Pre-Inspection
|
2/22/2021
|
Conditional Approval
|
RICKEY JACKSON
|
|
Footing/Foundation/Slab
|
3/3/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
3/5/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
3/8/2021
|
Partial Approval
|
RICKEY JACKSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/12/2021
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
3/18/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
3/18/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
3/18/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
3/19/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
3/19/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
3/19/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
3/23/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/24/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
3/26/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/26/2021
|
Partial Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/31/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
4/5/2021
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Reinforced Masonry Frame
|
4/5/2021
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Verify Sprinkler Sign Off
|
4/5/2021
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Reinforced Concrete Frame
|
4/6/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
4/7/2021
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/9/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/9/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
4/13/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
4/13/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
4/13/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/14/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/15/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
4/15/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
4/15/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
4/15/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/19/2021
|
Conditional Approval
|
RICKEY JACKSON
|
|
Footing/Foundation/Slab
|
4/19/2021
|
Partial Approval
|
RICKEY JACKSON
|
|
Deputy Reinf. Concrete
|
4/20/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/20/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/21/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/21/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
4/21/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/22/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/22/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/23/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/23/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/23/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
4/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
4/23/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Verify Sprinkler Sign Off
|
4/23/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/26/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/26/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
4/27/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/27/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
4/27/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
4/28/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Concrete
|
4/28/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
4/28/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Drilled-In Anchors
|
4/29/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
4/29/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Masonry
|
4/29/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
4/30/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
4/30/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Masonry
|
4/30/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
5/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
5/3/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
5/4/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/4/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/4/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/4/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
5/5/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/5/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/5/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/5/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
5/6/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Pre-Stress Concrete
|
5/6/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Concrete
|
5/6/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
5/6/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
5/6/2021
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Reinforced Masonry Frame
|
5/6/2021
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Verify Sprinkler Sign Off
|
5/6/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Drilled-In Anchors
|
5/7/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Pre-Stress Concrete
|
5/7/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Concrete
|
5/7/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
5/7/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Pre-Stress Concrete
|
5/10/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/10/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/11/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/11/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/12/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/12/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/13/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
5/13/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Pre-Stress Concrete
|
5/14/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/14/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
5/14/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/17/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/17/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/18/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/18/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/18/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/19/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/19/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
5/19/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
5/19/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
5/20/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Concrete
|
5/20/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
5/20/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Pre-Stress Concrete
|
5/21/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
5/21/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Masonry
|
5/21/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Masonry
|
5/25/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Pre-Stress Concrete
|
5/26/2021
|
Approved
|
JOHN KITCKO
|
|
Deputy Reinf. Masonry
|
5/26/2021
|
Approved
|
JOHN KITCKO
|
|
Green Building Rough
|
5/26/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Reinforced Masonry Frame
|
5/26/2021
|
Partial Approval
|
JOHN KITCKO
|
|
Structural Steel Frame
|
5/26/2021
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Deputy Pre-Stress Concrete
|
5/27/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
5/27/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Pre-Stress Concrete
|
5/28/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
5/28/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Green Building Rough
|
5/28/2021
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
5/28/2021
|
Partial Inspection
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
6/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
6/2/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Pre-Stress Concrete
|
6/2/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
6/2/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Footing/Foundation/Slab
|
6/2/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Drilled-In Anchors
|
6/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
6/3/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
6/3/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/4/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/4/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/7/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
6/7/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Pre-Stress Concrete
|
6/8/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/8/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
6/14/2021
|
Partial Approval
|
RICKEY JACKSON
|
|
Reinforced Masonry Frame
|
6/14/2021
|
Partial Approval
|
RICKEY JACKSON
|
|
Deputy Pre-Stress Concrete
|
6/15/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Concrete
|
6/15/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
6/15/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Pre-Stress Concrete
|
