9502 N VAN NUYS BLVD 1-49 91402

Certificate Information: 9502 N VAN NUYS BLVD 1-49 91402

Application / Permit
19010-10000-06092
Plan Check / Job No.
B19LA27173
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW CONSTRUCTION OF 4-STORY, 49-UNIT APARTMENT.
Permit Issued
Issued on 4/22/2021
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 FARSHAD ALIMOHAMADI
Disabled Access Plans Picked Up 1/28/2020 APPLICANT
Corrections Issued 1/29/2020 FARSHAD ALIMOHAMADI
Quality Review Completed 2/2/2020 YOUNG KIM
Building Plans Picked Up 2/13/2020 APPLICANT
Applicant returned to address corrections 12/29/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/11/2021 FARSHAD ALIMOHAMADI
Green Plans Picked Up 3/3/2021 APPLICANT
Applicant returned to address corrections 3/9/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/26/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 4/20/2021 FARSHAD ALIMOHAMADI
Issued 4/22/2021 APPLICANT
Permit Closed-Status Void 4/6/2022 ANDREW DORSO
Re-Activate Permit 4/7/2022 ANDREW DORSO
TCO Issued (Expire Date: 10-16-2023) 4/19/2023 RICKEY JACKSON
CofO in Progress 9/15/2023 DANNY RODRIGUEZ
Permit Finaled 9/25/2023 RICKEY JACKSON
CofO Issued 9/25/2023 RICKEY JACKSON
Permit Finaled 9/25/2023 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 3/5/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 5/29/2020 JEREMY CARTER
Driveway location Cleared 7/14/2020 BRANDON WILSON
Eng Process Fee Ord 176,300 Cleared 8/26/2020 ELAINE LEI
Trees in Parkway Cleared 11/12/2020 JOHN KIM
DCP conditions approval Cleared 11/19/2020 KENNETH LE
Sewer availability Cleared 1/4/2021 GUILLERMO PETRA
Permit Cleared 1/20/2021 GUILLERMO PETRA
Highway dedication Cleared 2/2/2021 GUILLERMO PETRA
Public Housing Cleared 2/10/2021 THOMAS ANTONIO
DAS Clearance Cleared 2/18/2021 WAI LAU
Green Code Cleared 3/3/2021 AARON COSTA
Fire Marshall Fire Life Safety Cleared 3/4/2021 VIDAL GARCIA
Low Impact Development Cleared 3/9/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/10/2021 JOHN TRIANTAFYLLOS
"Q" conditions Cleared 3/25/2021 RICHARD REASER
Frnt yard landscape/Water mgmt Cleared 3/25/2021 RICHARD REASER
Miscellaneous Cleared 3/25/2021 RICHARD REASER
Miscellaneous Cleared 3/25/2021 RICHARD REASER
Miscellaneous Cleared 3/25/2021 RICHARD REASER
Opn space landscape/Water mgmt Cleared 3/25/2021 RICHARD REASER
Prkng lot landscape/Water mgmt Cleared 3/25/2021 RICHARD REASER
Building over 3-story or 36-ft Cleared 3/26/2021 CALOSHA APPROVED
"T" removal Cleared 3/30/2021 RICHARD REASER

Contact Information

Architect Yanez,, Arturo; Lic. No.: C24019 4061 BEVERLY GLEN BL      SHERMAN OAKS, CA 91423
Contractor Alpha Construction Co Inc; Lic. No.: 241368-B 14601 AETNA STREET      VAN NUYS, CA 91411

