3016 N NORTH MAIN ST 90031

Certificate Information: 3016 N NORTH MAIN ST 90031

Application / Permit
19010-10000-06106
Plan Check / Job No.
B19LA27190
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
BUILDING 1: NEW 5 STORY MIXED USE BUILDING & DENSITY BONUS AFFORDABLE HOUSING PROJECT: 4 STORY, TYPE VA, 97 APARTMENTS OVER 1 STORY, TYPE IA, GROCERY STORE/RETAIL. 96 UNITS RESTRICTED FOR 49 ELI & 47 LI HOUSE HOLD.
Permit Issued
Issued on 10/20/2021
Issuing Office
Metro
Current Status
CofO Issued on 9/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 KESETE HAREGOT
Disabled Access Plans Picked Up 2/20/2020 APPLICANT
Corrections Issued 3/2/2020 KESETE HAREGOT
Quality Review Completed 3/18/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 3/26/2020 APPLICANT
Applicant returned to address corrections 7/6/2020 KESETE HAREGOT
Applicant returned to address corrections 8/13/2020 KESETE HAREGOT
Applicant returned to address corrections 8/27/2020 KESETE HAREGOT
Green Plans Picked Up 5/27/2021 APPLICANT
Applicant returned to address corrections 7/7/2021 KESETE HAREGOT
Plan Check Approved 10/20/2021 KESETE HAREGOT
Issued 10/20/2021 APPLICANT
TCO Issued (Expire Date: 06-17-2025) 12/19/2024 RAFAEL ESPINOZA
TCO Issued (Expire Date: 12-08-2025) 6/11/2025 RAFAEL ESPINOZA
CofO in Progress 9/18/2025 RAFAEL ESPINOZA
Permit Finaled 9/19/2025 ERNESTO CORRAL
CofO Issued 9/19/2025 ERNESTO CORRAL
Permit Finaled 9/19/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 10/7/2020 THOMAS LANG
Permit Cleared 1/22/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/11/2021 THOMAS LANG
Green Code Cleared 5/27/2021 AARON COSTA
Internal circulation Cleared 6/2/2021 KEVIN ARUCAN
Low Impact Development Cleared 7/1/2021 ANDRES COVARRUBIAS
Building over 3-story or 36-ft Cleared 7/28/2021 CALOSHA APPROVED
Tract Map conditions Cleared 8/5/2021 JOE LUCKEY
Roof/Waste drainage to street Cleared 8/17/2021 THOMAS LANG
Bicycle Parking Cleared 8/26/2021 JEREMY CHOK
Highway dedication Cleared 9/8/2021 THOMAS LANG
Hydrant and Access approval Cleared 9/8/2021 JOHN CONNEALLY
Sewer availability Cleared 9/17/2021 JEANIE LAM
Trees in Parkway Cleared 9/30/2021 JOEL HERNANDEZ
Work Adjacent to Public Way Cleared 10/6/2021 ROSA SILVA
Fire Marshall Fire Life Safety Cleared 10/14/2021 VIDAL GARCIA
Public Housing Cleared 10/14/2021 JOEL LAUNCHBAUGH
DAS Clearance Cleared 10/18/2021 KESETE HAREGOT
CPC Cleared 10/20/2021 PABLO ESTRADA
Density Bonus 12.22.A.25 Cleared 10/20/2021 NICHOLAS KAWAZOE
Frnt yard landscape/Water mgmt Cleared 10/20/2021 PABLO ESTRADA
Opn space landscape/Water mgmt Cleared 10/20/2021 PABLO ESTRADA
Site Plan review Cleared 10/20/2021 PABLO ESTRADA

Contact Information

Architect Suarez,, Hugo; Lic. No.: C10561 1959 E OAKWOOD STREET      PASADENA, CA 91104
Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/30/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/27/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/28/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/29/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/2/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/2/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/2/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/3/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/4/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 5/4/2022 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 5/5/2022 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 5/5/2022 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 5/9/2022 Corrections Issued RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/11/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/11/2022 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/16/2022 Partial Inspection ERNESTO CORRAL
Pre-Inspection 5/16/2022 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 5/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 5/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 5/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 5/25/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/25/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/25/2022 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 5/25/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 5/26/2022 Conditional Approval ERNESTO CORRAL
Green Building Rough 5/26/2022 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 5/26/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/26/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 5/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 6/8/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/10/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 6/13/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/14/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/15/2022 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/15/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 6/16/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/17/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 6/17/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 6/21/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/22/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/23/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/24/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/27/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/28/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/29/2022 Conditional Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 6/29/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 6/30/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/7/2022 Conditional Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 7/7/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/7/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 7/8/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/13/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/15/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/18/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 7/19/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 7/20/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 7/21/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 7/22/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 7/26/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/27/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 7/29/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 8/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/2/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 8/3/2022 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 8/3/2022 Partial Approval TED RIES
