial Approval | LARRY ARNICK |
| Footing/Foundation/Slab | 1/17/2025 | Not Ready for Inspection | LARRY ARNICK |
| T-Bar Ceiling | 1/22/2025 | No Access for Inspection | RONALD JIMENEZ |
| Reinforced Concrete Frame | 2/4/2025 | Partial Approval | LARRY ARNICK |
| Green Building Rough | 2/5/2025 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 2/5/2025 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 3/20/2025 | Partial Approval | LARRY ARNICK |
| Green Building Rough | 4/7/2025 | Not Ready for Inspection | LARRY ARNICK |
| Reinforced Concrete Frame | 4/7/2025 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 4/7/2025 | Not Ready for Inspection | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Partial Approval | LARRY ARNICK |
| Footing/Foundation/Slab | 5/13/2025 | Partial Approval | LARRY ARNICK |
| Footing/Foundation/Slab | 6/9/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 6/11/2025 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 7/28/2025 | Partial Approval | LARRY ARNICK |
| Footing/Foundation/Slab | 8/25/2025 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Rough | 8/26/2025 | Partial Approval | LARRY ARNICK |
| Reinforced Concrete Frame | 8/26/2025 | Partial Approval | LARRY ARNICK |
| Verify Sprinkler Sign Off | 8/26/2025 | Not Ready for Inspection | LARRY ARNICK |
| T-Bar Ceiling | 10/10/2025 | Not Ready for Inspection | LARRY ARNICK |
| Posting Pre-Inspection | 10/14/2025 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 10/21/2025 | Partial Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2026 | Partial Approval | LARRY ARNICK |
| Special/Order Compliance | 1/7/2026 | Conditional Approval | LARRY ARNICK |
| Wood Frame | 1/21/2026 | Corrections Issued | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2026 | Partial Approval | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2026 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2026 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2026 | Partial Approval | RONALD JIMENEZ |
| Wood Frame | 4/8/2026 | Corrections Issued | RONALD JIMENEZ |