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/24/2021 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/6/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 10/6/2021 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/7/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/8/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 10/13/2021 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/13/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 10/15/2021 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/18/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/19/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 10/19/2021 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 10/19/2021 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 10/20/2021 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 10/21/2021 Partial Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 10/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/25/2021 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 10/26/2021 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 10/26/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/27/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/28/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 10/28/2021 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 10/29/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/1/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/2/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/3/2021 Approved SORIN CIRSTOIU
Reinforced Masonry Frame 11/3/2021 Not Ready for Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 11/4/2021 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/5/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 11/5/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/8/2021 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 11/8/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/9/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/9/2021 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/9/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/10/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/10/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/12/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/12/2021 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 11/12/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/15/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/15/2021 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/15/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/16/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/16/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 11/16/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/17/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/17/2021 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/17/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/18/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/18/2021 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 11/18/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/19/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/19/2021 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 11/19/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/22/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/23/2021 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 11/23/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/24/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 11/24/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/29/2021 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 11/30/2021 Conditional Approval RICKEY JACKSON
Deputy Reinf. Masonry 12/2/2021 Approved JEFFREY DURAN
Reinforced Concrete Frame 12/2/2021 Conditional Approval JEFFREY DURAN
Reinforced Masonry Frame 12/2/2021 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 12/3/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 12/6/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/7/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/8/2021 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/9/2021 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 12/9/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 12/10/2021 Partial Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 12/13/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/16/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 12/16/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/17/2021 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/17/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/20/2021 Conditional Approval JEFFREY DURAN
Green Building Rough 1/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 1/6/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/6/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 1/6/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/24/2022 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 1/24/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/26/2022 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 1/26/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/28/2022 Conditional Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 1/28/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/31/2022 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/31/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/1/2022 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 2/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/2/2022 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/2/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 2/2/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/3/2022 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 2/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 2/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/4/2022 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 2/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/5/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/8/2022 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/8/2022 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 2/23/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/23/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 2/23/2022 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 3/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 3/10/2022 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/10/2022 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 3/11/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/11/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Not Ready for Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 3/15/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/15/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 3/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 3/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 3/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 4/5/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/5/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Not Ready for Inspection ANDREW DORSO
Deputy Wood Construction 4/8/2022 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 4/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/13/2022 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/20/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/20/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 4/20/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 4/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/26/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/28/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/28/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 4/28/2022 Partial Approval DANNY RODRIGUEZ
Wood Frame 4/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 5/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 5/3/2022 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 5/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 5/5/2022 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 5/5/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/5/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 5/5/2022 Partial Approval DANNY RODRIGUEZ
Insulation 5/6/2022 Partial Approval DANNY RODRIGUEZ
Insulation 5/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 5/12/2022 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 5/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 5/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 5/16/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 5/17/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/17/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 5/17/2022 Partial Approval DANNY RODRIGUEZ
Wood Frame 5/19/2022 Partial Approval DANNY RODRIGUEZ
Insulation 5/20/2022 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 5/23/2022 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Corrections Issued DANNY RODRIGUEZ
Wood Frame 5/23/2022 Partial Approval DANNY RODRIGUEZ
Insulation 5/24/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 5/25/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 5/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 5/25/2022 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Not Ready for Inspection DANIEL VARNUM
Insulation 5/26/2022 Not Ready for Inspection DANIEL VARNUM
Insulation 5/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/1/2022 Partial Approval DANNY RODRIGUEZ
Wood Frame 6/1/2022 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 6/3/2022 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 6/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/3/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/3/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 6/6/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/7/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/7/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/7/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 6/8/2022 Conditional Approval DANNY RODRIGUEZ
Insulation 6/8/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/8/2022 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 6/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 6/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 6/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 6/13/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 6/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 6/21/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/21/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/21/2022 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 6/22/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/22/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 6/22/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 6/24/2022 Partial Inspection ANDREW DORSO
Green Building Rough 6/28/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/28/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/28/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 6/28/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 6/30/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/30/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 6/30/2022 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 6/30/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/1/2022 Partial Approval DANNY RODRIGUEZ
Insulation 7/1/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/1/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 7/7/2022 Partial Inspection CAMERON CHABAN
Insulation 7/7/2022 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 7/7/2022 Partial Approval CAMERON CHABAN
Wood Frame 7/7/2022 Corrections Issued CAMERON CHABAN
Insulation 7/8/2022 Not Ready for Inspection BRUCE CAMPBELL
Light Gage Steel Frame 7/8/2022 Partial Approval BRUCE CAMPBELL
Drywall Nailing 7/12/2022 Partial Approval DAVID BURKHEAD
Insulation 7/12/2022 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/15/2022 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 7/15/2022 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 7/15/2022 Not Ready for Inspection DANIEL VARNUM
Wood Frame 7/15/2022 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 7/20/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 7/20/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/20/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 7/20/2022 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 7/27/2022 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 7/27/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 7/28/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 7/28/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 7/28/2022 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 8/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 8/5/2022 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 8/9/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 8/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 8/10/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 8/15/2022 Partial Inspection DAVID BURKHEAD
Light Gage Steel Frame 8/15/2022 Partial Approval DAVID BURKHEAD
Drywall Nailing 8/26/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 8/26/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/29/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 8/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 9/2/2022 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 9/8/2022 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 9/9/2022 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 9/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 9/16/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 9/22/2022 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 9/30/2022 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 10/4/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 10/12/2022 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 10/12/2022 Corrections Issued DANNY RODRIGUEZ
Light Gage Steel Frame 10/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 10/18/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 10/25/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 10/25/2022 Approved DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/9/2022 Conditional Approval DANNY RODRIGUEZ
Pre-Inspection 12/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 1/13/2023 Partial Inspection ANDREW DORSO
Pre-Inspection 1/27/2023 Not Ready for Inspection DANIEL VARNUM
Pre-Inspection 1/31/2023 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 1/31/2023 Conditional Approval STEVEN LEVITT
Pre-Inspection 2/28/2023 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 4/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 4/5/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 4/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 4/5/2023 Partial Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/5/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 4/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 4/7/2023 Partial Inspection DANNY RODRIGUEZ
Smoke Detectors 4/7/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Final 4/11/2023 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 4/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 4/11/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/11/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 4/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 4/13/2023 Corrections Issued DANIEL VARNUM
Final 4/20/2023 Partial Inspection DANNY RODRIGUEZ
Insulation 8/1/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/12/2023 Approved DANNY RODRIGUEZ
Final 9/12/2023 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 9/12/2023 Approved DANNY RODRIGUEZ
Green Building Final 9/12/2023 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Approved DANNY RODRIGUEZ
Smoke Detectors 9/12/2023 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/12/2023 Approved DANNY RODRIGUEZ
Wood Frame 9/12/2023 Approved DANNY RODRIGUEZ
Final 9/14/2023 OK to Issue CofO DANNY RODRIGUEZ