Footing/Foundation/Slab 8/3/2022 Partial Approval TED RIES
Masonry Wall/Backfill 8/3/2022 Not Ready for Inspection TED RIES
Deputy Reinf. Concrete 8/4/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/5/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/19/2022 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/19/2022 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 8/19/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/19/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 8/29/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 8/30/2022 Conditional Approval WINSTON DUNNING
Deputy Steel/Welding 8/31/2022 Conditional Approval WINSTON DUNNING
Light Gage Steel Frame 9/8/2022 Partial Approval RAFAEL ESPINOZA
Insulation 9/12/2022 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 9/15/2022 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 9/15/2022 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 9/21/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 9/29/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 9/29/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/3/2022 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 10/3/2022 Partial Approval RAFAEL ESPINOZA
Insulation 10/3/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/3/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/11/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/11/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 10/14/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/24/2022 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/24/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/26/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Insulation 10/28/2022 Not Ready for Inspection MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/1/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 11/1/2022 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 11/3/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/8/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/9/2022 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 11/9/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/9/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/10/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 11/15/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 11/15/2022 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 11/15/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/15/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 11/15/2022 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 11/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 11/17/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 11/18/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 11/18/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/21/2022 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 11/21/2022 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 11/21/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 11/21/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/22/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 12/7/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Partial Approval RAFAEL ESPINOZA
Insulation 12/27/2022 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 1/23/2023 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Partial Approval GREGORY POMISH
Drywall Nailing 1/26/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/27/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/27/2023 Partial Approval RAFAEL ESPINOZA
Insulation 2/3/2023 Partial Approval RAFAEL ESPINOZA
Insulation 2/7/2023 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 2/9/2023 Partial Approval RAFAEL ESPINOZA
Insulation 2/9/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/10/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 2/10/2023 Corrections Issued RAFAEL ESPINOZA
Insulation 2/13/2023 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 2/13/2023 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 2/14/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/14/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 2/14/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/15/2023 Partial Approval RAFAEL ESPINOZA
Insulation 2/16/2023 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 2/17/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/17/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/21/2023 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 2/21/2023 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 2/21/2023 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/21/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 2/21/2023 Partial Approval RAFAEL ESPINOZA
Insulation 2/22/2023 Not Ready for Inspection JEROME BLACKWOOD
Deputy Wood Construction 2/27/2023 Conditional Approval RAFAEL ESPINOZA
Insulation 2/27/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/27/2023 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/28/2023 Partial Inspection RAFAEL ESPINOZA
