148-150 W 79TH ST 90003
Certificate Information: 148-150 W 79TH ST 90003
- Application / Permit
- 19010-10000-06080
- Plan Check / Job No.
- B19LA27148
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2-story duplex with attached 3-car garage.
- Permit Issued
- Issued on 5/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2020 | HELEN NGUYEN |
| Green Plans Picked Up | 1/9/2020 | APPLICANT |
| Corrections Issued | 1/22/2020 | HELEN NGUYEN |
| Quality Review Completed | 1/26/2020 | YOUNG KIM |
| Building Plans Picked Up | 1/31/2020 | APPLICANT |
| Plan Check Approved | 3/3/2020 | HELEN NGUYEN |
| Issued | 5/5/2020 | LADBS |
| CofO in Progress | 11/28/2020 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
| CofO Issued | 12/10/2020 | DEROLD HAUFF |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 2/11/2020 | HELEN NGUYEN |
| Low Impact Development | Cleared | 2/12/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/12/2020 | JEANETTE VONG |
| Address approval | Cleared | 2/14/2020 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/14/2020 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 2/21/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/26/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2020 | Conditional Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 6/16/2020 | Partial Approval | EUGENE CASSIDY |
| Insulation | 6/17/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/11/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/11/2020 | Conditional Approval | FREDDIE RIVERA |
| Green Building Rough | 8/11/2020 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 8/11/2020 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 8/11/2020 | Approved | FREDDIE RIVERA |
| Sewer | 8/11/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 8/11/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/13/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/13/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Gas Test | 8/13/2020 | Partial Inspection | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/13/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/13/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/13/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/18/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/18/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 8/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/19/2020 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/19/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/25/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/25/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/28/2020 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/28/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 9/24/2020 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 11/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/18/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 11/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/18/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 11/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/18/2020 | Approved | ALEJANDRO DE ARTOLA |
| Final | 11/25/2020 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/25/2020 | Approved | ALEJANDRO DE ARTOLA |