11048 W DEBBY ST 91606
Certificate Information: 11048 W DEBBY ST 91606
- Application / Permit
- 19010-10000-06110
- Plan Check / Job No.
- B19LA27198
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1 story ADU per AB 494 and SB 229. Fully Sprinklered.
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 8/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Green Plans Picked Up | 1/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 2/18/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 2/19/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Plan Check Approved | 12/16/2020 | SAMUEL GONZALEZ |
| Issued | 3/25/2021 | APPLICANT |
| CofO in Progress | 8/10/2022 | JOHN HAYES |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
| CofO Issued | 8/24/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 2/12/2020 | NEGAR NEJAD |
| Construction near power lines | Cleared | 3/6/2020 | OSCAR CASTRO |
| Address approval | Cleared | 3/19/2020 | RENZ SORIANO |
| Low Impact Development | Cleared | 8/6/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/10/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/10/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 10/27/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Levet Inc; Lic. No.: 1027447-B | 1110 SONORA AVE #101 GLENDALE, CA 91201 |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/13/2021 | Approved | DANIEL DREW |
| Underground Mechanical | 5/13/2021 | Approved | DANIEL DREW |
| Underground Mechanical | 5/20/2021 | Corrections Issued | ARAM AVEDISIAN |
| Underground Mechanical | 5/21/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 8/4/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 8/4/2021 | Approved | DANIEL DREW |
| Green Building Rough | 8/4/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 8/4/2021 | Approved | DANIEL DREW |
| Verify Sprinkler Sign Off | 8/4/2021 | Not Ready for Inspection | DANIEL DREW |
| Wood Frame | 8/4/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Partial Approval | DANIEL DREW |
| Green Building Rough | 9/2/2021 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 9/2/2021 | Partial Approval | CHARLES POWELL |
| Insulation | 9/13/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 9/22/2021 | Approved | DANIEL DREW |
| Final | 2/3/2022 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 2/3/2022 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 2/3/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Final | 3/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 3/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Service/Power Release | 3/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 3/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| BUILDING-Rough-Frame | 4/22/2022 | Approved | ARAM AVEDISIAN |
| Final | 4/22/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 4/22/2022 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 4/22/2022 | Not Required | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 4/22/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/28/2022 | No Access for Inspection | MICHEL ABAJAN |
| Final | 4/28/2022 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 4/28/2022 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 4/28/2022 | No Access for Inspection | MICHEL ABAJAN |
| Final | 5/26/2022 | Corrections Issued | JACK KARGODORIAN |
| Final | 6/3/2022 | Corrections Issued | ARAM AVEDISIAN |
| Final | 6/14/2022 | Corrections Issued | JOHN HAYES |
| Final | 7/25/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/10/2022 | OK to Issue CofO | JOHN HAYES |