Insulation 2/28/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/1/2023 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/1/2023 Partial Approval RAFAEL ESPINOZA
Insulation 3/1/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/1/2023 Partial Approval RAFAEL ESPINOZA
Insulation 3/2/2023 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 3/6/2023 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 3/6/2023 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Partial Inspection RAFAEL ESPINOZA
Insulation 3/6/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/7/2023 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Partial Approval RAFAEL ESPINOZA
Insulation 3/7/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/8/2023 Partial Approval RAFAEL ESPINOZA
Insulation 3/8/2023 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/8/2023 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 3/10/2023 Partial Approval RAFAEL ESPINOZA
Insulation 3/10/2023 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 3/14/2023 Partial Approval RAFAEL ESPINOZA
Insulation 3/14/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 3/15/2023 Conditional Approval MICHAEL ROSENBERG
Insulation 3/16/2023 Partial Inspection KATY RAMIREZ
Drywall Nailing 3/20/2023 Partial Approval GREGORY POMISH
Insulation 3/20/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 3/21/2023 Partial Approval JAMES POWERS
Drywall Nailing 3/21/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/21/2023 Partial Approval JAMES POWERS
Drywall Nailing 3/22/2023 Not Ready for Inspection GREGORY POMISH
Insulation 3/22/2023 Partial Approval GREGORY POMISH
Light Gage Steel Frame 3/22/2023 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 3/23/2023 Partial Approval GREGORY POMISH
Insulation 3/23/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 3/24/2023 Partial Inspection GREGORY POMISH
Insulation 3/24/2023 Partial Inspection GREGORY POMISH
Drywall Nailing 3/28/2023 Partial Approval JULIAN CAPUCETTI
Insulation 3/28/2023 Partial Approval JULIAN CAPUCETTI
Deputy Wood Construction 3/29/2023 Conditional Approval RAFAEL ESPINOZA
Insulation 3/29/2023 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 3/30/2023 Partial Inspection RAFAEL ESPINOZA
Insulation 3/30/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/3/2023 Partial Inspection RAFAEL ESPINOZA
Insulation 4/3/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/11/2023 Partial Approval RAFAEL ESPINOZA
Insulation 4/11/2023 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 4/12/2023 Conditional Approval LARRY ARNICK
Drywall Nailing 4/12/2023 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 4/12/2023 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 4/18/2023 Partial Approval RAFAEL ESPINOZA
Insulation 4/18/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/24/2023 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 4/24/2023 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/1/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 5/3/2023 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/3/2023 Partial Approval RAFAEL ESPINOZA
Insulation 5/3/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/9/2023 Not Ready for Inspection LARRY ARNICK
T-Bar Ceiling 5/9/2023 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 5/16/2023 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 5/25/2023 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 5/30/2023 Partial Approval LARRY ARNICK
Drywall Nailing 5/31/2023 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 5/31/2023 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 6/5/2023 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 6/7/2023 Partial Approval LARRY ARNICK
Drywall Nailing 6/15/2023 Partial Approval LARRY ARNICK
Structural Steel Frame 6/15/2023 Partial Approval LARRY ARNICK
Drywall Nailing 6/20/2023 Partial Approval LARRY ARNICK
Light Gage Steel Frame 6/20/2023 Partial Approval LARRY ARNICK
Drywall Nailing 6/21/2023 Partial Approval LARRY ARNICK
Light Gage Steel Frame 6/21/2023 Partial Approval LARRY ARNICK
Drywall Nailing 6/22/2023 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 6/22/2023 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 7/11/2023 Not Ready for Inspection LARRY ARNICK
Deputy Steel/Welding 7/12/2023 Conditional Approval LARRY ARNICK
Insulation 7/12/2023 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 7/13/2023 Not Ready for Inspection LARRY ARNICK
Insulation 7/18/2023 Partial Approval LARRY ARNICK
Insulation 7/19/2023 Partial Approval LARRY ARNICK
Drywall Nailing 7/24/2023 Partial Approval LARRY ARNICK
Drywall Nailing 8/1/2023 Partial Approval LARRY ARNICK
Light Gage Steel Frame 8/1/2023 Partial Approval LARRY ARNICK
Drywall Nailing 8/9/2023 Partial Approval LARRY ARNICK
Deputy Steel/Welding 8/14/2023 Conditional Approval LARRY ARNICK
Drywall Nailing 8/14/2023 Partial Approval LARRY ARNICK
Light Gage Steel Frame 8/14/2023 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 8/15/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Partial Approval LARRY ARNICK
Drywall Nailing 8/18/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 8/22/2023 Partial Approval LARRY ARNICK
Drywall Nailing 8/23/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Partial Approval LARRY ARNICK
Deputy Wood Construction 8/25/2023 Conditional Approval LARRY ARNICK
Drywall Nailing 8/30/2023 Partial Approval LARRY ARNICK
Drywall Nailing 9/20/2023 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 9/20/2023 Partial Approval LARRY ARNICK
Drywall Nailing 9/28/2023 Partial Approval LARRY ARNICK
Light Gage Steel Frame 9/28/2023 Partial Approval LARRY ARNICK
Drywall Nailing 10/3/2023 Partial Approval LARRY ARNICK
Light Gage Steel Frame 10/3/2023 Partial Approval LARRY ARNICK
Drywall Nailing 10/5/2023 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 10/5/2023 Partial Approval LARRY ARNICK
