1656 N SILVERWOOD TER 90026
Certificate Information: 1656 N SILVERWOOD TER 90026
- Application / Permit
- 19010-10000-06097
- Plan Check / Job No.
- B19LA27177
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 36'-8"X35'-2" 2-STORY SINGLE FAMILY DWELLING OVER BASEMENT GARAGE. 1 OF 4
- Permit Issued
- Issued on 1/20/2021
- Issuing Office
- Current Status
- CofO Issued on 5/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | GEORGE ALVAREZ |
| Corrections Issued | 1/23/2020 | GEORGE ALVAREZ |
| Quality Review Completed | 1/25/2020 | STANLEY RAAP |
| Green Plans Picked Up | 6/24/2020 | APPLICANT |
| Applicant returned to address corrections | 8/25/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 11/13/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 12/14/2020 | GEORGE ALVAREZ |
| Issued | 1/20/2021 | APPLICANT |
| Building Plans Picked Up | 10/14/2021 | APPLICANT |
| CofO in Progress | 5/19/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/20/2025 | DEROLD HAUFF |
| CofO Issued | 5/20/2025 | DEROLD HAUFF |
| Permit Finaled | 5/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 3/5/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 3/5/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 3/5/2020 | JOHN CONNEALLY |
| Permit | Cleared | 3/5/2020 | THOMAS LANG |
| Sewer availability | Cleared | 3/5/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 5/11/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 6/24/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 10/30/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | WALLIE JONG |
| Haul Route | Cleared | 11/12/2020 | GEORGE ALVAREZ |
Contact Information
| Architect | Neubert,, Aaron Douglas; Lic. No.: C29005 | 3052 BERKELEY CIRCLE LOS ANGELES, CA 90026 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Engineer | Shank,, Ken M; Lic. No.: L8271 | 2566 N FERNANDO RD LOS ANGELES, CA 90065 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/5/2021 | Partial Inspection | SCOTT FINNILA |
| Deputy Reinf. Concrete | 4/16/2021 | Conditional Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 4/16/2021 | Corrections Issued | ROBERT VORHIS |
| Footing/Foundation/Slab | 4/27/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 4/30/2021 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 5/5/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 11/2/2021 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 11/5/2021 | Conditional Approval | AMY COLIN |
| Footing/Foundation/Slab | 11/22/2021 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/3/2021 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 12/9/2021 | No Access for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 12/10/2021 | Partial Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 12/10/2021 | Not Ready for Inspection | JOSE AVILA |
| Verify Sprinkler Sign Off | 12/10/2021 | Partial Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 12/16/2021 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 12/21/2021 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 3/9/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/21/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/1/2022 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 4/15/2022 | Partial Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/24/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/31/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Steel/Welding | 7/6/2022 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | THOMAS LOGRASSO |
| Green Building Rough | 8/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 8/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Pre-Inspection | 3/14/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/22/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/24/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Conditional Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/16/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/14/2024 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 6/12/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/12/2024 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 6/12/2024 | No Access for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/14/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/14/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/18/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/18/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/18/2024 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 6/18/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/25/2024 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 6/25/2024 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 6/25/2024 | Partial Approval | WILLIAM KUEHN |
| Insulation | 7/2/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 7/5/2024 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/16/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/8/2024 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 8/15/2024 | Approved | ANTHONY RAMOS |
| Insulation | 8/15/2024 | Approved | ANTHONY RAMOS |
| Footing/Foundation/Slab | 8/28/2024 | Approved | ROY SPAULDING |
| Pre-Inspection | 9/25/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/27/2024 | Approved | LUIS CASTRO |
| Underground Mechanical | 12/13/2024 | Partial Approval | JOHN QUINTANILLA |
| Pre-Inspection | 2/26/2025 | Partial Approval | FREDDIE RIVERA |
| Deputy Steel/Welding | 3/28/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 3/28/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 4/28/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 4/28/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 4/28/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/28/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 5/7/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 5/7/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 5/7/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/7/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 5/19/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 5/19/2025 | Approved | HAMIK HARTOUNIAN |