6/16/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
6/16/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Masonry
|
6/16/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Pre-Stress Concrete
|
6/17/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Concrete
|
6/17/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Masonry
|
6/17/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
6/17/2021
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Reinforced Masonry Frame
|
6/17/2021
|
Partial Approval
|
HAMID PISHEHVAR
|
|
Deputy Pre-Stress Concrete
|
6/18/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
6/18/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/18/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/21/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
6/21/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/21/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/22/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
6/22/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/22/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/23/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
6/23/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/23/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/24/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
6/24/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/24/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/25/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
6/25/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/25/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
6/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
6/25/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/28/2021
|
No Access for Inspection
|
JOE VELASQUEZ
|
|
Deputy Reinf. Concrete
|
6/28/2021
|
No Access for Inspection
|
JOE VELASQUEZ
|
|
Deputy Reinf. Masonry
|
6/28/2021
|
No Access for Inspection
|
JOE VELASQUEZ
|
|
Deputy Pre-Stress Concrete
|
6/29/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
6/29/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/29/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
6/30/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
6/30/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
7/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
7/1/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
7/1/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/2/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/2/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
7/2/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/7/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/7/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
7/7/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/8/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/8/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
7/8/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
7/8/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
7/8/2021
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/9/2021
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Deputy Reinf. Concrete
|
7/9/2021
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Deputy Reinf. Masonry
|
7/9/2021
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Deputy Pre-Stress Concrete
|
7/12/2021
|
Conditional Approval
|
JOHN DODGE
|
|
Deputy Reinf. Concrete
|
7/12/2021
|
Conditional Approval
|
JOHN DODGE
|
|
Deputy Reinf. Masonry
|
7/12/2021
|
Conditional Approval
|
JOHN DODGE
|
|
Deputy Drilled-In Anchors
|
7/13/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Pre-Stress Concrete
|
7/13/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
7/13/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Masonry
|
7/13/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
7/14/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/14/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/14/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
7/14/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
7/15/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Pre-Stress Concrete
|
7/15/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
7/15/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
7/16/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/16/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/16/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Drilled-In Anchors
|
7/19/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/19/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/19/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
7/20/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
7/20/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
7/21/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
7/21/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/29/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
7/30/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
7/30/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
7/30/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
8/6/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
8/6/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
8/9/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
8/9/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
8/11/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
8/11/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
8/17/2021
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Reinforced Masonry Frame
|
8/17/2021
|
Partial Approval
|
GRANT WOODS
|
|
Green Building Rough
|
8/20/2021
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Reinforced Masonry Frame
|
8/20/2021
|
Partial Approval
|
ROBERT DAVIS
|
|
Deputy Pre-Stress Concrete
|
8/23/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
8/23/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
8/24/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
8/24/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
8/25/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
8/25/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
8/25/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
8/25/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
8/26/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
8/26/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
8/27/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
8/27/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
8/30/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
8/31/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
8/31/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
9/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
9/1/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
9/2/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
9/2/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
9/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
9/3/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
9/3/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
9/3/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
9/7/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Masonry
|
9/7/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Piling/Pier/Caisson
|
9/8/2021
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
9/9/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Masonry
|
9/9/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
9/10/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Masonry
|
9/10/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
9/13/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Masonry
|
9/13/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
9/14/2021
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Masonry
|
9/14/2021
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
9/15/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Masonry
|
9/15/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Green Building Rough
|
9/15/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Reinforced Masonry Frame
|
9/15/2021
|
Partial Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
9/16/2021
|
Conditional Approval
|
RICKEY JACKSON
|
|
Deputy Reinf. Masonry
|
9/16/2021
|
Conditional Approval
|
RICKEY JACKSON
|
|
Deputy Reinf. Concrete
|
9/17/2021
|
Conditional Approval
|
JOHN KITCKO
|
|
Deputy Reinf. Masonry
|
9/17/2021
|
Conditional Approval
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
9/17/2021
|
Partial Approval
|
BRUCE CAMPBELL
|
|
Deputy Reinf. Concrete
|
9/20/2021
|
Conditional Approval
|
JOHN DODGE
|
|
Deputy Reinf. Masonry
|
9/20/2021
|
Conditional Approval
|
JOHN DODGE
|
|
Deputy Reinf. Masonry
|
9/22/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
9/22/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
9/22/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
