831-833 E 109TH ST 90059

Certificate Information: 831-833 E 109TH ST 90059

Application / Permit
19010-10000-06076
Plan Check / Job No.
B19LA27145
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 2-STORY DUPLEX WITH ATTACHED 3-CAR GARAGE.
Permit Issued
Issued on 3/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 1/7/2020 MICHAEL LOPEZ
Green Plans Picked Up 1/9/2020 APPLICANT
Corrections Issued 1/22/2020 MICHAEL LOPEZ
Quality Review Completed 1/30/2020 ALLEN MANALANSAN
Building Plans Picked Up 1/31/2020 APPLICANT
Plan Check Approved 2/28/2020 MICHAEL LOPEZ
Issued 3/16/2020 LADBS
CofO in Progress 10/13/2020 EUGENE CASSIDY
Permit Finaled 12/10/2020 DEROLD HAUFF
CofO Issued 12/10/2020 DEROLD HAUFF
Permit Finaled 12/10/2020 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 2/12/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/12/2020 JEANETTE VONG
Address approval Cleared 2/14/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/14/2020 JEANETTE VONG
Permit Cleared 2/14/2020 JEANETTE VONG
Sewer availability Cleared 2/14/2020 JEANETTE VONG
Trees in Parkway Cleared 2/18/2020 JOHN KIM
Hydrant and Access approval Cleared 2/21/2020 GEORGE SUCHAND
Green Code Cleared 2/27/2020 MICHAEL LOPEZ

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/30/2020 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 5/5/2020 Conditional Approval WILLIAM ROSE
PLUMBING-Rough 5/15/2020 Partial Approval EUGENE CASSIDY
Wood Frame 5/15/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Partial Approval BRIAN CHRISTIAN
Insulation 5/18/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 6/15/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 6/30/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Rough 6/30/2020 Approved BRIAN CHRISTIAN
Green Building Rough 6/30/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 6/30/2020 Approved BRIAN CHRISTIAN
PLUMBING-Rough 6/30/2020 Approved BRIAN CHRISTIAN
Sewer 6/30/2020 Approved BRIAN CHRISTIAN
Verify Sprinkler Sign Off 6/30/2020 Approved BRIAN CHRISTIAN
Insulation 7/7/2020 Approved EUGENE CASSIDY
Drywall Nailing 7/10/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/10/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/13/2020 Approved EUGENE CASSIDY
Final 10/13/2020 OK to Issue CofO EUGENE CASSIDY
Gas Test 10/13/2020 Approved EUGENE CASSIDY
Green Building Final 10/13/2020 Approved EUGENE CASSIDY
HVAC-Final 10/13/2020 Approved EUGENE CASSIDY
PLUMBING-Final 10/13/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/13/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 10/13/2020 Approved EUGENE CASSIDY
Smoke Detectors 10/13/2020 Approved EUGENE CASSIDY