Deputy Drilled-In Anchors 10/19/2023 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 10/19/2023 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/19/2023 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/24/2023 Partial Approval LARRY ARNICK
Light Gage Steel Frame 10/24/2023 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 10/31/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/31/2023 Corrections Issued RAFAEL ESPINOZA
Masonry Wall/Backfill 11/1/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 11/2/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 11/8/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 11/9/2023 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 11/15/2023 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 11/15/2023 Partial Approval LARRY ARNICK
Verify Sprinkler Sign Off 11/15/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Masonry 11/17/2023 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 11/29/2023 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 12/5/2023 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 1/11/2024 Partial Approval LARRY ARNICK
Final 1/30/2024 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 1/30/2024 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 1/30/2024 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 3/1/2024 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 3/1/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/14/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 3/14/2024 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 3/14/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 3/18/2024 Partial Inspection RAFAEL ESPINOZA
Wood Frame 3/18/2024 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 3/26/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 3/28/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/28/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/9/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/11/2024 Approved RAFAEL ESPINOZA
Interior/Exterior Lathing 4/15/2024 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/16/2024 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/22/2024 Corrections Issued RAFAEL ESPINOZA
Light Gage Steel Frame 4/22/2024 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 4/24/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/24/2024 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 4/29/2024 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 5/13/2024 Approved RAFAEL ESPINOZA
Drywall Nailing 5/28/2024 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 6/10/2024 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 6/10/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/10/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/10/2024 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 6/17/2024 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 7/3/2024 Approved RAFAEL ESPINOZA
Light Gage Steel Frame 7/11/2024 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 7/11/2024 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 7/15/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/16/2024 Conditional Approval RAFAEL ESPINOZA
Piling/Pier/Caisson 7/16/2024 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 7/16/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/16/2024 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 7/19/2024 Partial Inspection RONALD JIMENEZ
Footing/Foundation/Slab 7/29/2024 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/31/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 7/31/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 8/6/2024 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/12/2024 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 8/14/2024 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/21/2024 Conditional Approval RAFAEL ESPINOZA
Piling/Pier/Caisson 8/21/2024 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 8/21/2024 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/21/2024 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 8/26/2024 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 9/4/2024 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 9/6/2024 Approved RONALD JIMENEZ
Drywall Nailing 9/10/2024 Partial Approval RAFAEL CORTES
Pre-Inspection 10/3/2024 Not Ready for Inspection RAFAEL CORTES
Final 10/17/2024 Corrections Issued RAFAEL ESPINOZA
Footing/Foundation/Slab 10/17/2024 Approved RAFAEL ESPINOZA
Green Building Final 10/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 10/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 10/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 10/17/2024 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 10/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 10/24/2024 Corrections Issued RAFAEL CORTES
Insulation 10/28/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 10/30/2024 Partial Approval RAFAEL CORTES
Final 12/2/2024 Partial Inspection RAFAEL ESPINOZA
Green Building Final 12/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 12/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 12/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 12/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 12/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 12/2/2024 Not Ready for Inspection RAFAEL ESPINOZA
Pre-Inspection 12/17/2024 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 5/20/2025 Approved RAFAEL CORTES
Final 9/18/2025 OK to Issue CofO RAFAEL ESPINOZA
Green Building Final 9/18/2025 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 9/18/2025 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 9/18/2025 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 9/18/2025 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/18/2025 Approved RAFAEL ESPINOZA
Wood Frame 9/18/2025 Approved RAFAEL ESPINOZA