9/23/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
9/29/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
9/29/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
9/29/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
9/29/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
10/6/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
10/6/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
10/6/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
10/7/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
10/7/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
10/8/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
10/15/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
10/15/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
10/21/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
10/21/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
10/21/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
10/21/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
10/21/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
10/22/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
10/22/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
10/28/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
10/28/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
11/4/2021
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Green Building Rough
|
11/4/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
11/4/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
11/5/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Steel/Welding
|
11/5/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
11/9/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
11/9/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
11/10/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
11/10/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
11/10/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
11/10/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
11/15/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
11/15/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
11/16/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
11/16/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
11/16/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
11/16/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Pre-Stress Concrete
|
11/19/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
11/19/2021
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
11/19/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
11/19/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Steel/Welding
|
11/24/2021
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
12/3/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Green Building Rough
|
12/3/2021
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Reinforced Masonry Frame
|
12/3/2021
|
Partial Approval
|
DANIEL VARNUM
|
|
Light Gage Steel Frame
|
12/6/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
12/9/2021
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
12/9/2021
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Steel/Welding
|
12/22/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
12/27/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Light Gage Steel Frame
|
12/27/2021
|
Partial Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
12/29/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
1/4/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Green Building Rough
|
1/10/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
1/10/2022
|
Corrections Issued
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
1/11/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
1/12/2022
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Excavation/Setback/Form/Re-Bar
|
1/19/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
1/20/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
1/20/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Insulation
|
1/21/2022
|
Partial Approval
|
DANIEL VARNUM
|
|
Light Gage Steel Frame
|
1/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
1/26/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
1/26/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
1/27/2022
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Steel/Welding
|
1/27/2022
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
1/28/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
1/28/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
1/28/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
1/28/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
1/31/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Steel/Welding
|
1/31/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
1/31/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Masonry
|
2/1/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
2/1/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
2/1/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Steel/Welding
|
2/3/2022
|
Conditional Approval
|
JOHN KITCKO
|
|
Drywall Nailing
|
2/3/2022
|
Partial Approval
|
JOHN KITCKO
|
|
Green Building Rough
|
2/3/2022
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Insulation
|
2/3/2022
|
Partial Approval
|
JOHN KITCKO
|
|
Light Gage Steel Frame
|
2/7/2022
|
Partial Approval
|
DANIEL VARNUM
|
|
Interior/Exterior Lathing
|
2/11/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
2/14/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Interior/Exterior Lathing
|
2/15/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
2/23/2022
|
Not Ready for Inspection
|
DANIEL VARNUM
|
|
Green Building Rough
|
2/24/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
2/24/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
2/28/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
3/3/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
3/10/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
3/10/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
3/11/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
3/16/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
3/16/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
4/8/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Masonry Wall/Backfill
|
4/13/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
4/15/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
4/15/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Light Gage Steel Frame
|
4/20/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
4/22/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
T-Bar Ceiling
|
5/4/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
T-Bar Ceiling
|
5/6/2022
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Posting Pre-Inspection
|
6/16/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Posting Pre-Inspection
|
6/17/2022
|
Partial Inspection
|
ROBERT DAVIS
|
|
Green Building Rough
|
6/23/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Pre-Inspection
|
7/6/2022
|
Partial Inspection
|
CAMERON CHABAN
|
|
Drywall Nailing
|
7/18/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
7/18/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
7/18/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
7/18/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
7/18/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
7/18/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
7/18/2022
|
SGSOV Not Ready
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
7/18/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
7/19/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
7/19/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Green Building Final
|
7/19/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Green Building Rough
|
7/19/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
7/19/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
7/19/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
7/19/2022
|
SGSOV Not Ready
|
DANNY RODRIGUEZ
|
|
Smoke Detectors
|
7/19/2022
|
Approved
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
7/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
7/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
7/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Masonry Frame
|
7/25/2022
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
SGSOV-Seismic Gas S/O Valve
|
7/25/2022
|
SGSOV No Gas
|
DANNY RODRIGUEZ
|
|
Drywall Nailing
|
7/27/2022
|
Approved
|
JONATHAN QUACH
|
|
Final
|
7/27/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
7/27/2022
|
Approved
|
JONATHAN QUACH
|
|
Reinforced Masonry Frame
|
7/27/2022
|
Approved
|
JONATHAN QUACH
|
|
T-Bar Ceiling
|
7/27/2022
|
Approved
|
JONATHAN QUACH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2022
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Final
|
8/3/2022
|
OK to Issue CofO
|
DANNY RODRIGUEZ
|